How is Planned Value calculated?
Planned value= Planned % of project completed x BAC
If project budget is $50,000 & you should have 40% of it complete after 2 months, then the planned value would be (40% x $50,000) = $20,000
How is Cost Performance Index calculated?
earned value (EV) / actual cost (AC)
What is a RACI chart
Responsibility assignment matrix is a diagram used to define team roles as Responsible, Accountable, Consulted, & Informe
How is contingency cost calculated?
probability x loss
What is a phase gate?
A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a program or project.
A CPI of 1.4 indicates what?
CPI 1 = Neutral
CPI > 1 = Good
CPI < 1 = Negative, overbudget
CPI = cost performance index, relates to cost of project
What is the communication channels formula?
N * (N-1)/2 where N represents number of stakeholders. Stakeholders include project manager.
How is CPI calculated
cost performance index = EV/AC
What is the primary purpose of expected monetary value (EMV)?
To numerically prioritize risk