CAPM Exam Questions - Chapter 06 - Time Management Flashcards
What is the variance of a project that has a best case estimate of 6, a most likely case estimate of 7, and a worst case estimate of 10? A. 2.08 B. 0.44 C. 0.67 D. 7.33
B
Your project is significantly over budget and behind schedule. It is critical that you determine your projected duration. To gain a better understanding of the project you analyze the sequence of deliverables, activities or tasks to find the ones with the least amount of schedule flexibility. What technique are you using? A. GERT B. CPM C. PERT D. PDM
B
A project manager is discussing her project with her boss. They are concerned that the project might be falling behind schedule and decide they must determine the project’s likely completion date and find out where any flexibility exists. Which of the following tools would best provide this information? A. AOA B. PDM C. CPM D. Network Diagramming
C
You are the project manager for a new product. You are in the planning phase of your project and have just been told by one of your senior resources that they require the completed schematics before they can begin to build the product prototype. This is an example of what kind of dependency? A. Mandatory B. Discretionary C. Internal D. External
A
You are the project manager at a major pharmaceuticals company. You are planning the release of a new drug and must wait for regulatory approval before you can begin manufacture of the drug. This is an example of what kind of dependency? A. Discretionary B. Mandatory C. Internal D. External
D
Which of the following is a type of bar chart? A. Gaussian distribution B. Scatter plot C. Gantt Chart D. Logit model
C
As a general rule, which of the following is better illustrated by network diagrams than by bar charts?
A. Project progress
B. Logical relationships between activities
C. The project’s critical chain
D. Resource needs
B
Which of the following is not correct about PDM?
A. The critical path always has dummy tasks
B. Every network has at least one critical path
C. The network displays all task interdependencies
D. Tasks not on the critical path have slack or float
A
Which of the following terms represents a method of problem solving that relies on inductive reasoning from past experience or expert judgment when there is no relevant mathematical algorithm available? A. A heuristic B. A logit C. GERT D. Analogous estimating
A
Which of the following best describe the amount of time that one activity can be delayed without impacting the early start of its succeeding task or activity? A. Lead time B. Float C. Lag time D. None of the above
C
Which of the following terms best represents the amount of time one activity can begin prior to the completion of its preceding dependent task? A. Lag time B. Lead time C. Float D. None of the above
B
Which of the following statements is correct?
A. A network diagram allows you to determine the amount of time the project will take.
B. A WBS allows you to determine the longest chain of dependent tasks.
C. Changing the end date of the project will cause the network diagram to change.
D. The critical path will always contain dummy tasks.
A
Which of the follow statements about a milestone is true?
A. A milestone can have any duration
B. A milestone has the same duration as the task, activity or deliverable it represents
C. A milestone always has zero duration
D. None of the above
C
Which of the following statements best describes the relationship between standard deviation and risk?
A. Standard deviation provides the level of uncertainty about the estimate
B. Standard deviation defines whether or not safety is in the estimate
C. Standard deviation defines the accuracy of the estimate
D. There is no relationship between risk and standard deviation
A
Your boss asks you to use Monte Carlo Analysis to evaluate your project. For what purpose was this request most likely made?
A. To create an activity’s estimated length
B. To gain an indication of the risk in the project
C. To define the order in which activities occur
D. Define project resource requirement
B
On Monday morning your boss comes into your office and asks about the amount of slack you have on a specific activity in your project. This is determined by which of the following:
A. Performing a PERT analysis
B. Estimating the task or activity length
C. Creating a PDM diagram
D. Determining the total amount of time that a schedule activity may be delayed without impacting the project delivery
D
Your boss enters your office and is concerned that a particular activity will delay the delivery of the project. What is the best thing to do?
A. Determine if the activity is on the critical path
B. Explain why your boss should not worry
C. Perform a GERT analysis
D. Examine the activity’s risk triggers
A
You and your project team have obtained estimates for your project, assigned resources, and developed a Precedence Diagram of the project. Several of your resources are very concerned that two of the activities are not being focused on enough and will end up delaying the project because they are critical components of the project’s end product. What is the best thing to do?
A. Sit down with the resources to discuss the project Gantt Chart
B. Determine if the activities in question are on the Critical Path
C. Examine the project’s Risk Register
D. Evaluate alternative project execution paths
B
Which of the following best describes the impact of multiple Critical Paths on a project?
A. The project takes longer to complete
B. The project is more expensive
C. The project takes more resources to manage
D. The project risk increases
D
You and your project team have just completed the development of your PDM Diagram. The current diagram shows there are three critical paths in your project. What is the best thing to do next?
A. Re-evaluate the network for errors
B. Develop the project schedule
C. Examine the project risk register
D. Discuss alternative networks with your team
B
In discussing your project with management you determine that the project schedule is the most flexible and the project scope is the least flexible. If the allowable monthly project expenditures are fixed, then what is the best thing to do?
A. Level the resources
B. Examine the project’s critical path
C. Analyze the project’s life cycle costs
D. Crash the project
A
Your manager asks you to produce a report on your project for management. Which of the following would best meet the request? A. Bar Chart B. PERT Chart C. Milestone Chart D. Gantt Chart
C
You and your project team have just completed the development of your project schedule. Based on the constraints provided by the project sponsor, the project is scheduled to be completed after the project deadline. Assuming that costs are the least important constraint and scope is the most important constraint, which of the following is the best thing to do?
A. Fast track the project
B. Crash the project
C. Reassess the critical path
D. Develop a critical chain model for the project
B
You and your project team have just completed the development of your project schedule. Based on constraints provided by the project sponsor, the project is scheduled to be completed after the project deadline. Assuming that costs are the most important constraint and scope is the least important constraint, which of the following is the best thing to do? A. Crash the project B. Reassess the critical path C. Develop a new project schedule D. Fast track the project
D
Your manager comes to you and demands that you complete your project three weeks early. What is the best thing to do?
A. Meet with your project team to examine alternatives for crashing and fast tracking
B. Tell your boss the project critical path does not allow for a three week early completion
C. Ask the project to work overtime
D. Ask your manager if you can reduce the scope of the project.
A