AS Decision - 8: Critical Path Analysis Flashcards

1
Q

What does a dummy show (2)

A
  • a dummy activity shows dependencies between activities
  • each activity must be uniquely represented in terms of its events
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Total Float Time

A

Latest Finish Time - Duration - Earliest Start Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The lower bound for the number of workers required to complete a project within the critical time

A

the smallest integer greater than or equal to: (sum of all activity times)/(critical time of project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly