Capacity Shortage Actions Flashcards

1
Q

How many Capacity Shortage Actions are there, and what are they?

A

There are 4 Capacity Shortage Actions:

  1. Maximum Emergency Generation
  2. Emergency Mandatory Load Management Reductions
  3. Voltage Reduction
  4. Manual Load Dump
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of the Maximum Emergency Generation Action?

A

To increase generation above the Maximum Economic Level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the trigger for the Maximum Emergency Generation Action?

A

Real-Time Generation is needed to meet the load demand that is greater than the highest incremental cost level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of the Emergency Mandatory Load Management Reduction Action?

A

To provide additional relief by using PJM Controllable Load Management programs(Relief is expected to be required after initiating Maximum Emergency Generation).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is load curtailment achieved utilizing Emergency Mandatory Load Management Reductions?

A

Long Lead Time: curtailment achieved in 1-2 hours

Short Lead Time: curtailment achieved in 1 hour or less

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of the Voltage Reduction Action?

A

To reduce load to provide a sufficient amount of reserve to maintain tie flow schedules and preserve limited energy resources and/or to increase transmission system voltages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the trigger for the Voltage Reduction Action?

A

Load relief is still needed to maintain ties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of the Manual Load Dump Action?

A

Issued to provide relief when all other possible means o supplying internal load have been exhausted to prevent a catastrophe within PJM or to maintain tie schedules so as not to jeopardize the reliability of other interconnected regions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the trigger for the Manual Load Dump Action?

A

Implemented when PJM cannot provide adequate capacity to meet load or critically overloaded transmission lines or equipment cannot be relieved in an other way and/or low frequency operation occurs with part(s) of the RTO.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly