Breach, Damages and Equitable Remedies Flashcards
State and Explain the 3 key forms of breach of contract
- Actual Breach
- Repudiatory breach
- Anticipatory breach
Actual breach is where the breach occurs on the due date for performance.
Repudiatory breach is a breach of contract that gives the aggrieved party the right to choose either to end the contract or to affirm it. In either case, the aggrieved party may also claim damages. A breach of condition is normally repudiatory, as is breach of an intermediate term that deprives the other party of substantially the whole benefit of the contract.
Anticipatory breach occurs where, before the due date for performance, a party shows an intention not to perform his contractual obligations. It is referred to as renunciation. (This may be expressed or implied)
Express anticipatory breach occurs where one of the parties declares, before the due date for performance, that they have no intention of carrying out their contractual obligations.
Implied anticipatory breach occurs where one of the parties does something which makes subsequent performance of their contractual undertaking impossible.
What are the effects of an anticipatory breach?
An anticipatory breach does not automatically bring the contract to an end.
The innocent party has two options:
- Treat the contract as discharged and bring an action for damages immediately, without waiting for the contractual date of performance as in Hochster v De La Tour (1853)
or
- Elect to treat the contract as still valid, complete his side of the bargain and then sue for payment by the other side.
Aside from exceptions like White & Carter (Councils) v McGregor (1961) There is an element of danger in not accepting the repudiation of the contract when it first becomes apparent.
For example, where the innocent party elects to wait for the time of performance, he takes the risk of the contract being discharged for some other reason and thus of losing his right to sue on the basis of the breach of contract.
What are the effects of a Repudiatory breach?
The innocent party is at liberty to bring the contract to an end following a breach of condition, serious breach of a innominate term or a repudiation but is not obliged to do so.
However in practice the innocent party may have little option but to terminate the contract.
If the innocent party does not wish to terminate the contract, he is said to ‘reject’ the other party’s repudiatory breach, but this does not mean that he is waiving it entirely, in the sense of treating it as if it were not a breach for all purposes, because he may still claim damages.
In contrast, if the innocent party decides to terminate the contract, he is said to ‘accept’ the other party’s repudiatory breach.
So the two key options are either the innocent party;
- Elects to ‘reject the breach’ and keep the contract alive
or
- Elect to ‘accept the breach’ and discharge the contract
Generally, acceptance of a repudiation discharges the whole contract—in other words, all the outstanding primary obligations.
Explain the aim of damages for breach of contract and cite the relevant authority
The aim of damages is to put the non-breaching party in the position they would have been in had the contract been performed as agreed (Robinson v Harman (1848).
In order to calculate damages we need to know the extent of the loss which results from the breach.
Explain the two categories of Damages for breach
There are two different types of damages:
- Compensatory damages/Actual damages
- Non-compensatory damages
Explain the key types of damages that may be awarded for breach of contract:
Key types of damages that may be awarded for breach of contract:
- Compensatory Damages (i.e. loss of expectation, profits etc)
- Liquidated Damages
and Non-compensatory damages including: - Nominal Damages
Nominal damages are awarded where a legal wrong has been committed but no consequential loss has been caused. The purpose of the award is vindicatory – to mark the existence of the right in question and to mark the fact of its violation by the wrongdoer.
- Restitutionary Damages
Restitutionary Damages which aim to strip from a wrongdoer gains made by committing a wrong or breaching a contract. The benefit gained by the wrongdoer may exceed the detriment or loss to the person wronged.
Explain the two different ways that the damages for breach can be measured
There are two different ways in which this can be measured:
- Expectation measure
- Reliance measure
Expectation measure involves a comparison between the claimant’s current position, and the position they would have been in had the contract been performed correctly.
The first important rule of the expectation measure is that it is calculated on the expectation that the breaching party would have performed their obligations under the contract, but no more and no less (Lavarack v Woods of Colchester Ltd [1966]
The second key rule is cost of cure.
Cost of cure: This method involves determining the cost required to remedy the breach of contract or to restore the injured party to the position they would have been in if the contract had been adequately performed. It typically involves assessing the cost of completing or rectifying the performance of the contract.
Reliance measure:
The reliance measure aims to put the claimant back in the position he was before the contract was made. This is relevant for where one of the parties has incurred expenditure in preparing for their side of the bargain. At this point you need to remember that only one measure of damages can be relied on, expectation or reliance.
This principle was confirmed as fundamental in Golden Strait Corporation v Nippon Yusen Kubishika Kaisha, The Golden Victory [2007]
State and Explain the key things that someone can claim damages for and what they can NOT claim damages for
What can a party claim damages for?
The claimant CAN claim for:
- loss of finances i.e. profits (pecuniary losses)
- losses for injury suffered as a consequence of the breach (which usually leads to pecuniary losses i.e. not being able to work and earn money)
- Loss of expectation etc.
- Wasted expenditure
The claimant CANNOT generally claim for:
- Non-pecuniary losses are generally not recoverable in a claim for breach of contract.
A claimant cannot recover more than its actual loss, and if the claimant suffers no loss, the claimant will be constrained to recovering only nominal damages.
The justification for this rule is that the courts are unwilling to put the parties in a better position that they would have been in had the contract been properly performed.
Wasted expenditure
Whilst someone can generally claim for wasted expenditure The claimant cannot claim damages for wasted expenditure if this would amount to compensating the claimant for having made a ‘bad bargain’.
Explain the exeption to the general principle that Non-pecuniary losses are generally not recoverable in a claim for breach of contract.
Non-pecuniary losses are generally not recoverable in a claim for breach of contract.
However, in some circumstances, a modest sum may be awarded for the disappointment suffered as a result of not receiving the promised performance. Thus things like mental distress, disappointment and mental distress are typically not able to be compensated for - Addis & Gramophone Co. Ltd (1909)
However there are exceptions to this general rule where we have a contract whereby the main purpose of aim of that contract is to have a good time or aid someone in having a good experience i.e. holidays, weddings, haircuts - they can qualify as a proper contract for the award of damages for mental distress.
There are some cases where the law regards it as appropriate to make non pecuniary loss i.e. for disappointment and this type of award is most evidently depicted in Jarvis v Swans Tours Ltd (1973).
Explain the concept of ‘performance interest’ and why it is relevant when claiming damages
The ‘performance interest’ or contractual expectation is based on identifying and assessing the value of certain ‘benefits’ that the claimant expected to receive under the contract.
These benefits may not be limited to an expectation of financial benefits, but can include anticipated subjective benefits (known as ‘the consumer surplus’)
Damages for breach of contract should give effect to this ‘performance interest’ by awarding damages to compensate for:
- the loss of the expected financial benefit; and
- the loss of ‘subjective benefits’ (the consumer surplus) or preferences that are considered to be part of the contractual expectation - Ruxley Electronics v Forsyth and Farley v Skinner
Explain damages for loss of expectation
Expectation loss will normally be compensated on the basis of the difference in value measure, i.e. the difference in value between the promised performance and the actual performance.
The measurement of expectation loss may be a speculative and uncertain process, especially in cases in which it must be assessed by reference to difference in value and in which the assumed value of the market price is unavailable as a guide.
Nevertheless, as a general principle, damages for lost expectation may always be recovered, subject to the various limitations considered - Watts v Morrow [1991] 1 WLR 1421. Thus, the court will attempt to put some value on an expectation even when what is lost is no more than an opportunity to take the risk of making a profit, rather than a certain loss of a speculative profit.
State the definition of Liquidated Damages
A Liquidated damages clause allows contracting parties to agree in advance the amount of damages that should be paid if a particular contractual obligation is subsequently breached. It is a contractual provision which sets such an amount of damages.
This type of clause is enforceable providing it does not exceed a genuine attempt to estimate in advance the loss which the claimant would be likely to surfer form the breach of the obligation in question - Chitty on contracts
Explain the distinction between Liquidated Damages/ a liquidated damages clause vs Unliquidated damages
The contractual provision which is contained within a contract sets out such an amount of damages that would be paid in the event of a breach - so its expressly incorporated within the contract.
In contrast Unliquidated damages are damages that the court work out and award based on various factors because there is no stipulated amount set out in the contrast for if breach occurs.
Explain and state the criteria necessary for a Liquidated Damages Clause to be Valid and Enforceable
For a liquidated damages clause to be enforceable it must be;
- Genuine Pre-Estimate of Loss:
The sum stipulated must represent a genuine attempt to estimate in advance the loss likely to be suffered in the event of a breach. It should not be extravagant or unconscionable in amount in comparison with the highest conceivable loss that could follow from the breach.
- Intention to Compensate:
The primary intent behind the clause must be to compensate the injured party, rather than to deter the other party from breaching the contract or to punish them for a breach.
(it must be proportionate and certainty must be present)
- Not a Penalty:
English law distinguishes between liquidated damages and penalty clauses. A penalty clause is not enforceable because it is punitive in nature. The test for whether a clause is a penalty was traditionally whether the sum stipulated for was extravagant and unconscionable in comparison with the greatest loss that could conceivably be proved to have followed from the breach
- Compliance with Legislation:
The clause must comply with any relevant statutory requirements, such as those set out in the Unfair Contract Terms Act 1977, which may render an excessively harsh liquidated damages clause unenforceable.
A liquidated damages clause will not be enforceable if a court determines that it amounts to a penalty. If a clause is deemed to be a penalty, the non-breaching party will not be able to recover the specified sum and will instead have to prove their actual loss and seek unliquidated damages.
The criteria for whether a damages clause amounts to a penalty is stipulated in Dunlop Pneumatic Tyre Co v New Garage and Motor Co (1915).
A clause is presumed to be a penalty clause if:
- the stipulated sum is extravagant in comparison with the maximum loss that could be incurred
- the same sum is payable in respect of one or more breaches, both trifling and serious
- the sum stipulated is larger than the amount which would actually be payable if the contract were performed.
Explain the criteria the court uses in assessing a claim for unliquidated damages
There are two factors to consider in determining the amount of unliquidated damages:
- remoteness of loss (i.e. what losses can be claimed for?) and
- measure of damages (i.e. how much are those losses worth?)