AS Decision - 8: Critical Path Analysis Flashcards
1
Q
What does a dummy show (2)
A
- a dummy activity shows dependencies between activities
- each activity must be uniquely represented in terms of its events
2
Q
Total Float Time
A
Latest Finish Time - Duration - Earliest Start Time
3
Q
The lower bound for the number of workers required to complete a project within the critical time
A
the smallest integer greater than or equal to: (sum of all activity times)/(critical time of project)