All Formulas Flashcards

1
Q

Future Value of Money (FV)

A

PV (1 + i)n

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Present Value of Money (PV)

A

FV / (1 + i)n

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Net Present Value (NPV)

A

PV-(All Costs)

>1 is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Internal Rate of Return (IRR)

A

> 0 is good

Always pick the highest IRR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Three-point-estimating: Triangular Distribution

A

(O + M + P) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Three-point-estimating: PERT/BETA

A

(O + 4M + P) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Variance (CV)

A

EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index (CPI)

A

EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Variance (SV)

A

EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Schedule Performance Index

A

EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate to Complete (ETC)

A

EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To Complete Performance Index (BAC Focused)

A

(BAC-EV) / (BAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

To Complete Performance Index (EAC Focused)

A

(BAC-EV) / (EAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate at Completion (EAC), when performance will continue as it has been

A

BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Estimate at Completion (EAC), when performance will go back to original planned rate

A

AC + BAC - EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Estimate at Completion (EAC), when the initial plan is no longer accurate

A

AC + (Bottom-up ETC)

17
Q

Estimate at Completion (EAC), when future performance will be influenced by both CPI and SPI

A

AC + [(BAC-EV) / (CPIxSPI)]

18
Q

Benefit-Cost Ratio (BCR)

A

Benefits (in terms of PV) / Costs (in terms of PV)

>1 is good

19
Q

Variance at Completion

A

BAC - EAC

20
Q

Communication Channels

A

N (N-1) / 2