Capital Investment Decisions Flashcards

1
Q

Four methods of evaluation

A

Accounting rate of return
Payback period
Net present value
Internal rate of return

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Accounting rate of return formula

A

Average annual

Operating profit / av investment to earn that profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

ARR decision rule

A

For a project to be acceptable, it must achieve a target ARR as a minimum

When two or more competing projects exceed the minimum rate, the one with the higher (or highest) ARR should be selected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Payback period

A

The payback period is the length of time it takes for an initial investment to be repaid out the net cash inflows from a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Payback period decision rule

A

For a project to be acceptable, it should have a shorter payback period than the max payback period set by the business

If two or more competing projects have payback periods shorter than the max payback period, the project with the shorter payback period should be selected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

NPV

A

The present value of cash inflows are compared to the pv of cash outflows, the difference is the NPV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

NPV decision rule

A

If the NPV of a project is positive it should be accepted, if negative reject

If two or more competing projects have positive NPV the project with higher NPV should be selected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PV of £1 received in future

A

1/(1+r)^t

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why is NPV superior to ARR and PP

A

Npv fully addresses the timing of cash flows, the whole of the relevant cash flows and the objectives of the business

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Internal rate of return

A

The internal rate of return is the discount rate, which, when applied to the future cash flows of a project, will produce an NPV of precisely zero

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

IRR decision rule

A

For a project to be acceptable, it must meet a minimum irr requirement(opportunity cost of finance)

If two + competing projects exceed the minimum IRR the one with higher IRR should be selected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

IRR Formula

A

IRR = A + (C/(C-D) x (B - A) ) %

Where a = first interest rate
B = second interest rate
C = first NPV
D= second NPV (neg figure)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly