Breach of Contract and Remedies Flashcards
Material Breach
(Common Law)
i.e., when the nonbreaching party does not receive the substantial benefit of its bargain.
Minor Breach
(Common Law)
i.e., the breaching party has substantially performed
Breach
(UCC)
The seller generally must strictly perform all obligations. The doctrine of material breach only applies in installment contracts or it the parties so provide.
Repudiation of promise
(Anticipatory Repudiation)
The repudiation must be clear and unequivocal (as opposed to mere insecurity), may be by conduct or words, and, if a statement, must be made to the promisee or a third-party beneficiary or assignee of the promise.
Nonbreaching party’s options
(Anticipatory Repudiation)
The promisee can generally treat the repudiation as a breach and sue the promisor immediately or ignore it and demand performance.
Nonbreaching party’s options
(when the date of performance has not passed plus full performance)
The promisee must wait until the promisor’s performance is due before filing suit.
(Typically occurs when the remaining obligation is the payment of money)
Retraction of repudiation
May be retracted until such time as the promisee (i) acts in reliance on the repudiation, (ii) signifies acceptance of the repudiation, or (iii) commences an action for breach. Notice of the retraction must be sufficient enough to allow for the performance of the promisee’s obligations.
Unilateral Contracts
(Anticipatory Repudation)
The doctrine of anticipatory repudiation does not apply to a unilateral contract when the offeror withdraws the offer once the offeree has begun to perform since offeree is not required to complete her performance.
Prospective Inability to Perform
A party can demand assurance of performance if there are reasonable grounds for insecurity about the other party’s ability or willingness to perform.
Expectation Damages
(in general)
Intended to put the nonbreaching party in the same position as if the contract had been performed. Must be calculated with reasonable certainty.
Expectation Damages
(Partial performance)
A partially performing party can generally recover for work performed, plus expectation damages for the work not yet performed.
Expectation Damages
(Economic waste)
In a construction contract, if the award of damages based on the cost to fix or complete the construction would result in economic waste, then a court may award damages equal to the diminution in the market price of the property caused by the breach.
UCC–Breach of warranty damages
The difference at the time and place of acceptance between the value of the goods accepted and the value they would have had if they had been as warranted.
Direct Damages
Are the necessary and usual result of the defendant’s wrongful act.
Consequential Damages
Result naturally from the breach, but need not be the usual result of the breaching party’s conduct. Instead, they need only be a reasonably foreseeable result of the breach in the partie’s specific circumstances. They must be proven with reasonable certainty.
Consequential Damages
(UCC)
Neither consequential nor special damages can be recovered under the UCC unless specifically provided by a UCC provision or by another rule of law.
Incidental Damages
May be awarded to the nonbreaching party as compensation for commercially reasonable expenses incurred as a result of the other party’s breach.
Liquidated Damages
(Enforeceability)
Two-prong test:
(i) The amount of liquidated damages was reasonable, bearing some relation to the damages that might be sustained; and
(ii) Actual damages were uncertain in amount and would be difficult to prove.