AOCs Flashcards
1
Q
Who must be notified if outlet pressure exceeds MAOP?
A
Gas Control
2
Q
Who must be consulted to see if a system shut down is possible?
A
System Analysis
3
Q
If you have any questions or concerns about the integrity of the system, who must be contacted?
A
Engineering , System Analysis
4
Q
If a system can’t be shut down, what must be used?
A
Regulator bypass
- Monitor upstream and downstream pressures
- Use a recorder as a second means of monitoring
- Check set points on the monitor and controller
5
Q
What must be done before placing any regulator back in service?
A
Lockup and function test