BOP/ESS Electrical Flashcards

1
Q

What is the design capacity of Transformer TR-12-EP-1?

A

Designed to handle an accident in one unit with Containment Spray with Blackout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why are the EP breakers to T-bus interlocked to prevent closure unless all other feed breakers to that bus are open?

A

EP is 30° out of phase with other grid connections through reserve power and unit auxiliaries

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the maximum loading per unit due to the temperature limitation on the aluminum feeder cables?

A

600 amps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the voltage SDG output breaker trip coil?

A

48 VDC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the voltage SDG output breaker closing coil?

A

230 VAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When will 11BCMC automatically close?

A

For a fault located on either TR11BMC or on TR11CMC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When will 11BCMC not automatically close?

A

For a fault located on either bus (11BMC or 11CMC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is regarded as the RUN bus?

A

The RUN bus is the supply source

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is regarded as the START bus?

A

The START bus is the bus that will be “started” or connected to the power source

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When would you pull open knife switches to prevent automatic closure of the reserve feed breaker?

A

-When a standing close signal from fast transfer exists and you want to control when the breaker closes
OR
-Conditions in which anti-pumping circuit is energized without breaker closure and conditions now allow breaker to be closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How must the EP Feed Breaker to a T bus be closed to supply power from EP which can be supplied from either the 69kV grid or the SDGs ?

A

Manually to a dead bus because EP is 30° out of phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why should a T bus power source transfer to/from EP always be a dead bus transfer?

A

Because EP is 30° out of phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What do you have to do with both power sources lost to U1 Main Transformer cooling?

A
  • Power is reduced to 50% using the RAPID POWER REDUCTION procedure.
  • If cooling cannot be restored within 2 hours, TRIP the Reactor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If winding temperature Hi-Hi is received accompanying loss of cooling on U1 Main Transformer, what must you do?

A

Trip the Reactor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What do you have to do with both power sources lost to U2 Main Transformer cooling?

A

Restore one group immediately or Trip Reactor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the backup power supply to the RAT?

A

Step down transformer upstream of RAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How do you reset the Anti-Pumping Circuit?

A

Take the control switch to trip/reset

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Which power supply provides power to TCSN?

A

11/21C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Which power supply provides power to TCSE?

A

11/21D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Which bus feeds U1 Main Transformer Group 1 Coolers?

A

TCSN - Norm

TCSE - Backup

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Which bus feeds U1 Main Transformer Group 2 Coolers?

A

TCSE - Norm

TCSN - Backup

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Which bus feeds U2 Main Transformer Group 1 Coolers?

A

TCSN - Norm

TCSE - Backup

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Which bus feeds U1 Main Transformer Group 2 Coolers?

A

TCSE - Norm

TCSN - Backup

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Both SDGs are sized to support?

A

Sized to power one unit/one train of vital equipment needed to ensure RCS inventory control following a Station Blackout.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

SDGs power which RCS Makeup loads?

A
CCP
NESW pump
ESW pump 
CCW pump 
MDAFW pump
Ctrl Air Compressor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is the SDG auto start sequence on a loss of EP?

A
  • Senses the undervoltage on the 69kV EP bus, waits 150 seconds.
  • Sends the open signal to the MDS.
  • Verifies the MDS is open, and then sends the start signal to the SDGs
  • 1st SDG to reach speed and voltage (25 secs) closes its breaker (12-52-SDGS-2 or 12-52-SDGS-3) onto the dead bus.
  • The remaining SDG auto synchronizes to the bus and closes its output breaker.
  • PowerLynx then closes the tie breaker (12-52-SDGS-4) to the station EP bus.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is meant by QUALIFIED?

A
  • Each offsite circuit must be capable of maintaining rated frequency and voltage and accepting the required loads during an accident.
  • A qualified offsite circuit consists of all breakers, transformers, switches, interrupting devices, cabling and controls required to transmit power from the offsite transmission network to the onsite class 1E emergency buses
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Which Tech Spec states if you have 1 required offsite circuit inoperable, that you must preform SR 3.8.1.1 for required operable offsite circuit within 1 Hr?

A

T.S. 3.8.1 Condition A (AC Sources - Operating)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What does TS 3.8.1 B state? (AC Sources - Operating)

A

If you have 1 required EDG inop,
WITHIN 1 hr:
- Verify both SDGs are available and perform the lineup SR 3.8.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What does TS 3.8.1 H state? (AC Sources - Operating)

A

If you have 3 or more required AC sources inop,
IMMEDIATELY:
- Enter L.C.O. 3.0.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Load Shed is sensed on which buses and at what voltage is it caused by in both units?

A

T11/21A, T11/21B, T11/21C, T11/21D. And it has to sense 94V on Unit 1, and 93V on Unit 2 for 2 sec on 2/3 sensors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What buses is degraded bus voltage sensed on?

A

T11/21A and T11/21D. 2/3 sensors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What will happen if your T11A Bus is at 113v for 8 sec?

A

Nothing yet, At 9 seconds, an alarm will come in for degraded bus voltage

34
Q

What will happen if your T11D Bus is at 113v for 99 sec?

A

It will cause a fast bus transfer to associated RAT

35
Q

What will happen if you T11A Bus is at 113v for 120 sec?

A

It will trip the A and B RCP Bus x-tie bkrs and cause a load shed. AB EDG will start and load to the T11A and T11B bus and ESF equip will sequence on

36
Q

Which transformer normally provides power to the AB RAT?

A

Transformer 5

37
Q

Which transformer normally provides power to the CD RAT?

A

Transformer 9

38
Q

Which offsite power source must you close in manually and why?

A

EP, because EP is 30° out of phase

39
Q

How long is the wait for the fast bus transfer to RAT if you have a generator trip?

A

Instant

40
Q

How long is the wait for the fast bus transfer to RAT if you have a Turbine trip?

A

30 Sec

41
Q

How long is the wait for the fast bus transfer to RAT if you have a Reactor trip?

A

30 Sec

42
Q

If an overcurrent is sensed on TR11B, what happens first?

A

It trips the low side breaker (11B11)

43
Q

If an overcurrent is sensed on TR11B, what happens after the low side breaker trips and the fault is still sensed on TR11B after 30 cycles?

A

The HEA will activate causing a open signal to go to the RCP Bus tie bkr (T11B1), EP supply bkr (T11B2), and AB EDG supply bkr (T11B4). and if in modes 5 and 6 with 11BD (crosstie) racked in it will close due to a close signal to cross tie B and D 600V buses, An alarm will come in as well in CR

44
Q

If an overcurrent is sensed on TR11A, what happens after the low side breaker trips and the fault is still sensed on TR11A after 30 cycles?

A

Sends an open signal to the low side and high side bkrs, and the close signal to the 11AC crosstie bkr. An alarm will come in as well in CR

45
Q

At what temp does the first group of cooling on the UAT auto start?

A

70° C

46
Q

At what temp does the second group of cooling on the UAT auto start?

A

75° C

47
Q

At what temp does the first group of cooling on the RAT auto start?

A

80° C

48
Q

At what temp does the second group of cooling on the RAT auto start?

A

85° C

49
Q

What temp does the Main Transformer stby cooling group auto start?

A

70° C

50
Q

If the normal power source is lost to the Main Transfer cooling group, at what temp will the standby cooling group start?

A

75° C

51
Q

What bus is power for bus AFWX in Unit 1 fed from?

A

11D via ABD-D

52
Q

What bus is power for bus AFW in Unit 1 fed from?

A

11C via ABD-C

53
Q

What bus is power for bus ELSC in Unit 1 fed from?

A

11B via ABD-B

54
Q

What bus is power for bus ELSCX in Unit 1 fed from?

A

11A via ABD-A

55
Q

What bus is power for bus ELSCX in Unit 2 fed from?

A

21B via ABD-B

56
Q

What bus is power for bus ELSC in Unit 2 fed from?

A

21B via ABD-B

57
Q

What bus is power for bus AFW in Unit 2 fed from?

A

21C via ABD-C

58
Q

What bus is power for bus AFWX in Unit 2 fed from?

A

21C via ABD-C

59
Q

What does T.S. 3.8.9 E state? (Distribution Systems - Operating)

A

If required Train N 250 VDC electrical power distribution subsystem inoperable
IMMEDIATELY:
Declare Turbine Driven Aux Feed N-Train inoperable

60
Q

What does T.S. 3.8.9 F state? (Distribution Systems - Operating)

A

If one or more required Unit 2 electrical distribution subsystems inoperable
IMMEDIATELY:
Declare associated ESW train(s) inoperable

61
Q

What does T.S. 3.8.9 G state? (Distribution systems - Operating)

A

If two or more electrical power distribution subsystems inoperable that result in a loss of safety function IMMEDIATELY:
Enter L.C.O. 3.0.3

62
Q

What does T.S. 3.8.10 A state? (Distribution Systems - Shutdown)

A

If one or more required AC, DC, or 120 VAC vital bus electrical power distribution subsystems inoperable, IMMEDIATELY:
- Declare associated supported required feature(s) inoperable
OR
- Suspend core alterations, suspend fuel movement activities, do not reduce SDM or Boron concentration, initiate action to restore to operable, and declare RHR subsystems inop

63
Q

What does T.S. 3.8.2 A state? (AC Sources - Shutdown)?

A

If required offsite circuit is inoperable,
IMMEDIATELY:
- Declare associated supported required feature(s) inoperable
- Suspend core alterations, suspend fuel movement activities, do not reduce SDM or Boron concentration, initiate action to restore to operable

64
Q

What does T.S. 3.8.2 B state? (AC Sources - Shutdown)?

A

If required EDG is inoperable,
IMMEDIATELY:
- Declare associated supported required feature(s) inoperable
- Suspend core alterations, suspend fuel movement activities, do not reduce SDM or Boron concentration, initiate action to restore to operable

65
Q

What does Load Conservation do?

A
  1. Trips and locks out selected non-essential vital bus loads (only trips 600 V loads)
  2. Prevents restarting any stripped loads until either the 75 second load conservation timer times out or SI is reset after the 60 second SI timer times out.
  3. Trips NESW pump
66
Q

What will give you a Load Conservation?

A
  1. LOOP with a SI
  2. LOOP with a CTS Actuation
  3. SI followed by a Load Shed
  4. CTS followed by a Load Shed
67
Q

What is a Load Shed?

A

Under Voltage 2/3 Phases on ANY T-Bus 94 (U2 93) V ind 2 sec

68
Q

What happens on a Load Shed?

A

Trips RCP X-Tie Bkrs and trips Load Shed loads, Starts EDG and sequences loads on.

69
Q

What switch [CR & Yard] configuration must you have to be able to close Generator Output Breakers?

A

Control Switch in Yard and in CR must be in close to be able to close breaker.

70
Q

Where do the Generator Output Breakers get their Control Power from?

A

Powered from 125VDC Yard power

71
Q

Where do SDG and EP bkrs get their control power from?

A

48V DC

72
Q

What powers the SDG output breaker closure?

A

230V AC from SDG output

73
Q

Which ONE of the following correctly identifies the response to a differential (HEA) fault condition on Transformer TR21BMC?

A

Transformer TR21BMC high-side and low-side breakers trip, then the bus 21BMC and bus 21CMC crosstie breaker closes.

74
Q

What is the design capacity of both Supplemental Diesels?

A

Sized to power one unit/one train of vital equipment needed to ensure RCS inventory control following a Station Blackout.

75
Q

Describe the design capacity of EP?

A

EP is designed to handle a Concurrent Blackout in both Units with a CTS in one of those two Units

76
Q

The Supplemental Diesel Generators (SDGs) are used to provide power to?

A

a CCP, CCW pump and ESW pump in a SINGLE unit to maintain the core covered during a Station Blackout

77
Q

RAT cooling comes from?

A

11/21 D

78
Q

Unit 2 is in MODE 3 with the Unit 2 East ESW crosstied to Unit 1. The Unit 2 West ESW crosstie is closed. Which TBUS breakers are required to be operable?

A

T21A, T21B, T21C, T21D and T11A

79
Q

The UNIT Differential (HEA) is powered by train?

A

Train B (AB buses)

80
Q

33VED is powered by which train?

A

33VED powered by Train A (CD)

81
Q

OVERALL Differential (HEA) is powered by?

A

Switchyard Cabinet