APV Flashcards
What does APV stand for?
Adjusted Present Value
When is it appropriate to use APV to evaluate a project financed with new debt?
When the capital structure changes significantly, and thus WACC is no longer appropriate.
APV Step 1:
Calculate a base case value (NPV) of a project using the Keu as a discount factor (cost of equity for an ungeared company).
Keu formula?
Rf + Beta * (Rm - Rf)
APV Step 2:
Find the present value of the tax shield
Present value of tax shield formula?
£ Debt x Int % x Tax % x Annuity factor
APV Step 3:
APV = NPV + PV Tax Savings - Issue costs
What is the following question asking for you to do?
What appraisal methodology should be used if the project is financed entirely by debt?
Calculate the Adjusted Present Value
When is APV Relevant
When the capital structure (D/E) is expected to change