CAPM Definitions Flashcards
an overview document to formally authorizes a project or a phase and includes stakeholders, the project objectives, deliverables, and milestones.
document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the PM with the authority to apply organizational resources to project activities
Project Charter
document that primarily focuses on the business rationale, including ROI, benefits, and risks.
Business Case
Document defining, preparing, and coordinating all plan components and consolidating them. outlines the basis of all project work and how it will be perfromed.
Project Management Plan
document that includes detailed deliverables, work requirements, risks, acceptance criteria, and constraints/assumptions/exclusions (Initiating Phase)
Project Scope Statement
a process where you compare the work that has gotten done to the project management plan to see if they line up
Control Scope
a process where stakeholders formally accept the project deliverables
Validate Scope
unauthorized work added to scope
Scope Creep
doing extra work not in the scope
Gold Plating
table created that will link the requirement back to its source and used to help manage changes to the project scope. it tracks the original stakeholder, why the requirement was added, description, and the status of it
Requirements Traceability Matrix
breakdown of work into smaller levels of work that subdivides project deliverables and project work into smaller more manageable components (from info on scope statement)
WBS - work breakdown structure
breaking down each of the project deliverables into smaller components - work packages should be able to estimate time, cost, effort
decomposition
detailed content of WBS that includes time estimate, cost, team member, account info, ect.
WBS dictionary
progressive elaboration - near term work packages are able to be defined in a much greater detail
Rolling Wave Planning
graphical representation of all work needed to perform the project. represents the flow of the project and the work packages relationships to each other -
a visual tool that helps schedule activities in a project plan by creating a network diagram that shows dependencies and critical paths
Precedence Diagramming Method
tangible limitations of work packages that are tied together. One work package must be completed prior to subsequent work package beginning.
They are a fundamental aspect of the work and cannot be changed. These dependencies are based on the physical or logical relationship between tasks and the order in which they must be completed. For example, the installation of a foundation must be completed before building construction can begin. Usually easy to identify because they are based on the nature of the work and the inherent dependencies between tasks.
Mandatory Dependences (Hard Logic or Hard Dependencies)
work packages that are tied together but do not have limitations - work in unison or tandem
Refers to the relationships in project management that are based on best practices, preferences, or expert judgment rather than hard requirements.
They are often flexible and can be adjusted based on the needs and priorities of the project. However, project managers must be careful while considering the potential consequences of changing them.
Discretionary Dependencies (Soft Logic or Preferential Logic)
work package relationship between project and non-project activities that are outside the control of the project team
External Dependencies
work activities within the control of the team
Internal Dependencies
amount of time a successor activity can be advanced with respect to a predecessor activity
Lead
directs the delay in the successor work package or activity
Lag
technique that uses a statistical relationship between historical data, project parameters, other variables to calculate an estimate for activity parameters
Parametric Estimating
relies on historical information to predict estimates (time, budget, difficulty) for current projects. Used when there’s limited info/time. Costs less in time/money but least accuracy in estimating.
Analogous Estimation (Top-Down)
very detailed estimation and takes a while to complete - breaks down the work to the lowest levels then aggregating back up to find and overall duration
Bottom-Up Estimating
(opt + pess + most likely) / 3
program evaluation and review technique - a scheduling tool that uses a weighted average formula to predict the length of activities and the project
Three Point Estimate or Triangle Distribution
(opt + pess + (most likely x 4) / 6
program evaluation and review technique - a scheduling tool that uses a weighted average formula to predict the length of activities and the project
PERT estimation formula or BETA distribution
a method to flatten the schedule when resources are over-allocated or allocated unevenly
Resource Optimization Technique
ensures workers are not overextended on activities - but it might extend the schedule
Resource Leveling
amount of time a task can be delayed without delaying the start of a successor task
Free Float
the amount of time a scheduled activity can be delayed without delaying the overall project completion date.
(name the formula)
Total Float
Formula - TF = Late Finish - Early Finish
cost estimate between -5% and 10%
Definitive
cost estimate between -10% and 25%
Budgeted
cost estimate between -25% and 75%
Rough Order of Magnitude
the process of estimating the total cost of a project by combining the individual cost estimates of its activities, work packages, or deliverables - delivers a high level overview with less accuracy
Cost Aggregation
project’s current run rate vs. what was planned over the life cycle of the project - done when there are limited funds to spend on the project and work may need to be rescheduled
Funding Limit Reconciliations
cost of all the activities - work packages, contingency reserves, control accounts
Cost Baseline
cost baseline + management reserves
Project Budget (Actual Cost)
matrix grid that shows the project resources assigned to each work package - shows which stakeholders are responsible, accountable, consulted, or informed, and are associated with project activities, decisions, and deliverables
Responsibility Assignment Matrix (RACI Chart)
bar chart that visually shows a project’s schedule and progress over time -
activities are listed on the vertical axis, dates shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates
FUCKING CRITICAL PATH
Gantt Chart