ASBESTOS Flashcards

1
Q

What are the 3 types of Asbestos?

A
  1. Chrysotile
  2. Amosite
  3. Crocidolite
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is the duty holder under the CAR 2012?

A

Either the owner of the premises if vacant or the tenant if they are occupying under a repairing lease.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the TWO main types of asbestos survey?

A
  1. Management Survey – to locate and assess, and advise on its management during occupation and use of the premises. No sampling of materials or
  2. Refurbishment and Demolition (R&D) Survey – Required where a premises is being refurbished or demolished. Samples and materials are taken and analysed, and management recommendations are made.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Are you aware of any guidance for working with asbestos?

A

Asbestos Essentials are HSE Publications which guidance to comply with the Control of Asbestos Regulations 2012.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What was the process of removing the asbestos cement debris discovered on site?

A

The debris was removed in accordance with Asbestos essentials A11 (removing asbestos debris)

Preparation
- Ensure safe access
- Ensure appropriate PPE is worn
Procedure
- Dampen AC with spray
- Gather/ scoop AC debris into Asbestos waste bag.
- Clean contaminated surfaces with damp rags and adhesive tape and dispose in asbestos waste bag, tape close.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was the process for removal of the cracked sheets?

A

If the existing asbestos sheets were to be drilled into they would be in accordance with Asbestos Essentials A9 (Drilling holes in asbestos cement (ac).

Preparation

  • Ensure safe access
  • Restrict access
  • Ensure appropriate PPE is worn

Procedure

  • Protect surfaces from contamination with taped 500 gauge polyethene sheet.
  • Tape up the drilling points to prevent crumbling and use a gel to control fibres
  • Use a class H Vacuum to control fibres
  • Remove all preparation equipment and dispose as asbestos waste
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Were the asbestos debris removal works at Unit 15 Abbey Road notifiable to the HSE?

A

Yes they were Notifiable, Non Licensed Works.

The Asbestos contractor notified the HSE of the NNLW with asbestos prior to undertaking the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When should the HSE be notified for asbestos works?

A

When the works are either licensed or Notifiable Non-Licensed Works (NNLW). If the licensable work then the HSE must be notified at least 14 days before the works start on site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly