All Formulas Flashcards
Future Value of Money (FV)
PV (1 + i)n
Present Value of Money (PV)
FV / (1 + i)n
Net Present Value (NPV)
PV-(All Costs)
>1 is good
Internal Rate of Return (IRR)
> 0 is good
Always pick the highest IRR
Three-point-estimating: Triangular Distribution
(O + M + P) / 3
Three-point-estimating: PERT/BETA
(O + 4M + P) / 6
Cost Variance (CV)
EV - AC
Cost Performance Index (CPI)
EV / AC
Schedule Variance (SV)
EV - PV
Schedule Performance Index
EV / PV
Estimate to Complete (ETC)
EAC - AC
To Complete Performance Index (BAC Focused)
(BAC-EV) / (BAC-AC)
To Complete Performance Index (EAC Focused)
(BAC-EV) / (EAC-AC)
Estimate at Completion (EAC), when performance will continue as it has been
BAC / CPI
Estimate at Completion (EAC), when performance will go back to original planned rate
AC + BAC - EV