CA Flashcards
What are the payment terms under the JCT Contract
The contractor can make an application for payment any time up until 7 days before the due date and the Final Date for Payment is 14 days following the due date
What is the standard End of Defects period under the JCT Intermediate contract
3 months unless stated otherwise
What is are the different insurance provisions within a JCT contract?
- 5.4A…
- 5.4B…
- 5.4C…
What is the benefit of a joint insurance policy?
The benefit of a joint names contract to the property owner is that they have control of the insurance and will be notified if the cover is cancelled during the work.
What are Liquidated Damages?
Liquidated damages (“LDs”) are pre-determined sums that become payable upon a breach of contract.
How do you assess Extensions of Time in a JCT Minor Works Contract?
The contract administrator finish
How do you assess Extensions of Time in a JCT Intermediate Contract?
see relevant events section of contract
How do you assess Extensions of Time in a JCT Standard Contract?
Assess the contractor’s reasoning against the the list of Relevant Events under the JCT Standard Building Contract 2016
What is are the differences between relevant matters and relevant events?
A relevant matter entitles the contractor to claim direct loss or expense.
A relevant event entitles the contractor to an extension of time.
What are the effects of practical completion on a contract?
- Possession…
- Insurance…
- Retention…
- Defect period begins…
- No (more) Liquidated Damages
What is the role of the Contract Administrator?
The CA is employed by the client to administer the contract on his behalf as an agent, however he must always act with impartiality and integrity. Duties include formulating the contract, issuing instructions, raising certificates, carrying out site inspections, assessing EOT claims.
What are the differences between an application for payment and a valuation?
What are the payment procedures under the JCT Minor Works Contract?
What are the payment procedures under the JCT Intermediate Contract?
What are the payment procedures under the JCT Standard Contract?
What are the differences between the JCT MWBC and the JCT IC?
IC has Sectional completion.
IC has Early possession.
IC has relevant events.
IC has named subcontractors.
IC has advance payment.
What are the differences between the JCT IC and the JCT SC?
What should you consider when advising on a procurement route?
The client’s budget, level of quality required, time available and willingness to take on risk.
What factors affect procurement choice?
Time, quality and cost are often the main factors. However risk is becoming a major concern. Other considerations include complexity, type of client, specialist input and controllable variation.
What is traditional procurement?
With this approach the client appoints consultants for design, cost control and contract administration. The contractor is responsible for carrying out the works.
What are the advantages and disadvantages of traditional procurement?
Advantages:
• Control of quality
• No built in contractor risk premium
• Client knows lump sum cost
• There is a contractual date for completion
• Change is relatively easy.
Disadvantages:
• Commitment to the lump sum price is often undermined by client changes
• All design risks lie with client
• High pre-contract design fees
• Long design period.
What is design and build procurement?
With this approach the tender documents outlining the employers requirements are prepared by consultants employed by the client. It is the responsibility of the contractor to carry out the design and the work.
What are the advantages and disadvantages of D&B?
Advantages:
• Cost and contract dates are secured early on
• Time can be saved by starting the construction works whilst the design is completed
• All risks lie with the contractor
• Main contractor provides single point of responsibility for design and build.
Disadvantages:
• Project becomes price driven at the expense of quality
• Contractor assumes higher risk and this is reflected in the price
• Changes can be expensive and give rise to EOT
How can the two stage Design & Build procurement route work in practice?
It can significantly reduce the tender period and the some of the design period ran concurrently with the construction period. It also allows you to make use of the expertise of the contractor to highlight buildability issues early on in the process and it gets there buy into the design.
What is management contracting?
A design team prepares project drawings and a specification. A management contractor is selected by a process of tender and interview. His role is literally to manage the execution of the works. The contractors are usually appointed by the MC with all the works to be done undertaken in ‘packages’
What are the advantages and disadvantages of Management Contracting?
Advantages:
• Quick method of procuring a main contractor.
• Flexible as design can extend into the construction period.
• Programme and cost plan agreed by design team.
• The employer can stop the work before proceeding to construction for a fee.
Disadvantages:
• Risk of market inflation if delays.
• The final cost is not known until contract is complete.
• Very close cost control is required.
• Method requires high level of client involvement.
What is construction management?
In this method a construction manager joins the design team early in the project acting as an agent, not a principal. The CM is appointed based on a negotiated fee. The CM’s role is simply to supervise and plan the works. Each work package contractor has a separate contract with the client and is paid directly by the client.
What are the advantages and disadvantages of Construction Management?
Advantages:
• Maximum overlap with design and construction
• Quality can be assured
• Expertise of CM fully utilized.
Disadvantages:
• Client has no commitment from the contractors on overall price
• Client takes all the risk
• Total price not known until well into the programme.