How is Planned Value calculated?

A

Planned value= Planned % of project completed x BAC
If project budget is $50,000 & you should have 40% of it complete after 2 months, then the planned value would be (40% x $50,000) = $20,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How is Cost Performance Index calculated?

A

earned value (EV) / actual cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a RACI chart

A

Responsibility assignment matrix is a diagram used to define team roles as Responsible, Accountable, Consulted, & Informe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How is contingency cost calculated?

A

probability x loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a phase gate?

A

A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a program or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A CPI of 1.4 indicates what?

A

CPI 1 = Neutral
CPI > 1 = Good
CPI < 1 = Negative, overbudget
CPI = cost performance index, relates to cost of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the communication channels formula?

A

N * (N-1)/2 where N represents number of stakeholders. Stakeholders include project manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is CPI calculated

A

cost performance index = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the primary purpose of expected monetary value (EMV)?

A

To numerically prioritize risk