All Words Flashcards
What is “Acceptance Criteria”?
A set of conditions that are met before deliverables are accepted by the customers or sponsors.
What is “Activity”?
A distinct, scheduled portion of work performed during the project. Usually stored on the activity list.
What is “Actual Cost (AC)”?
The actual cost incurred for the work performed on an activity during a specific time period.
What is “Analogous Estimating”?
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Also known as top-down estimating.
What is “assumption”?
A factor in the planning processes considered to be true or real without proof or demonstration.
What is a “backward pass”?
A critical path method technique for computing the late start and late finish dates by working backward through the schedule model from the project end date.
What is “baseline”?
The accepted version of a work product which can be changed using formal change control processes and is used as the basis for comparison to actual results.
What is “bottom-up estimating”?
A method of estimating project duration or cost by aggregating the estimates for the lower-level components of the “work breakdown structure (WBS)”?
What is “change control”?
A process whereby changes to documents, deliverables, or baselines related to the project are identified, documented, approved, or rejected.
What is a “change control board”?
A formally commissioned group responsible for reviewing, assessing, approving, deferring, or rejecting changes to the project, and for recording and communicating such decisions.
What is a “change control system”?
A set of procedures that defines how modifications to the project deliverables and documentation are managed and controlled.
What is a “change report”?
A formal proposal to change any document, deliverable, or baseline in the project management plan.
What is a “communication management plan”?
A component of the project management plan that describes how, when, and by whom information will be administered and distributed.
What is a “configuration management system”?
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
What is a “constraint”?
A restrictive feature that affects the execution of a project.
What is a “contingency reserve”?
Time or money assigned in the schedule or cost baseline for known risks with response strategies.
What is a “corrective action”?
A planned activity that restores the performance of the project work with the project management plan.
What is a “cost baseline”?
The approved version of work packages cost estimates and contingency reserve that can be changed using formal change control procedures.
What is a “cost management plan”?
A component of a project management plan that defines how costs will be planned and controlled.
What is the “cost performance index (CPI)”?
A measure of the cost efficiency of budgeted resources is expressed as the ratio of earned value and the actual cost.
What is “cost variance (CV)”?
The amount of budget shortfall or surplus at a given point in time, which is expressed as a difference between the earned value and the actual cost.
What is “crashing”?
A schedule compression technique used to shorten the schedule duration by adding resources. This will generally increase the cost of the project.
What is the “critical chain method”?
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources.
What is the “critical path”?
The sequence of activities that represents the longest path through a project, which determines the shortest and longest possible duration. Activities on the critical path have no float.
What is “critical path activity”?
Any activity on the critical path in a project schedule.
What is the “critical path method”?
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule.
What is “decomposition”?
A technique used for dividing and subdividing the project deliverables into smaller, more manageable parts. Also used to subdivide the project activities.
What is “defect repair”?
An intentional activity to modify a nonconforming product or product component.
What is “deliverable”?
A part of the product that is presented to the customer or stakeholders for acceptance.
What is “duration”?
The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks.
What is the “early finish date”?
The earliest an activity can finish without delaying the project end date.
What is the “early start date”?
The earliest an activity can start without delaying the project end date.
What is the “earned value (EV)”?
The amount of money worth of work actually accomplished on the project.
What is “earned value management”?
A methodology that combines scope, schedule, and resource measurements to assess project performance.
What is “estimate at completion (EAC)”?
The forecast of the total cost of the project at the end is based on the current spending rate of the project.
What is “estimate to complete (ETC)”?
The amount of money that will be needed to complete the current project is based on the current performance.
What is “fast-tracking”?
A schedule compression technique in which activities or phases are done in parallel for at least a portion, of the project, or the entire donation. This can increase the risk of the project.
What is “finish-to-finish”?
A relationship in which a successor activity cannot finish until a predecessor activity has finished.
What is “finish-to-start”?
A relationship in which a successor activity cannot start until a predecessor activity has finished.
What is a “forward pass”?
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule.
What is a “functional organization”?
An organizational structure in which staff is grouped by area of specialization and the project manager has limited authority.
What is a “Gantt chart”?
A bar chart of schedule information where activities are listed. Generally part of the project schedule.
What is “lag”?
The amount of time whereby a successor activity will be delayed to a predecessor activity.
What is a “late finish date”?
The latest activity can finish without delaying the project’s end date.
What is a “late start date”?
The latest activity can start without delaying the project’s end date.
What is “lead”?
The amount of time where a successor activity can be started before the predecessor activity finishes.
What are “lessons learned”?
The data gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.
What is a “logical relationship”?
It is a dependency between two activities.
What is a “matrix organization”?
An organizational structure in which the project manager shares authority with the functional manager.
What is the “management reserve”?
The time or money that management puts aside in addition to the schedule or cost baseline and issues for unforeseen work that is within the scope of the project. This is not under the control of the project manager and will need an approved change request to access it.
What is a “milestone”?
A significant point or event in a project.
What is a “milestone schedule”?
A type of schedule that presents milestones with planned dates.
What is the “most likely duration”?
An estimate of the most probable activity duration that takes into account all of the known variables.
What is the “network path”?
A sequence of activities linked by logical relationships in a project schedule network diagram.
What is “opportunity”?
A risk that would have a positive effect on one or more project objectives.
What is “optimistic duration”?
An estimate of the shortest activity duration that takes into account all of the known variables.
What is “organizational process assets”?
Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization.