Black Spectacles Cards Flashcards

1
Q

What is a benefit of having your construction documents follow the “4 Cs”? (Clear, complete, concise, and correct)

A

Well-prepared construction drawings provide the contractor with the necessary information to build, which typically results in fewer CHANGE ORDERS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When creating a hybrid fee structure for a project, what is the ideal structure for each phase of the project if trying to appease both Owner and Architect?

A

SD - Hourly (because it will encourage the owner to be decisive)

DD & CD - Fixed Fee (Shows the architect will be efficient)

CA - Hourly (Because its is difficult for the arch to predict construction changes)

% of Const Cost - bad for the arch because true const costs are hard to assess

GMP & Lump Sum - same as fixed fee, but typically applied to contractor fees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Designer professionals should use which strategy when designing buildings in order to comply with building codes such as the International Building Code?

A

Review local modifications to the model codes!

Codes are frequently revised and sections can be modified, added, or eliminated. Large cities in particular will often rewrite sections of building codes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does a firm’s completion of a schematic design help the firm prepare for the next project?

A

The opportunity to REVIEW INTERNAL PROCESSES is a benefit of the schematic design phase, because it facilitates a collaborative, firm-wide approach to setting design goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is the best time for project costs to be controlled?

A

At the beginning of the project when determining scope, quality, and the project delivery method

(The project’s biggest decisions are made at the beginning and the rest follow)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The speed at which fire extends along the surface of a material is a measure of which term?

A

Flame Spread Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What indicates the amount of smoke given off when a tested material is burned?

A

Smoke Developed Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What indicates how much heat energy a material will add to a fire when burned?

A

Fuel Contributed Rating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is ASTM?

A

The American Society for Testing and Materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who typically owns the instruments of service such as CD’s, models, built structures, and other design representations?

A

ARCHITECT and CONSULTANTS - Architects and their consultants shall be deemed the authors and owners of their respective instruments of service, including drawings and specifications. The owner is granted a nonexclusive license to use the instruments of service for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a construction manager doing during a Construction Manager as Constructor (CMc) project?

A

A CMc advises on constructability and cost estimates during the design of a project, and then shifts to the responsibilities of building according to the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a construction manager doing during a Construction Manager as Agent (CMa) project?

A

A CMa is brought on board early during a project to advise the owner on constructability aspects, and can stay further into the project to coordinate construction for a fixed price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a construction manager doing during a Construction Manager at Risk (CMAR) project?

A

CMAR is a delivery method where the construction manager (CM) commits to complete the project within a guaranteed maximum price (GMP), which is based on the construction documents and specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a construction manager doing during a Construction Manager as Advisor (CM-Advisor) project?

A

A CM-Advisor provides advice on constructability and cost estimation but does not construct buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which project delivery method is best for fast-tracked projects?

A

The construction manager delivery system works well for fast-tracked projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is included in the architect’s cost-of-the-work estimates?

A

All costs for the construction of the work itself, including the contractor’s construction cost, overhead, and profit

17
Q

What part of a B101 contract does liability insurance fall under?

A

8 - Claims and Disputes!

18
Q

According to B101, which dates does the owner provide to the architect?

A
  • Start of Construction

- Date of Substantial Completion

19
Q

Who is usually responsible for testing of the work on site when questioned?

A

The Contractor (in A201)

20
Q

What is a critical path?

A

The longest path in a project flow chart. This sets the construction schedule.

21
Q

Why is Design-Bid-Build required to have such detailed drawings?

A

Because of the bidding process. Contractors need to know exactly what they are building so that they can price things accurately.

22
Q

What is as-of-right use in zoning?

A

When a use for a site is allowed by the zoning laws without any modification.

23
Q

Who determines when the project has been substantially completed?

A

The Architect

24
Q

Who enforces ADA?

A

The Department of Justice

25
Q

What is the procurement phase?

A

Bidding for construction materials and methods