BSOP 330 Entire Course Flashcards
DEVRY BSOP 330 Entire Course Includes DQ’s, Lab Assignments, Quiz And Case Study
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-entire-course
BSOP 330 Week 1 DQ 1
BSOP 330 Week 1 DQ 2
BSOP330 Week 1 Lab Assignment Problems 4.1, 4.5, 4.9 and 4.11, pages 140-141
BSOP 330 Week 2 DQ 1
BSOP 330 Week 2 DQ 2
BSOP330 Week 2 Lab Assignments Chapter Four Problems 4.23, 4.27, 4.33, and 4.35
BSOP330 Week 2 Southwestern Case study
BSOP 330 Week 3 DQ 1
BSOP 330 Week 3 DQ 2
BSOP330 Week 3 Lab Assignments Chapter 13 problems 13.3, 13.5, 13.9, 13.21
BSOP 330 Week 4 DQ 1
BSOP 330 Week 4 DQ 2
BSOP330 Week 4 Lab Assignments Chapter 12, problems 12.1, 12.5, 12.9, 12.15
BSOP330 Week 4 Quiz
BSOP330 Week 4 Southwestern Case study Printing companies Programs and Inserts
BSOP 330 Week 5 DQ 1
BSOP 330 Week 5 DQ 2
BSOP330 Week 5 Homework Problems Mater Production Schedule Problem 1, 2 and 3
BSOP330 Week 5 Quiz
BSOP 330 Week 6 DQ 1
BSOP 330 Week 6 DQ 2
BSOP330 Week 6 Lab Assignments Chapter 14, problem
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Entire Course Includes DQ’s, Lab Assignments, Quiz And Case Study
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-entire-course
DEVRY BSOP 330 Master Planning All Weeks Discussion Questions Check this A+ tutorial guideline at http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-discussion-questions BSOP 330 Week 1 DQ 1 BSOP 330 Week 1 DQ 2 BSOP 330 Week 2 DQ 1 BSOP 330 Week 2 DQ 2 BSOP 330 Week 3 DQ 1 BSOP 330 Week 3 DQ 2 BSOP 330 Week 4 DQ 1 BSOP 330 Week 4 DQ 2 BSOP 330 Week 5 DQ 1 BSOP 330 Week 5 DQ 2 BSOP 330 Week 6 DQ 1 BSOP 330 Week 6 DQ 2 BSOP 330 Week 7 DQ 1 BSOP 330 Week 7 DQ 2 For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Master Planning All Weeks Discussion Questions
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-discussion-questions
DEVRY BSOP 330 Week 1 Lab Assignment Problems 4.1, 4.5, 4.9 and 4.11, pages 140-141
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-1-lab-assignment-problems-4.1-4.5-4.9-and-4.11paes-140-141
Problems: 4.1: The following gives the number of pints of type A blood used at Woodlawn Hospital in the past 6 weeks:
a) Forecast the demand for the week of October 12 using a 3-week moving average.
b) Use a 3-week weighted moving average, with weights of .1, .3, and .6, using .6 for the most recent week. Forecast demand for the week of October 12.
c) Compute the forecast for the week of October 12 using exponential smoothing with a forecast for August 31 of 360 and α = .2.
Problems: 4.5: The Carbondale Hospital is considering the purchase of a new ambulance. The decision will rest partly on the anticipated mileage to be driven next year. The miles driven during the past 5 years are as follows:
Year Mileage
1 3,000
2 4,000
3 3,400
4 3,800
5 3,700
a) Forecast the mileage for next year using a 2-year moving average.
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 1 Lab Assignment Problems 4.1, 4.5, 4.9 and 4.11, pages 140-141
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-1-lab-assignment-problems-4.1-4.5-4.9-and-4.11paes-140-141
DEVRY BSOP 330 Week 2 Lab Assignments Chapter Four Problems 4.23, 4.27, 4.33, and 4.35
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-2-lab-assignments-chapter-four-problems-4.23-4.27-4.33-and-4.35
4.23
a) Compute MAD and MAPE for management’s technique
b) Do management’s results outperform (i.e., have smaller MAD and MAPE than) a naive forecast?
c) Which forecast do you recommend, based on lower forecast error?
4. 33
a) Forecast the number of transistors to be made next year, using linear regression.
b) Compute the mean squared error (MSE) when using linear regression.
c) Compute the mean absolute percent error (MAPE).
4. 35
a) Use the model to predict the selling price of a house that is 1,860 square feet.
b) A 1,860-square-foot house recently sold for $95,000. Explain why this is not what the model predicted.
c) If you were going to use multiple regression to develop such a model, what other quantitative variables might you include?
d) What is the value of the coefficient of determination in this problem?
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 2 Lab Assignments Chapter Four Problems 4.23, 4.27, 4.33, and 4.35
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-2-lab-assignments-chapter-four-problems-4.23-4.27-4.33-and-4.35
DEVRY BSOP 330 Week 2 Southwestern Case study
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-2-southwestern-case-study
1. Develop a forecasting model, justifying its selection over other techniques, and project attendance through 2007.
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 2 Southwestern Case study
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-2-southwestern-case-study
DEVRY BSOP 330 Week 3 Lab Assignments Chapter 13 problems 13.3, 13.5, 13.9, 13.21
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-3-lab-assignments-chapter-13-problems-13.3-13.5-13.9-13.21
Chapter 13 problems 13.3:
The president of Hill Enterprises, Terri Hill, projects the firm’s aggregate demand requirements over the next 8 months as follows:
Her operations manager is considering a new plan, which begins in January with 200 units on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan A.
Plan A: Vary the workforce level to execute a “chase” strategy by producing the quantity demanded in the prior month. The December demand and rate of production are both 1,600 units per month. The cost of hiring additional workers is $5,000 per 100 units. The cost of laying off workers is $7,500 per 100 units. Evaluate this plan.
Chapter 13 problems 13.5:
Hill is now considering plan C. Beginning inventory, stockout costs, and holding costs are provided in Problem 13.3:
a) Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average requirements and allow varying inventory levels.
b) Plot the demand with a graph that also shows average requirements. Conduct your analysis for January through August.
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 3 Lab Assignments Chapter 13 problems 13.3, 13.5, 13.9, 13.21
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-3-lab-assignments-chapter-13-problems-13.3-13.5-13.9-13.21
DEVRY BSOP 330 Week 4 Lab Assignments Chapter 12, problems 12.1, 12.5, 12.9, 12.15
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-4-lab-assignments-chapter-12-problems-12.1-12.5-12.9-12.15
Chapter 12, problems 12.1
L. Houts Plastics is a large manufacturer of injection-molded plastics in North Carolina. An investigation of the company’s manufacturing facility in Charlotte yields the information presented in the table below. How would the plant classify these items according to an ABC classification system?
Chapter 12, problems 12.5 William Beville’s computer training school, in Richmond, stocks workbooks with the following characteristics: Demand ,500 units/year Ordering cost S = $25/order Holding cost H = $4/unit/year
a) Calculate the EOQ for the workbooks.
b) What are the annual holding costs for the workbooks?
c) What are the annual ordering costs?
Chapter 12, problems 12.9
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 4 Lab Assignments Chapter 12, problems 12.1, 12.5, 12.9, 12.15
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-4-lab-assignments-chapter-12-problems-12.1-12.5-12.9-12.15
DEVRY BSOP 330 Week 4 Quiz
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-4-quiz
BSOP 330 Week 4 Quiz
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 4 Quiz
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-4-quiz
DEVRY BSOP 330 Week 4 Southwestern Case study Printing companies Programs and Inserts
Check this A+ tutorial guideline at
http: //www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-4-southwestern-case-study-printing-companies-programs-and-inserts
1. For the programs, what are the EOQ’s for both printing companies? How many orders of each size will be needed?
2. For the inserts, what are the EOQ’s for both printing companies? How many orders of each size will be needed?
3. Using the EOQ’s above and volume order information provided, what will be the cost of the programs and inserts if they are purchased from Quality Printing
4. Using the EOQ’s above and volume order information provided, what will be the cost of the programs and inserts if they are purchased from First Printing.
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 4 Southwestern Case study Printing companies Programs and Inserts
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-4-southwestern-case-study-printing-companies-programs-and-inserts
DEVRY BSOP 330 Week 5 Homework Problems Mater Production Schedule Problem 1, 2 and 3
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-5-homework-problems-mater-production-schedule-problem-1-2-and-3
MASTER PRODUCTION SCHEDULE
MAKE-TO-STOCK
Beginning PAB prior to week number one is 500.
If the forecast is larger than the book orders, complete the MPS using the forecast demand. If the booked orders is larger than the forecast complete the MPS using the booked orders
Lead-time for MPS releases is one week.
All MPS releases must be in lot sizes of 250 units.
Period order coverage is one period.
1. Complete the MPS due line and the MPS released line.
2. Complete the PAB line.
3. Complete the ATP line.
BSOP Master Planning, Week 5 Assignment, Problem Two
Make-to-Stock MPS
GIVENS FOR THE MPS PROBLEM:
1. Beginning on-hand inventory prior to week one is 200 units.
2. If the forecast is larger than the book orders, complete the MPS using the forecast demand. If the booked orders is larger than the forecast complete the MPS using the booked orders
3. Lead-time for MPS planned orders is one week.
4. All MPS releases must be in lot sizes of 200 or multiples of 200.
REQUIRED:
Complete the MPS due and MPS planned lines.
Calculate the new projected on-hand inventory line.
Calculate the ATP line for the entire MPS.
BSOP330 Master Planning, Week 5, Problem 3
Forecast Disaggregation
Product Family Blenders
Model Number
Percent of the Annual Forecast
B-100
10.00%
B-200
7.00%
B-300
25.00%
B-400
30.00&
B-500
12.00%
B-600
16.00%
Total
100.00%
Note: the total percentage must equal exactly 100%.
If the aggregate forecast for the family of blenders for the month of September is 5,000 units, complete the chart below.
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 5 Homework Problems Mater Production Schedule Problem 1, 2 and 3
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-5-homework-problems-mater-production-schedule-problem-1-2-and-3
DEVRY BSOP 330 Week 5 Quiz
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-5-quiz
1.Question :(TCO 9, 10, & 12) The MPS
Student Answer:
must sum up to the total in the production plan.
can have any quantity necessary to meet customer demand.
is only used in make-to-stock manufacturing.
does not have to be tested for capacity limits.
2.Question :(TCO 12) In an assemble-to-order MPS, the items stocked in inventory are
Student Answer:
finished goods.
component parts.
raw materials.
sub-assemblies.
3.Question :(TCOs 9, 11, & 12) Which one of the following pieces of information would be more useful to the order entry department in a make-to-stock company?
Student Answer:
The planned order receipt file
The planned MPS released quantity file
The available to promise file
The balance of the forecast quantity
4.Question :(TCO 12) A forecast
Student Answer:
is always 100 percent correct.
will get better and better the more time and money you spend.
is a time prediction of the future based on the past.
is a monthly project that marketing loves to do.
5.Question :(TCO 10 & 12) In job shop (make-to-order) operations, the master production schedule is usually expressed in
Student Answer:
end items.
modules.
kits.
customer orders.
warehouse orders.
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 5 Quiz
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-5-quiz
DEVRY BSOP 330 Week 6 Lab Assignments Chapter 14, Problems 14.1, 14.3, 14.9, 14.13
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-6-lab-assignments-chapter-14-problems-14.1-14.3-14.9-14.13
You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.)
Chapter 14, problems 14.3
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
a) Construct a product structure. Identify all levels, parents, and components.
b) b) Prepare a time-phased product structure.
Chapter 14, problems 14.9
As the production planner for Gerry Cook Products, Inc., you have been given a bill of material for a bracket that is made up of a base, two springs, and four clamps. The base is assembled from one clamp and two housings. Each clamp has one handle and one casting. Each housing has two bearings and one shaft. There is no inventory on hand.
Your boss at Gerry Cook Products, Inc., has just provided you with the schedule and lead times for the bracket in Problem 14.8. The unit is to be prepared in week 10. The lead times for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (1 week), casting (3 weeks), bearing (1 week), and shaft (1 week). a) Prepare the time-phased product structure for the bracket. b) In what week do you need to start the castings?
Chapter 14, problems 14.13
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 6 Lab Assignments Chapter 14, Problems 14.1, 14.3, 14.9, 14.13
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-6-lab-assignments-chapter-14-problems-14.1-14.3-14.9-14.13
DEVRY BSOP 330 Week 7 Case Study Final
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-7-case-study-final
Question 1. Which variations in demand for police services should be considered in an aggregate plan for resources? Which variations can be accomplished with short-term scheduling adjustments?
Question 2. Evaluate the current staffing plan. What does it cost? Are 26 officers sufficient to handle the normal workload?
Question 3: Determine the cost of the Chiefs plan. Do you need to implement the Chief’s plan or can the current staff handle the load? Explain your thinking
Question 4: From the data in the case, determine the schools current cost to provide police services during football games.
Question 5: There isn’t any one right answer for this question. This a critical thinking question. Based on what you have read and the scheduling and costs you put together, what do you see as alternatives for the manning the schedule.
For more classes visit
www.bsop330entirecourse.com
DEVRY BSOP 330 Week 7 Case Study Final
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-7-case-study-final
DEVRY BSOP 330 Week 7 Lab Assignments Chapter 16, Problems 16.1, 16.3, 16.5, and 16.9
Check this A+ tutorial guideline at
http://www.edu644entirecourse.com/bsop-330-devry/bsop-330-week-7-lab-assignments-chapter-16,-problems-16.1-16.3,-16.5-and-16.9
Chapter 16, problems 16.1, 16.3, 16.5, and 16.9 (pages 640-641)
16.1 Leblanc Electronics, Inc., in Nashville, produces short runs of custom airwave scanners for the defense industry. You have been asked by the owner, Larry Leblanc, to reduce inventory by introducing a kanban system. After several hours of analysis, you develop the following data for scanner connectors used in one work cell. How many kanbans do you need for this connector?
Daily demand 1,000 connectors
Lead time 2 days
Safety stock day
Kanban size 500 connectors
16.3
Chris Millikan Manufacturing, Inc., is moving to kan-bans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.
16.5
Discount-Mart, a major East Coast retailer, wants to determine the economic order quantity (see Chapter 12 for EOQ formulas) for its halogen lamps. It currently buys all halogen lamps from Specialty Lighting Manufacturers, in Atlanta. Annual demand is 2,000 lamps, ordering cost per order is $30, annual carrying cost per lamp is $12.
a) What is the EOQ?
b) What are the total annual costs of holding and ordering (managing) this inventory?
c) How many orders should Discount-Mart place with Specialty Lighting per year?
For more classes visit
www.edu644entirecourse.com
DEVRY BSOP 330 Week 7 Lab Assignments Chapter 16, Problems 16.1, 16.3, 16.5, and 16.9
Check this A+ tutorial guideline at
http://www.edu644entirecourse.com/bsop-330-devry/bsop-330-week-7-lab-assignments-chapter-16,-problems-16.1-16.3,-16.5-and-16.9
DEVRY BSOP 330 Week 7 Quiz
Check this A+ tutorial guideline at
http://www.bsop330entirecourse.com/bsop-330-devry/bsop-330-week-7-quiz
1. (TCOs 5 & 12) Manufacturing cycle time is best defined as the (Points : 4)
length of the work shift, expressed in minutes per day.
time it takes a unit to move from one workstation to the next.
time between the start of one unit and the start of the next unit.
sum of all the task times to make one unit of a product.
time from raw materials receipt to finished product exit.
2. (TCOs 5 & 12) The implementation of JIT offers several advantages, including (Points : 4)
reduced throughput.
increase in variability to better respond to variable demand.
decreased profit margins.
support for lean production.
increased work in process inventory.
3. (TCOs 5 & 12) Which of the following statements regarding JIT in services is true? (Points : 4)
Restaurants do not use JIT layouts because they interfere with the creation of a good servicescape.
Excess customer demand in services such as air travel is met by dipping into safety stocks.
All of the JIT techniques for dealing with suppliers, layout, inventory, and scheduling are used in services.
Scheduling is not relevant to the effective use of JIT in services.
All of the above are false.
4. (TCO 12) Which of the following is the author of the phrase, “Inventory is evil”? (Points : 4)
Poka Yoke
Pat “Keiretsu” Morita
Kanban Polka