BLRS 6026 - Routine Boiler Maintenance & Inspection (Chp 12) Flashcards
Before welders are allowed to weld on a boiler they must have a:
A) Performance qualification card
B) Certificate of qualification
C) Welding test conducted
D) Certificate of qualification and a performance qualification card
E) Certain minimum number of years experience
D) Certificate of qualification and a performance qualification card
If there is a possibility of freezing, the best method for layup is the:
A) CO2 method B) Glycol method C) Wet method D) Dry method E) Nitrogen cap method
D) Dry method
The wet method of boiler storage requires the boiler to be:
A) Scale free B) Filled with distilled water C) Completely filled with water to exclude air D) Boiled out E) Chemically cleaned
C) Completely filled with water to exclude air
Leaks in steam, water and fuel connections:
A) Can be ignored until the next shut down B) Are not an operation issue C) Only need to be contained D) Are not important E) Can cause damage due to wire drawing
E) Can cause damage due to wire drawing
The purpose of an alkaline boil out of a boiler is to:
A) Remove bicarbonate scale B) Remove silica scale C) Neutralize ash deposits D) Neutralize acidic materials E) Remove grease, oil or other contaminants
E) Remove grease, oil or other contaminants
A hydrostatic test consists of filling the boiler:
A) Completely full and pressurizing it with air
B) To operating level and pressurizing it with a pump
C) Operating level and pressurizing it with nitrogen
D) Completely full of water and pressurizing it with a pump
E) ½ full and pressurizing it with air
D) Completely ‘‘full of water’’ and ‘‘pressurizing it with a pump’’
One of the legal responsibilities of the engineer during an inspection is:
A) To notify the Worker’s Compensation Board of the inspection
B) To be in possession of an inspection certificate
C) To allow the inspector onto the premises, but only during normal working hours
D) To have at least two staff members present at all times
E) Point out any known or suspected defects to the inspector
C) To allow the inspector onto the premises, but only during normal working hours
A failed firetube may be detected by:
A) Water dripping from front or rear boiler door seals
B) Water vapour coming from the flue gas outlet
C) A hissing sound at the rear of the boiler
D) All of the above
E) Water visible through the rear sight glass
D) All of the above
The black light method of crack detection uses fluorescent:
A) Cameras B) Isotopes C) Paint D) Lights E) Penetrant
E) Penetrant
A hydrostatic test is carried out at:
A) 2 times the MAWP B) MAWP (Maximum Allowable Working Pressure) of the boiler C) 3 times the MAWP D) ½ times the MAWP E) 1 ½ times the MAWP
E) 1 ½ times the MAWP
A very important job during an internal inspection in regard to safety is:
A) Looking for evidence of damage
B) Producing a tagging system to account for valves, circuit breakers and other devices operated or removed from service to ensure the safety of the job
C) Servicing combustion equipment
D) Looking for evidence of scale
E) Ensuring that all equipment is in good operating condition
B) Producing a tagging system to account for valves, circuit breakers and other devices operated or removed from service to ensure the safety of the job
The most common acid for boiler cleaning is:
A) Hydrochloric B) Nitric C) Chelate D) Sulphuric E) Phosphoric
A) Hydrochloric
A tagged valve, damper circuit breaker or other device shall not be operated until the tag is:
A) Authorized to be removed by telephone or radio
B) Removed by the chief engineer
C) Removed by the owner
D) Authorized to be removed by the plant manager
E) Removed by the person directly in charge of the job
E) Removed by the person directly in charge of the job
During a hydrostatic test:
A) Safety valves must be removed and blanked off
B) All of the above
C) Air must be completely removed from the boiler
D) Water temperature should be at ambient temperature
E) All instruments and fittings not rated for 1 ½ times MAWP must be removed or isolated
B) All of the above
A boiler inspection:
A) Is done with the owner’s permission only
B) Must be done when the boiler inspector requests it
C) Must be done every two years
D) Must be done after every shut down of the boiler
E) Must be done before the boiler is ready for start up
B) Must be done when the boiler inspector requests it