Breach and Remedies Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What is discharge of contract and how does a contract discharge?

A

Ways a contract can end

Usually, a contract discharges because both parties have done what they agreed in the contract, if they haven’t done what they agreed this may be discharge by brief. However not all contracts that have been breached will be discharged

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Discharge by performance:

A

It is a strict rule, performance must be complete and exact. as seen in Cutter v Powell

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cutter v Powell (1795)

A

The claimant’s husband agreed by contract to act as a second mate on the ship the ‘Governor Parry’ on a return voyage to Jamaica. The voyage was to take eight weeks and he was to be paid on completion. A term in the contract stated:

“Ten days after the ship ‘Governor Parry,’ myself master, arrives at Liverpool, I promise to pay to Mr. T. Cutter the sum of thirty guineas, provided he proceeds, continues and does his duty as second mate in the said ship from hence to the port of Liverpool. Kingston, July 31st, 1793.”

Six weeks into the voyage the claimant’s husband died. The claimant sought to claim a sum to represent the six weeks work undertaken.

Held: The wife’s action failed. Payment was on condition that he worked the ship to Liverpool, since he did not fulfil this condition the widow was entitled to nothing.

Strict rule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Re Moore & Co Ltd (1921)

A

The number of tins in each carton was incorrect and so the goods did not correspond with the description of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Harshness : what ways can discharge by performance be utilized

A
  • Divisible contracts
  • Substantial performance
  • Prevention of full performance
  • Acceptance of part performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Divisible contracts:

A

If the contract has separate parts to it, then non completion of one part will not be breach of the whole contract

Case authority: Ritchie v Atkinson

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Ritchie v Atkinson (1808)

A

Divisible contract

By contract the claimant agreed to carry a cargo of specified quantity of hemp and iron. The price agreed was £5 per ton for the hemp and 5 shillings per ton of iron. The claimant only carried part of the agreed quantity. The defendant argued the contract had not been fully performed and therefore no payment was due.

Held:

The contract could be divided into separate parts as the parties had agreed a price per ton. The claimant was thus entitled to payment for the amount carried although the defendant was entitled to damages for non performance in relation to the amount not carried.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Substantial performance: subjective

A

If the party has substantially done what was required under the contract, then the doctrine of substantial performance may apply, the payment will be appropriate to the work done
This is only applicable to divisible contracts, not contracts where the entire agreement is a single transaction
Dakin and co v Lee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Dakin and co v Lee

A

The claimant builders contracted to perform some renovation work for the defendant at the defendant’s home. The price was to be paid on completion of the work. The defendant refused to pay the agreed price, arguing that the work had not been completed. Though the project was finished, the claimant had used materials which did not match the contractual specifications. They had also failed to properly cleat and join a set of joists over a window.

Issue(s)
Was the defendant bound to pay the price?
Decision
The Court of Appeal held in favour of the claimant. The work was substantially completed and the defendant had enjoyed the benefit of the contract. The fact that not all contract terms had been complied with did not prevent the obligation to pay from becoming live.

This Case is Authority For…
Some contracts have ‘entire contract’ obligations, which normally mean that one party is not obligated to pay until the other party has fully performed. However, the obligation to pay will still become live if the other party has ‘substantially’ performed the relevant work. This is likely the case if the only outstanding obligations are minor.

This ‘substantial performance’ principle does not apply if 1) the other party refuses to finish the work, 2) the work is of no benefit, or 3) the work is something completely different than what the parties contracted for.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Hoenig v Isaacs (1952)

A

The claimant agreed to decorate and furnish the defendant’s flat for £750 payable by two instalments and the balance on completion. The claimant completed the work but the defendant was unsatisfied some of the furnishings and refused to pay the all the final instalment. The cost of the defects in the furniture came to £56.

Held:

The claimant had substantially performed the contract and was therefore entitled to the contractually agreed price minus the cost of the defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Bolton v Mahadeva

A

The claimant installed central heating in the defendant’s home. The agreed contract price was £560. The defendant was not happy with the work and refused to pay. Defects in the work amounted to £174. The action by the claimant to enforce the payment failed since the court held there was no substantial performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Quantum Merit - Young v Thomas Properties Ltd

A

the courts will award as ‘much as its worth’
Young - contractor was contracted to resurface a car park, overall did his job but some small defects, the contractor was entitled to the contract less the savings he had made from buying less expensive materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Prevention of full performance

A

If one party prevents the other from carrying out their end of the contract, then the innocent party can still claim to be paid on quantum merit basis.
Planche v Colburn = The claimant agreed to write a book on costume and armour for the defendant as part of a series called ‘the Juvenile Library’. The agreed contract price was £100 to be payable on completion. The claimant commenced writing and had completed a great deal of it when the defendant cancelled the series. The defendant refused to pay the claimant despite his undertaking and the fact that the claimant was still willing to complete. The claimant brought an action to enforce payment.

Held:

The claimant was entitled to recover £50 because the defendant had prevented the performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Acceptance of part payment:

A

If one party agrees that the other party does not need to complete the entire contract, then it must be paid on a quantum merit basis
The other party has to consent to the part payment
If the innocent party has no choice but to take the benefit of the work done, this is not considered consent to part payment
Sumpter v Hedges

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Sumpter v Hedges

A

The claimant agreed to build two houses and stables for the defendant. It was agreed that £565 would be payable on completion. The claimant commenced performance and then ran out of money and was unable to complete. He had performed just over half of the contract. The defendant completed the work himself. The claimant sought to recover £333 representing the value of the work he had completed. He argued that in completing the work himself, the defendant had thereby accepted partial performance and prevented the claimant from completing the contract.

Held:

The claimant’s action failed. The court held that the defendant had no choice but to accept partial performance as he was left with a half completed house on his land.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Timing

A

Many contracts have a term in relation to time inserted into it, the courts will regard time as a condition if:
1) the parties have expressly stated in the contract that time is a critical aspect
2) in the circumstances time for completion is critical
3) one party has failed to perform on time and the other has insisted on a new date for completion of the term

If none of these apply, time will be seen as a warranty and not a term

Charles Rickards v Oppenheim: would cancel delivery if not there on time, was not there on time and he rejected it. He was entitled to this as time had been made of the essence

17
Q

Time and the consumer rights act 2015

A

s52 states that if the contract does not expressly state a time for the act then it must be completed within a reasonable time, if they are in breach of this, the consumer will have rights to a price reduction and can end the contract

18
Q

Types of terms: a condition

A

A condition is a term in a contract that is so important that a failure to perform the obligation would destroy the main purpose of the contract, if a contract is broken the person suffering the failure is entitled to end the contract.
This is repudiation (ending a contract)
Repudiation can only be used for a breach of condition not a breach of warranty
Poussard v Spiers and Pond

19
Q

Poussard v Spiers and Pond

A

Madame Poussard entered a contract to perform as an opera singer for three months. She became ill five days before the opening night and was not able to perform the first four nights. Spiers then replaced her with another opera singer.

Held:

Madame Poussard was in breach of condition and Spiers were entitled to end the contract. She missed the opening night which was the most important performance as all the critics and publicity would be based on this night.

20
Q

Warranty

A

a warranty is a minor term in a contract breach of which does not end the contract but allows a claim for damages only, if a warranty is breached, the main purpose of the contract can continue to be performed despite the breach.
No right to repudiate if there is a breach of warranty
Bettini v Gye

21
Q

Bettini v Gye (1876)

A

Bettini agreed by contract to perform as an opera singer for a three month period. He became ill and missed 6 days of rehearsals. The employer sacked him and replaced him with another opera singer.

Held:

Bettini was in breach of warranty and therefore the employer was not entitled to end the contract. Missing the rehearsals did not go to the root of the contract.

22
Q

Inominate term

A

This is a term in a contract that is not regarded as a condition or warranty and is decided based on the severity of the breach - decides if it is viewed as a warranty or condition
Hong Kong Fir Shipping v Kawasaki Kisen Kaisha

23
Q

Hong Kong Fir Shipping v Kawasaki Kisen Kaisha

A

ship was chartered to the defendants for a 2 year period. The agreement included a term that the ship would be seaworthy throughout the period of hire. The problems developed with the engine of the ship and the engine crew were incompetent. Consequently the ship was out of service for a 5 week period and then a further 15 week period. The defendants treated this as a breach of condition and ended the contract. The claimants brought an action for wrongful repudiation arguing the term relating to seaworthiness was not a condition of the contract.

Held:

The defendants were liable for wrongful repudiation. The court introduced the innominate term approach. Rather than seeking to classify the term itself as a condition or warranty, the court should look to the effect of the breach and ask if the breach has substantially deprived the innocent party of the whole benefit of the contract. Only where this is answered affirmatively is it to be a breach of condition. 20 weeks out of a 2 year contract period did not substantially deprive the defendants of whole benefit and therefore they were not entitled to repudiate the contract.

24
Q

Discharge by breach:

A

If a contract is not discharged through performance then it may be that one party has failed to perform their obligations, or both parties. The party that is considered the victim will be entitled to the damages
However just because there has been a breach does not mean that a contract will be terminated.
depends on if it is a breach of condition
Breach can either be of the entire contract or part performance

25
Q

Circumstances for breach:

A

1) one party gives up their responsibilities under it e.g not paying a bill on the due date
2) impossibility to perform their end of the contract due to their own act eg. closing a hairdressers businesses for holidays with appointments during that time
3) total or partial failure of performance - e.g. delivering defective goods

26
Q

Repudiatory breach:

A

A repudiatory breach is a serious violation of contract terms that undermines the core purpose of the agreement, indicating the unwillingness or inability of one party to fulfill their obligations.
This type of breach can happen in three ways:
1) a breach of condition
2) a refusal to perform the contract
3) a sufficiently serious breach of an innominate term i.e. a breach that would be considered a breach of condition

27
Q

Anticipatory breach:

A

One party gives advanced notice that that they will not be performing the contract
- the innocent party then has a choice
1) sue imm. for breach of a condition
2) wait for the time agreed for the performance and sue if performance does not take place

28
Q

Hochster v de la Tour

A

The claimant agreed to be a courier for the defendant for 3 months starting on 1st June 1852. On the 11th May the defendant wrote to the claimant stating he no longer wanted his services and refused to pay compensation. The claimant obtained a service contract elsewhere but this was not to start until 4th July. The claimant brought an action on 22nd May for breach of contract. The defendant argued that there was no breach of contract on 22nd May as the contract was not due to start until 1st of June.

Held:

Where one party communicates their intention not to perform the contract, the innocent party need not wait until the breach has occurred before bringing their claim. They may sue immediately or they can choose to continue with the contract and wait for the breach to occur.

29
Q

Actual breach

A

Where the breach occurs at the time or during the course of performance

30
Q

Remedies for breach

A

if they claim anticipatory breach, then the victim may claim damages immediately, this will put them in the same position as before the contract was completed.
Victim can repudiate the contract, if it is a breach of conditions then the victim can claim for damages and or repudiation