BOP/ESS Electrical Flashcards
What is the design capacity of Transformer TR-12-EP-1?
Designed to handle an accident in one unit with Containment Spray with Blackout
Why are the EP breakers to T-bus interlocked to prevent closure unless all other feed breakers to that bus are open?
EP is 30° out of phase with other grid connections through reserve power and unit auxiliaries
What is the maximum loading per unit due to the temperature limitation on the aluminum feeder cables?
600 amps
What is the voltage SDG output breaker trip coil?
48 VDC
What is the voltage SDG output breaker closing coil?
230 VAC
When will 11BCMC automatically close?
For a fault located on either TR11BMC or on TR11CMC
When will 11BCMC not automatically close?
For a fault located on either bus (11BMC or 11CMC)
What is regarded as the RUN bus?
The RUN bus is the supply source
What is regarded as the START bus?
The START bus is the bus that will be “started” or connected to the power source
When would you pull open knife switches to prevent automatic closure of the reserve feed breaker?
-When a standing close signal from fast transfer exists and you want to control when the breaker closes
OR
-Conditions in which anti-pumping circuit is energized without breaker closure and conditions now allow breaker to be closed
How must the EP Feed Breaker to a T bus be closed to supply power from EP which can be supplied from either the 69kV grid or the SDGs ?
Manually to a dead bus because EP is 30° out of phase
Why should a T bus power source transfer to/from EP always be a dead bus transfer?
Because EP is 30° out of phase
What do you have to do with both power sources lost to U1 Main Transformer cooling?
- Power is reduced to 50% using the RAPID POWER REDUCTION procedure.
- If cooling cannot be restored within 2 hours, TRIP the Reactor.
If winding temperature Hi-Hi is received accompanying loss of cooling on U1 Main Transformer, what must you do?
Trip the Reactor.
What do you have to do with both power sources lost to U2 Main Transformer cooling?
Restore one group immediately or Trip Reactor
What is the backup power supply to the RAT?
Step down transformer upstream of RAT
How do you reset the Anti-Pumping Circuit?
Take the control switch to trip/reset
Which power supply provides power to TCSN?
11/21C
Which power supply provides power to TCSE?
11/21D
Which bus feeds U1 Main Transformer Group 1 Coolers?
TCSN - Norm
TCSE - Backup
Which bus feeds U1 Main Transformer Group 2 Coolers?
TCSE - Norm
TCSN - Backup
Which bus feeds U2 Main Transformer Group 1 Coolers?
TCSN - Norm
TCSE - Backup
Which bus feeds U1 Main Transformer Group 2 Coolers?
TCSE - Norm
TCSN - Backup
Both SDGs are sized to support?
Sized to power one unit/one train of vital equipment needed to ensure RCS inventory control following a Station Blackout.
SDGs power which RCS Makeup loads?
CCP NESW pump ESW pump CCW pump MDAFW pump Ctrl Air Compressor
What is the SDG auto start sequence on a loss of EP?
- Senses the undervoltage on the 69kV EP bus, waits 150 seconds.
- Sends the open signal to the MDS.
- Verifies the MDS is open, and then sends the start signal to the SDGs
- 1st SDG to reach speed and voltage (25 secs) closes its breaker (12-52-SDGS-2 or 12-52-SDGS-3) onto the dead bus.
- The remaining SDG auto synchronizes to the bus and closes its output breaker.
- PowerLynx then closes the tie breaker (12-52-SDGS-4) to the station EP bus.
What is meant by QUALIFIED?
- Each offsite circuit must be capable of maintaining rated frequency and voltage and accepting the required loads during an accident.
- A qualified offsite circuit consists of all breakers, transformers, switches, interrupting devices, cabling and controls required to transmit power from the offsite transmission network to the onsite class 1E emergency buses
Which Tech Spec states if you have 1 required offsite circuit inoperable, that you must preform SR 3.8.1.1 for required operable offsite circuit within 1 Hr?
T.S. 3.8.1 Condition A (AC Sources - Operating)
What does TS 3.8.1 B state? (AC Sources - Operating)
If you have 1 required EDG inop,
WITHIN 1 hr:
- Verify both SDGs are available and perform the lineup SR 3.8.1.1
What does TS 3.8.1 H state? (AC Sources - Operating)
If you have 3 or more required AC sources inop,
IMMEDIATELY:
- Enter L.C.O. 3.0.3
Load Shed is sensed on which buses and at what voltage is it caused by in both units?
T11/21A, T11/21B, T11/21C, T11/21D. And it has to sense 94V on Unit 1, and 93V on Unit 2 for 2 sec on 2/3 sensors
What buses is degraded bus voltage sensed on?
T11/21A and T11/21D. 2/3 sensors