CAPM Glossary Pt. 1 Flashcards
A planning heuristic for creating the work breakdown structure (WBS). This rule states that the work package in a WBS must take no fewer than 8 hours of labor to create, and no more than 80 hours of labor to create
8/80 rule
The PMI publication that defines widely accepted project management practices. The CAPM and the PMP exams are based on this book.
A Guide to the Project Management Body of Knowledge (PMBOK Guide)
Treating others with conduct that may result in harm, fear, humiliation, manipulation, or exploitation. For example, berating a project team member because he/she has taken longer than expected to complete a project assignment may be considered humiliation.
Abusive manner
The process of accepting a risk because no other action is feasible, or because the risk is deemed to be of small probability, impact, or both, and a formal response is not warranted. This risk response is appropriate for both positive and negative risks but is often used for smaller risks within a project.
Acceptance
The receiver signals that the message has been received. Receipt of the message is shown, but not necessarily agreement with the message.
Acknowledgment
The receiver confirms that the message is being received through feedback, questions, prompts for clarity and other signs of confirmation.
Active listening
The observer interacts with the worker to ask questions and understand each step of the work being completed. In some instances, the observer could serve as an assistant in doing the work
Active observation
Begins with problem definition - the ability to discern between the cause and effect of the problem. Root-cause analysis looks beyond the immediate symptoms to the cause of the symptoms–which then affords opportunities for solutions.
Active problem solving
The primary output of breaking down the WBS packages. Also known as schedule activities.
Activity list
A diagram, such as the project network diagram, that shows the flow of the project work.
Activity network diagram
The actual amount of monies the project has spent to date.
Actual cost (AC)
Life cycles can be either iterative or incremental. Change is highly probably, and the project team will be working closely with the project stakeholders. You might also know this approach as agile or change-driven.
Adaptive life cycle
Once the project is done, either the team moves on to other assignments as a unit, or the project team is disbanded and individual team members go on to other work.
Adjourning
A diagram that breaks down ideas, solutions, causes, and project components and groups them together with other similar ideas and components. When stakeholders create a large number of ideas, you can use this diagram to cluster similar ideas together for further analysis.
Affinity diagram
The identification of more than one solution. Consider roles, materials, tools, and approaches to the project work.
Alternatives analysis
When an issue or claim must be settled before the contract can be closed, the parties involved in the issue or claim will try to reach a settlement through mediation or arbitration rather than litigation.
Alternative dispute resolution
A scope definition process of finding alternative solutions for the project customer while considering the customer’s satisfaction, the cost of the solution, and how the customer may use the product in operations.
Alternatives generation
Risks that have an uncertain, unclear nature, such as new laws or regulations, marketplace conditions, and other risks that are nearly impossible to predict.
Ambiguity risks
A somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be. However, this form of estimating is more reliable than team member recollections. It is also known as top-down estimating and is a form of expert judgment.
Analogous estimating
The area of expertise, industry or function where a project is centered. Examples include architecture, IT, health care, and manufacturing.
Application area
An assumption is something that is believed to be true or false, but has not yet been proven to be true or false. Assumptions that prove wrong can become risks for the project. All identified project assumptions are recorded in this document for testing and analysis.
Assumptions log
Project management team members may have authority over other project team members, may have the ability to make decisions, and perhaps even sign approvals for project work and purchases.
Authority power
A decision method where only one individual makes the decision for the group.
Autocratic
A risk response to avoid the risk.
Avoidance
The project manager refuses to act, get involved, or make decisions.
Avoiding power
An organization where organizational resources are pooled into one project team, but the functional managers and the project managers share the project power.
Balanced matrix structure
Comparing any two similar entities to measure their performance.
Benchmarking
An example of a benefits comparison model. It examines the benefit-to-cost ratio.
Benefit/cost ratio (BCR) model
A document the seller provides to the buyer. An estimate provided by a company when RFP does not contain clear scope or the requirements are not clearly defined. Price is the determining factor in the decision-making process.
Bid
A meeting of all the project’s potential vendors to clarify the contract statement of work and the details of the contracted work.
Bidders conference
An estimating approach that starts from zero, accounts for each component of the WBS and arrives at a sum for the project cost estimate. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs. Produces a definitive estimate.
Bottom-up estimating
A data-gathering technique that is similar to brainstorming, but provides brainstorming meeting participants with the questions and topics for brainstorming before the stakeholder identification meeting.
Brain writing
The most common approach to risk identification; usually completed by a project team with subject matter experts to identify the risks within the project.
Brainstorming
A broad estimate that is used early in the planning processes and also in top-down estimates. The range of variance for this estimate can be from -10 percent to +25 percent.
Budget estimate
Risks that affect the business and that may have negative or positive outcomes. Examples include using a less experienced worker to complete a task, allowing phases or activities to overlap, or forgoing the expense of formal training for on-the-job education.
Business risks
A quantifiable return on investment. The return can be tangible, such as equipment, money or market share. The return can also be intangible, such as brand recognition, trademarks, and reputation.
Business value
A ranking approach to identify the probability and impact by using a numerical value, such as from .01 (very low) to 1.0 (certain).
Cardinal scale
Diagrams that show the relationships between variables within a process and how those relationships may contribute to inadequate quality. The diagrams can help organize both the process and team opinions, as well as generate discussion on finding a solution to ensure quality. An Ishikawa diagram is an example.
Cause-and-effect diagram
A person who has slightly less project management experience than a PMP, but who has qualified for and then passed the CAPM examination.
Certified Associate in Project Management (CAPM)
A committee that evaluates the worthiness of a proposed change and either approves or rejects the proposed change.
Change control board (CCB)
A documented system that communicates the process for controlling changes to the project deliverables. This system works with the configuration management system and seeks to control and document proposals to change the project’s product. Documented in the scope management plan, this system defines how changes to the project scope are managed and controlled.
Change control system (CCS)
A log in which all changes that enter into a project are recorded. The characteristics of the change, such as the time, cost, risk, and scope details, are also recorded.
Change log