All Flashcards

1
Q

Three essential drivers that must be achieved to generate positive characteristics in project teams

A

Cohesiveness, Trust, Motivation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The five stages Dr. Bruce Tuckman (1965) introduced of group development

A

Forming, Storming, Norming, Performing, Adjorning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Forming

A

In this stage, team members may be meeting for the first time. Often, no one really knows much about anyone else on the team. It may be premature to refer to this group of individuals as a team. It is a time of introduction and forming relationships and understanding from exchange of information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Storming

A

Team members are beginning to know about each other, but they do not yet understand how to work together. Members may “jockey for position” within the team. The dynamics of working together beyond any written statement of “roles and responsibilities” are being established. Personalities surface, showing the strengths, weaknesses, and personal needs of each individual on the team. Integration into a team may come with some struggle and conflict.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Norming

A

Team members have “figured out” how they will interact with each other. Working relationships are beginning to form. Trust and understanding is beginning to form between team members. They are beginning to feel comfortable working together and openly and willingly sharing information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Performing

A

Team members are fully comfortable working together. Trust has been developed. Working relationships have jelled. Work is being conducted and project progress is occurring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Adjourning

A

This only occurs when all the team’s work has been completed and the team is no longer required. This may occur at any time in the project life cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Co-located Teams

A

involves team members physically working at the same location or holding project meetings together in a common setup.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Virtual Teams

A

are teams whose members interact primarily through electronic communications. Members of a virtual team may be within the same building or across continents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Two common situations occur that may prompt a change to the baseline scope

A

The scope may be expanded to include additional functionality or the scope may be diminished due to changes in the project environment such as reduced funding or requirements or changing time/due date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Scope creep

A

occurs when the project team integrates enhancements to the scope without proper evaluation and approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

work performance data

A

will identify the work activities that are completed, partially completed, or not started.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

risk register

A

is a list of potential risks, how the risks will be monitored, and what action will be taken should the risk event occur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

corrective action

A

is a document issued to identify quality failures and how they will be corrected. The deliverable itself may need to be reworked and the project plan may need to be revised to ensure that future deliverables do not include the same error.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The Four Categories of Change

A

Contingency plans, improvement changes, external events, scope change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The change management system

A

is in place to formally identify, evaluate, decide, and communicate project changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Recording

A

is the process of documenting and archiving project-related information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Reporting

A

is a key nonverbal communications methodology used to inform and to document project information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Weekly status reports that are often working documents for the team to communicate:

A

Accomplishments, Issues, Schedules, Resource utilization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Monthly status reports for senior stakeholders that would include:

A

Project overview bragging about progress, Issues including red light (critical) problems needing immediate resolution, yellow light items that are warning flags, and resolved issues, Current accomplishments, Future plans for the next month, Resource utilization and plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Monthly Financial Report

A

showing progress against the budget quantifying monies spent and planned to be spent and identifying issues with recommendations for resolution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Change management reporting

A

showing changes identified, requiring approval, and resolution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Project controls

A

are the data gathering, management, and analytical processes used to predict, understand, and constructively influence the time and cost outcomes of a project or program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Three Aspects of Project Quality

A

quality management, quality assurance, and quality control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Quality management

A

is the process of identifying the customer’s requirements and how they will be measured.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Quality assurance

A

is the process of validating that the requirements and measurements are appropriate for the project environment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Quality control

A

is the process of monitoring and changing project execution to ensure that activities are being executed as planned and will result in meeting the customer requirements. It is the monitoring and controlling process that occurs during project execution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Standards

A

are requirements that are generally accepted by a group of firms that produce similar products or services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Requirements

A

are what the customer needs to achieve from the completed project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Quality audits

A

are rigorous reviews of the project performance. These reviews are often completed by groups of experts outside of the project team such as a company’s quality assurance (QA) department or an outside consultant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

positive outcomes of the audit

A

Identifying issues before we go into production
Identifying best practices that can be adopted by future project teams
Identifying lessons learned that can improve performance on other projects
Identifying problems that can be corrected before additional costs are incurred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Checklists

A

are one way of monitoring that activities/tasks have been addressed and one method of assuring that all needed documents are written.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Project charters

A

contain enough information to understand who the project sponsor and project manager are, the purpose the project, a general idea of the scope, budget, and schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Statement of Work (SOW)

A

defines the project’s outcomes in terms of objectives, specific deliverables, acceptance criteria, technical requirements, milestones, constraints, and assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Work Breakdown Structure (WBS)

A

is a methodical deconstruction of deliverables into activities and then tasks to be performed. It details each activity that must be completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

living documents

A

are all planning documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

project scope

A

describes how the project outcomes will be created. Documents the customer’s expectations with regard to when the project will be completed (the time/schedule constraint) and how much the completed project will cost (the budget or cost constraint).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Evolution of the Scope Statement

A

Initial Scope (defining phase), Approved Scope Statement (planning phase), scope management (executing phase), scope verification (closing phase)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

product scope

A

is used to describe the portion of the scope statement that defines the features and functions of the project outcome or deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

project scope statement

A

represents a mutual understanding between the customer and the project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

project requirement

A

is a characteristic, function, or capability that must be present in the project final outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Project deliverables

A

are the features and functions of the project outcome that form the product scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Resource Responsibility Matrix

A

the resources needed are identified and the roles and responsibilities are detailed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

histogram

A

is a graph of a frequency distribution in which rectangles with bases on the horizontal axis are given widths equal to the class intervals and heights equal to the corresponding frequencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Knowledge, Skills, and Abilities (KSAs)

A

skills required by the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

resource leveling

A

The act of leveling the amount of resources needed to be constant over a period of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

deliverable

A

is a specific product or functionality that the project will provide.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Activities are connected to two types of deliverables:

A

Project management - communications, planning, execution, etc.
Project specific to the desired end result of this project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

8/80 rule

A

do not assign anything that takes less than eight hours so we allow resources sufficient work to occupy them and we don’t micromanage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Project management deliverables

A

the concrete items we need to manage this project. They are usually generic to a business or methodology adopted by a PM for use to manage the team and create sound communications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Project specific deliverables

A

project specific deliverables are required tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Risk Appetite

A

is the degree of uncertainty an entity is willing to take on in anticipation of a reward.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Risk Tolerance

A

is the degree, amount, or volume of risk that an organization or individual will withstand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Risk Threshold

A

refers to measurements along the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Below that risk threshold, the organization will accept the risk. Above that risk threshold, the organization will not tolerate the risk (PMBOK, 2015).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Risk Planning

A

is the process of reviewing every aspect of the project to identify what risks may occur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Risk Breakdown Structure (RBS)

A

which follows the WBS and insures that each activity and task in the WBS is reviewed for risk and opportunity and documented as identified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Risk Management Options

A

Avoid, mitigate, transfer and accept.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Risk Avoidance

A

During our planning, the team identifies the risk and sets a path to avoid the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Transfer of the risk

A

transfer risk to someone else

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Mitigation

A

is when the team acts in some fashion to reduce the impact or likelihood of the risk occurring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Accepting

A

the risk is a response strategy where we recognize the risk and say that it is a part of the project, normal business practice and the team will plan to accept it accordingly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Opportunity Management

A

Acceptance, Enhancing the opportunity and Sharing the opportunity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

risk register

A

lists all risks (external, technical, or organizational) and assigns scores for probability and severity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Probability Severity (P*S) score

A

helps us prioritize the risks appropriately.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

top-down estimation methods

A

These estimates are often provided by someone at the organization who has knowledge or experience from prior projects similar to the project being considered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Bottom-up estimation methods

A

require that estimates be made at the detailed work activity level of the WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

parametric estimating

A

top-down methods are based on the relationship between the current project and historical data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

ratio method

A

uses experience from prior projects to estimate the overall cost of the current project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

apportion method

A

is based on the ratio method but takes into consideration specific functionality or types of work that will be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Cost management

A

is the process of measuring how close actual costs are to the budget and then making changes in project execution as needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

baseline budget

A

is the approved budget and will be used as the standard for comparison of actual costs throughout the life of the project and identifying variances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Direct costs

A

are costs that are directly attributable to completing the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Direct overhead costs

A

are costs from the project that are shared across the work activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

General and administrative costs (G&A)

A

are overhead costs from the project organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

padding

A

people tend to add in extra time or money “just in case.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Contingency reserves

A

are costs included in the budget to cover situations that may occur. If the project requires the use of lumber, and lumber prices are known to fluctuate, then some portion of the lumber costs may be included in a contingency reserve. In a restaurant, food costs are very volatile and so the project must budget for those variances that can occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

management reserve

A

is an amount added to the overall project budget to cover unknown risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Realistic

A

Accurately reflects the way the organization does business.

Appropriate for the level of resources, capabilities, and external environment of the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Capable

A

Uses factors that are relevant to the organization.
We would not expect one model to cover all dimensions of a project, we would want to use models that cover their dimension comprehensively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Flexible

A

The model should provide accurate measures across a reasonable range of conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Easy to use

A

Provide results in a reasonable amount of time.

Results should be easily understood by the decision makers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Low cost

A

The costs of gathering data and running the model should be low relative to the scale of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Comparable

A

The model should be usable across a range of projects such that the outcomes of the model can be used to compare projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Non-numeric project selection models

A

focus on selection criteria that are not limited to traditional numeric performance measures (return on Investment [ROI], profit, revenue, etc.).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

competitive necessity model

A

require a project proposal, which includes justification, cost, and time estimates, as well as documented outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Operating necessity

A

evaluates a project based on whether it will ensure ongoing operations with the understanding that not executing the project will result in operations being interrupted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Sacred cow projects

A

are suggested by senior leadership or a powerful constituent of the company.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Numeric project selection models

A

use financial and other quantitative measures to drive decision making. Types are: internal rate of return, net present value, payback period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

time value of money

A

suggests that money is worth more to an organization now than in the future.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

payback period

A

calculates the amount of time required to earn back the cost of doing the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

payback period formula

A

(months) =Estimated Project Cost / Monthly Return

(annual) =Cost / Savings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

internal rate of return (IRR)

A

evaluates potential projects as if they were financial investments. It calculates the rate of return for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

Net present value (NPV)

A

is a financial measure of the total future benefits of a project minus the costs of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

future net cash flows

A

need to know the costs (cash outflows) and benefits (cash inflows) for the entire working life of the project outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

Checklist project selection model

A

use a series of questions to evaluate each potential project and then the answers to the questions would be compared to determine whether a project is accepted or rejected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Profit/profitability-based

A

measure the financial returns of the project and include: payback period, net present value, and internal rate of return as possible measure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Scoring project selection model

A

extends the benefits to the checklist approach and uses quantitative or qualitative criteria that are using a scale.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Weighted factor scoring model

A

senior management assigns a level of importance of each criterion which then assigns a value based on that level when calculating the total project score.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

operations

A

are the ongoing, daily activities of an organization that produces revenue and expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

project

A

is an activity or group of activities to generate a new, unique product, service, or results to support that program. However, it is possible that not all projects will be part of a larger program. There could, for example, be a project to develop a new battery that is more adaptable to more extreme temperature conditions. The product of this project could be applicable to all existing automobiles and not strictly a single program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

portfolio

A

is a group of related programs that support a long-term company goal or objective. The projects in a portfolio may individually address separate initiatives within the organization but collectively move the organization toward meeting a long-term goal or objective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

business strategy

A

consists of the activities, methods, tactics, etc. that will be employed to meet the business’s goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

program

A

is a group of related projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

project management

A

the application of knowledge, skills, tools and techniques to project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Phases of the Project Life Cycle

A

Defining (intializing), Planning, executing and closing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Defining

A

Defining (intializing), Planning, executing and closing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Planning

A
Technology
Business process
Staffing
Training
Testing
Communications
Budget constraints
Integration of the project with operations and other projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

Executing

A

Unexpected changes that may present themselves in the competitive environment
New organizational priorities
Loss of key project resources
Previously unidentified risks surfacing that puts the project plans in jeopardy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Closing

A

The closing phase of the project occurs when the project is completed to the customers’ satisfaction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

triple constraint

A

cost (budget), schedule (time), and scope (deliverables).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Project Manager (PM)

A

is responsible and accountable for managing the project to maximize its success

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

“working” project manager

A

a functional manager

113
Q

“dedicated” project manager

A

role in life is to be a project manager regardless of the operational needs of the business.

114
Q

Functional (Departmentalized)

A

is the oldest and most basic form of organization. It is the type of organization most often represented in corporation shareholder reports

115
Q

Projectized

A

is the oldest and most basic form of organization. It is the type of organization most often represented in corporation shareholder reports

116
Q

Matrix

A

has less clearly defined lines of reporting.

117
Q

Business scenario

A

represents an important business need or issue and provides an opportunity for others to create an appropriate, valuable solution

118
Q

Project objectives

A

the following are typically determined by the project sponsor and are intended to be very specific in order to appropriately communicate project expectations. SMART

119
Q

Active listening

A

the following is important to understanding what others are saying both verbally and nonverbally and for effective project management

120
Q

Stakeholder engagement

A

the following is the process of communicating and interacting with stakeholders in a way that keeps them interested and focused on their involvement in the project

121
Q

Team status reports

A

reports are often updated in an online collaboration tool and published weekly

122
Q

Work breakdown schedules

A

ensures that everyone understands what has to be delivered and who is responsible to do what when

123
Q

8 and 80 Rule

A

a project manager should avoid controlling tasks that take less than eight hours and should not let more than two weeks go by without checking in

124
Q

project management maturity model (OPM3) five levels

A
  1. “Ad Hoc” No formal standards, processes, methods, procedures, or staff to constitute a project management discipline. Standard technologies and reporting are sporadic
    2.”Planned” Project management standards, processes, methods, procedures, and staff exist in the organization, but are not considered to be an organizational standard. Basic documentation exists, inconsistent management support rarely/occasionally applied.
    3.”Managed” All project management standards, processes, methods, procedures, and staff are in place as organizational standards. Formal documentation exists, consistent management support, execution irregularly/inconsistently applied.
    4.”Integrated” More refined project management standards, processes, methods,
    procedures, and staff are in place. More refined documentation, consistent management support, consistent execution, and efficiency exist across all projects. Metrics are in place to collect performance data across all projects.
    5.”Sustained” Lessons learned and best practices are applied to continuously improve existing standards, processes, methods, procedures, and staff. Metrics are collected and applied at the project, portfolio, and
    organizational levels. The organization is in a position to evaluate future decisions based on past performance and maximize its competitive advantage in the industry.
125
Q

Weekly internal status meeting

A

kind of meeting each leader speak to the status of their work and project risks, and explain the status of any mitigation activities.

126
Q

Advantages of Functional (Departmentalized)

A

Lines of authority are clear.
Departmental work is easily prioritized by identified departmental authority.
There is flexibility in the use of staff.
Subject matter experts (SME) available to work on multiple projects.
Knowledge and experience readily shared between functional specialists.
Technical continuity exists within the organization.
Professional growth and career paths for the staff are clearly defined.

127
Q

disadvantages of Functional (Departmentalized)

A

Utilizing resources across functions can be difficult.
Requests for assistance from other departments not easily prioritized.
It is inefficient for projects requiring collaboration/cooperation between departments.
Project customer is not the only focus.
Organization does not focus on solving project business issues.
Project does not have a single individual responsible for all aspects of the project.
Response to customer needs is slow and difficult.
Project issues are not all given the same level of attention.
Project is not managed holistically.

128
Q

Advantages of Projectized

A

Clear lines of authority, the project manager has full authority.
Once SMEs are assigned, there is less need to negotiate availability of resources.
Project is managed holistically.
Response to customer and stakeholder issues is faster and clearer.
Skilled project team can support several successive projects of the same type.
Timely decision making on project issues.
Organizational structure is simple, flexible, and easy to understand.

129
Q

disadvantages of Projectized

A

PM must have enough work to keep SMEs busy full-time or risk loss to another project or functional area.
SME assigned may not have the most appropriate knowledge or expertise for the project.
Approach is expensive because of the duplication of personnel.
Equipment and personnel may be hoarded to ensure access to those resources.
Team members lose access to a repository of functional or technical expertise.
Policies and procedures may be applied inconsistently.
Team members may be anxious about post-project work.

130
Q

Advantages of Matrix

A

Central focus is the project.
Project managers have access to a large reservoir of technically skilled people. Potentially more access to SMEs as needed. More chance to get the most appropriate SME.
Project team members have less anxiety about the future.
Customer issues are responded to quickly.
Administrative personnel are not duplicated in each project team.
Resource balancing between projects is simpler and more efficient.
Project team organization is more flexible.

131
Q

Disadvantages of Matrix

A

Requires cooperation and coordination between and among functional departments and project managers.
SMEs not in daily contact with other SMEs for sharing of technical knowledge.
Person with decision-making power is not always clearly identified.
Resource balancing between projects can lead to friction.
Project closeout tasks are often difficult in strong matrix organizations.
Division of authority and responsibility is complex.

132
Q

project defining phase

A

the idea for the project is formalized into a project proposal and the decision on whether the project will be selected for implementation is made. It begins when an idea for a project is identified by a company.

133
Q

planning phase

A

when detailed planning occurs. It will require additional resources since people with specific knowledge about the work will need to provide input to the plan.

134
Q

executing phase

A

is when the bulk of the work to complete the project outcomes occurs. Based on the plans created during the project planning phase, the project team completes the required work activities.

135
Q

project closing phase

A

is when the project outcomes are delivered to the customer and/or sponsor and the customer and/or sponsor evaluates them to determine if they are acceptable - deliverables are ready, the budget and time requirements are met and quality is achieved, and lessons learned are documented. When the customer and/or sponsor accepts the project outcome(s), the PM must ensure that all the loose ends are tied up.

136
Q

project charter

A

summarizes all of the key information about the project and authorizes the project manager to assemble the team and begin detailed planning.

137
Q

collecting customer requirements

A

The process of gathering information from the customer and stakeholders in order to define the high level project outcomes

138
Q

project justification/business case

A

is a statement explaining the business need for the project.

139
Q

Project Selection Process

A

During the defining stage, the customer and project organization must determine whether the project is worthy of moving forward.

140
Q

project sponsor

A

The person in the project organization who has authority to expend resources for projects

141
Q

Integration Management Plan

A

Documents how the various processes and planning areas will be kept in sync throughout the project life cycle.

142
Q

Scope Management Plan

A

Documents how the scope will be initially developed, maintained during project execution, and verified at project closure.

143
Q

Risk Management Plan

A

Documents how risk events will be identified in advance, monitored, potentially mitigated, and managed across the project life cycle.

144
Q

Procurement Management Plan

A

Identifies how the project team will acquire products and services from outside organizations.

145
Q

Communications Management Plan

A

Documents which information will be communicated, when it will be communicated, how it will be communicated, and to whom.

146
Q

Human Resource Management Plan

A

Defines the roles, skills, and knowledge needed by project team members. Identifies when the human resource will be needed and how the person will be identified, trained, and integrated with the team.

147
Q

Stakeholder Management Plan

A

Explains how stakeholders will be identified along with their level of interest in the project and influence over the project. This is closely tied to the communications plan since stakeholders will need varying levels and frequency of information.

148
Q

Quality Management Plan

A

Documents how the quality of the project deliverables will be measured and what steps will be taken to monitor and assure that the quality meets the customer requirement.

149
Q

Cost Management Plan

A

Explains how costs will be estimated, monitored, controlled during the project.

150
Q

Time Management Plan

A

Explains how the schedule will be developed, monitored and controlled.

151
Q

Configuration Management Plan

A

Documents how the project team and stakeholders will keep track of the versions of project documents to ensure that the most up-to-date document is in use.

152
Q

Change Management Plan

A

Documents how changes to the project outcomes will be managed, approved, implemented, and monitored.

153
Q

Process Improvement Plan

A

Describes how the processes and procedures used on the project will be evaluated to ensure that the most efficient methods are implemented.

154
Q

Requirements Management Plan

A

Documents how the customer and stakeholder requirements will be identified, integrated to the project scope, tracked throughout the project, and verified at closure.

155
Q

monitoring and controlling

A

It is central to the PM’s role to know the status of the project work (monitor) and take action as needed to ensure the project plan is completed as planned (control).

156
Q

lessons learned

A

have great value to the project organization because they provide guidance for future projects.

157
Q

The triple constraint concept

A

It is not possible to change any one side of a triangle without affecting the other two characteristics

158
Q

The triple constraints are:

A

Time, Cost, Scope

159
Q

project scope

A

is, simply put, what the result of the project is desired to be.

160
Q

statement of work (SOW)

A

It defines the product of the project.

161
Q

Scope creep

A

occurs when there are any—but particularly small—incremental additions to the project scope that are not subject to the formal scope change process.

162
Q

critical path

A

is defined as the path with the longest duration from the start of the project to its completion.

163
Q

Float time/slack time

A

is the amount of time an activity can be delayed without affecting the completion date of the project.

164
Q

Administrative activities

A

during the project closing phase include performance report preparation, return of assets to the sponsoring organizations, archival of records, and documentation of lessons learned.

165
Q

Customer delivery activities

A

project closing phase include returning excess materials, reconciling accounts payable, and preparing required financial reports.

166
Q

Milestones

A

in a project schedule identify critical events and other activities that must be performed by specific dates before the project may proceed.

167
Q

Iterative planning processes

A

allows the project to move forward in phases when not enough information is known to plan the entire project

168
Q

common components of project scope statements

A

Project constraints, project acceptance criteria and technical requirements

169
Q

Project schedule

A

A timeline that specifies when the project begins and when it is supposed to end

170
Q

Project cost

A

The sum total of all expenses directly charged to the project

171
Q

Traditional project management methods

A

PERT, CPM, critical chain, waterfall, and PRINCE2

172
Q

Project evaluation and review technique (PERT)

A

was developed in the 1950s to support the U.S. Navy’s Polaris missile project. It uses a statistical approach to estimate the time that will be required to complete project work activities.

173
Q

Critical path method (CPM)Critical chain project management (CCPM)

A

was developed for the DuPont Corporation to help with projects in their manufacturing plants. It used for estimating project activity durations but CPM assumes that the estimates do not vary and time can be reliably estimated.

174
Q

Critical chain project management (CCPM)

A

focuses on managing the uncertainties of a project. It assumes that resources available to complete the project are in limited supply and it specifically plans to ensure resource availability.

175
Q

Waterfall

A

is a traditional practice which found its best use in software and hardware development.

176
Q

Extreme

A

addresses issues of extraordinary uncertainty or complexity.

177
Q

PRINCE2

A

is a highly structured project management method which focuses on the specification of the outputs rather than the coordination of activities

178
Q

duration

A

describe the number of time periods required to complete some portion of the work.

179
Q

activities

A

are the starting point for developing the project schedule because they identify specific work that will need to occur in order to execute the project.

180
Q

Deterministic duration estimation techniques

A

are appropriate when the activity durations are very predictable.

181
Q

Probabilistic duration estimation techniques

A

are used when there is uncertainty in how long an activity will take.

182
Q

one-point estimate

A

requires that the team expert provide a reliable estimate of the time necessary to complete the activity.

183
Q

triangular distribution

A

Activity Duration=O+M+P/3

184
Q

beta distribution

A

uses the three estimates (optimistic, most likely, and pessimistic) but places emphasis on the most likely estimate. Activity Duration=O+4M+P/6

185
Q

learning curves

A

that as a person repeats a task, the time required to complete the task decreases.

186
Q

Other factors that can influence the impact of learning curves

A

The complexity of the activity
The level of human input required
The duration of the activity
The skill level required

187
Q

Activity Estimate Standard Deviation

A

P−O/6

188
Q

Activity Estimate Range

A

(P−O)

189
Q

rill down in the Operations Plan, three specific activities have been identified

A

Design Procedures, Create Training Guide, and Write Job Descriptions

190
Q

single-point calculation

A

M*D

191
Q

network diagram

A

visually shows the team and stakeholders how the schedule will unfold.

192
Q

precedence diagram

A

show our understanding in a graphic representation for how the project will proceed.

193
Q

node label

A

its unique identifier for every activity.

194
Q

immediate predecessor

A

If a task is needed immediately

195
Q

Serial activities

A

are done in a single stream of tasks.

196
Q

Concurrent Activities

A

sets of activities can be done at the same time.

197
Q

Discretionary dependencies

A

where the PM can choose based on resource availability, including people, money/budget, and other materials

198
Q

Mandatory or logical dependencies

A

dependencies of one activity or task to another or legal requirements

199
Q

Internal dependencies

A

dependencies such as impact on milestones as defined by the project requirements or under management control

200
Q

External dependencies

A

dependencies that rely on external resources or forces

201
Q

Physical dependencies

A

where primer must be applied before the final paint or where the plumber and electrician cannot work in the same utility closet at the same time

202
Q

project schedule network diagram

A

A graphic representation of recognized dependencies.

203
Q

Finish-to-Start Relationships (FS)

A

is a logical relationship in which a successor activity cannot start until a predecessor has finished.

204
Q

Finish-to-Finish Relationships (FF)

A

is logical relationship where the successor task cannot be completed until the first task is completed.

205
Q

Start-to-Start Relationships (SS)

A

we cannot start the successor activity until the predecessor activity has started.

206
Q

Start-to-Finish Relationships

A

is where we cannot end the first task until the second task has started.

207
Q

Gantt Chart

A

visually depict relationships on a project

208
Q

lead Time

A

so that the successor task starts before its predecessor ends

209
Q

lag time

A

makes the successor task start some time after its predecessor ends.

210
Q

examples of resources used in project tasks

A

Money, supplies, humans

211
Q

Float or slack

A

is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

212
Q

Total float

A

is the difference between the finish date of the last activity on the critical path and the project completion date.

213
Q

negative float

A

which means the calculated completion date of the last activity is later than the targeted completion date established at the beginning of the project.

214
Q

free float

A

activities that are not on the critical path have a difference between their early start date and their late start date, those activities can be delayed without affecting the project completion date.

215
Q

forward pass

A

is when we start assigning dates based on the earliest start date, adding dates based on our estimates for each task in the diagram.

216
Q

backward pass

A

know the required end date of the project, we can start from the end date

217
Q

Reduce critical path

A

Inspect the tasks to identify if the tasks can be made shorter or if the estimate is too long. Have the experts review all of the estimates.

218
Q

crash

A

is to obtain the greatest amount of compression of the schedule/critical path for the least incremental cost or time.

219
Q

critical chain

A

builds on the critical path method by going a step further adding time buffers to account for limited resources.

220
Q

Fast-tracking

A

is the term for tasks when they overlap despite their dependencies

221
Q

Schedule compression

A

is the reduction of the overall project timeline to the least possible length for the least cost to the project.

222
Q

Schedule Compression Techniques

A

Do the work faster — using more or better resources often results in more costs or reducing quality.
Do less work — finish the tasks with less functionality.
Reduce the quality of the work, accepting the potential consequences.

223
Q

EV

A

Earned Value

Dollar value of work completed

224
Q

AC

A

Actual Cost
Total dollar value of costs to date, includes work and invoices already paid as well as expenses that have been incurred but not invoiced or paid

225
Q

BAC

A

Budget at Completion

Approved total baseline budget approved for completed project

226
Q

50-50 Rule

A

Assigns 50% compete once activity is started, and 100% upon completion. No in between, every task is marked with either a 0%, 50%, or 100%

227
Q

0-100 Rule

A

Every task is marked as 0% completed until it is finished, then marked as 100%

228
Q

Cost Variance

A

Determines if a project is meeting budget expectations

229
Q

Equation to determine if a project is meeting budget expectations

A

Cost Variance

CV = EV-AC
Earned Value - Actual Cost

230
Q

Schedule Variance

A

Determines if a project is meeting schedule expectations

231
Q

Equation to determine if a project is meeting schedule expectations

A

Schedule Variance

SV = EV-PV
Earned Value - Planned Value

232
Q

CPI

A

Cost performance index
Measures cost efficiency

CPI = EV/AC
(Earned Value / Actual Cost)

233
Q

CPI > 1 or 100%

CPI < 1 or 100%

A

CPI>1
Project team is completing more work at less cost than expected
CPI<1
Project team is accomplishing less work for the money spent and is behind budget

234
Q

SPI

A

Schedule performance index
Measures time efficiency

SPI = EV/PV
(Earned Value / Planned Value)

235
Q

SPI > 1 or 100%

SPI < 1 or 100%

A

SPI > 1
Project team is completing more work in less time than expected
SPI < 1
Project team is completing less work than what is required in the time allowed and is behind schedule

236
Q

What is TCPI

A

To complete performance index
What the CPI (cost performance index) will need to be for the remainder of the project if the team intends to finish on budget

237
Q

TCPI Equation

A

TCPI = (BAC - EV) / (BAC - AC)

Budget at Completion - Earned Value)/
(Budget at Completion - Actual Cost

238
Q

TCPI when project is over-budget and customer approves new EAC (estimated cost at completion):

A

TCPI = (BAC - EV) / (EAC - AC)

Budget at Completion - Earned Value)/
(New budget aka Estimated Cost at Completion - Actual Cost

239
Q

PCIB

A

Percent complete Index Budget
How much work has been completed

PCIB = EV / BAC
Earned Value / Budget at Completion

240
Q

What is PCIC

A

Percent complete index - cost

Used when customer agrees to a new BAC (budget at completion)

241
Q

PCIC Equation

A

PCIC = AC / EAC

Actual Cost / Estimated Cost at Completion

242
Q

ETC

A

Estimate to Completion
How much money will need to complete the project

ETC = (BAC - EV)/CPI

(Budget at Completion - Earned Value) /
Cost Performance Index

CPI = EV/AC

243
Q

EAC

A

Estimate at Completion
Forecast of how much more the project is expected to cost to complete

EAC = AC + ETC

Actual Cost = Estimate to Completion

ETC = (BAC - EV)/CPI [Cost performance index]
CPI = EV/AC
244
Q

EVA

A

Earned Value Assessment

245
Q

EVA Process Step 1

A

Collect measures from project records:

  1. AC - Actual Cost
  2. EV - Earned Value
  3. PV - Planned Value
  4. BAC - Budget at Completion
246
Q

EVA Process Step 2

A

Calculate Variances:

  1. CV - Cost Variance
  2. SV - Schedule Variance
  3. PCIB - Percent complete index budget
247
Q

EVA Process Step 3

A

Calculate Performance Factors

  1. CPI - Cost Performance Index
  2. SPI - Schedule Performance Index
248
Q

EVA Process Step 4

A

Calculate Estimates or Identifying Performance Factors
1. ETC - Estimate to completion
2. EAC - Estimate at completion
3. TCPI - To complete performance Index
4. PCIB - Percent complete index budget or
PCIC - (Percent complete index - cost)

249
Q

operations

A

are the ongoing, daily activities of an organization that produces revenue and expense.

250
Q

project

A

is an activity or group of activities to generate a new, unique product, service, or results to support that program. However, it is possible that not all projects will be part of a larger program. There could, for example, be a project to develop a new battery that is more adaptable to more extreme temperature conditions. The product of this project could be applicable to all existing automobiles and not strictly a single program.

251
Q

portfolio

A

is a group of related programs that support a long-term company goal or objective. The projects in a portfolio may individually address separate initiatives within the organization but collectively move the organization toward meeting a long-term goal or objective.

252
Q

business strategy

A

consists of the activities, methods, tactics, etc. that will be employed to meet the business’s goals.

253
Q

program

A

is a group of related projects.

254
Q

project management

A

the application of knowledge, skills, tools and techniques to project activities.

255
Q

Phases of the Project Life Cycle

A

Defining (intializing), Planning, executing and closing

256
Q

Defining

A

Determining the project’s sponsor and the project’s manager
Creating a project charter. The charter is a document that, like a contract, is agreed upon by the sponsor and key stakeholders. It defines the project and authorizes the resources, roles, responsibilities, authorities, and scope for the project.

257
Q

Planning

A
Technology
Business process
Staffing
Training
Testing
Communications
Budget constraints
Integration of the project with operations and other projects
258
Q

Executing

A

Unexpected changes that may present themselves in the competitive environment
New organizational priorities
Loss of key project resources
Previously unidentified risks surfacing that puts the project plans in jeopardy

259
Q

Closing

A

The closing phase of the project occurs when the project is completed to the customers’ satisfaction.

260
Q

triple constraint

A

cost (budget), schedule (time), and scope (deliverables).

261
Q

Project Manager (PM)

A

is responsible and accountable for managing the project to maximize its success

262
Q

“working” project manager

A

a functional manager

263
Q

“dedicated” project manager

A

role in life is to be a project manager regardless of the operational needs of the business.

264
Q

Functional (Departmentalized)

A

is the oldest and most basic form of organization. It is the type of organization most often represented in corporation shareholder reports

265
Q

Projectized

A

subject matter experts (SMEs) from different functional areas are assigned to directly report to the project manager (PM) for a specific project.

266
Q

Matrix

A

has less clearly defined lines of reporting.

267
Q

Business scenario

A

represents an important business need or issue and provides an opportunity for others to create an appropriate, valuable solution

268
Q

Project objectives

A

the following are typically determined by the project sponsor and are intended to be very specific in order to appropriately communicate project expectations. SMART

269
Q

Active listening

A

the following is important to understanding what others are saying both verbally and nonverbally and for effective project management

270
Q

Stakeholder engagement

A

the following is the process of communicating and interacting with stakeholders in a way that keeps them interested and focused on their involvement in the project

271
Q

Team status reports

A

reports are often updated in an online collaboration tool and published weekly

272
Q

Work breakdown schedules

A

ensures that everyone understands what has to be delivered and who is responsible to do what when

273
Q

8 and 80 Rule

A

a project manager should avoid controlling tasks that take less than eight hours and should not let more than two weeks go by without checking in

274
Q

project management maturity model (OPM3) five levels

A
  1. “Ad Hoc” No formal standards, processes, methods, procedures, or staff to constitute a project management discipline. Standard technologies and reporting are sporadic
    2.”Planned” Project management standards, processes, methods, procedures, and staff exist in the organization, but are not considered to be an organizational standard. Basic documentation exists, inconsistent management support rarely/occasionally applied.
    3.”Managed” All project management standards, processes, methods, procedures, and staff are in place as organizational standards. Formal documentation exists, consistent management support, execution irregularly/inconsistently applied.
    4.”Integrated” More refined project management standards, processes, methods,
    procedures, and staff are in place. More refined documentation, consistent management support, consistent execution, and efficiency exist across all projects. Metrics are in place to collect performance data across all projects.
    5.”Sustained” Lessons learned and best practices are applied to continuously improve existing standards, processes, methods, procedures, and staff. Metrics are collected and applied at the project, portfolio, and
    organizational levels. The organization is in a position to evaluate future decisions based on past performance and maximize its competitive advantage in the industry.
275
Q

Weekly internal status meeting

A

kind of meeting each leader speak to the status of their work and project risks, and explain the status of any mitigation activities.

276
Q

Advantages of Functional (Departmentalized)

A

Lines of authority are clear.
Departmental work is easily prioritized by identified departmental authority.
There is flexibility in the use of staff.
Subject matter experts (SME) available to work on multiple projects.
Knowledge and experience readily shared between functional specialists.
Technical continuity exists within the organization.
Professional growth and career paths for the staff are clearly defined.

277
Q

disadvantages of Functional (Departmentalized)

A

Utilizing resources across functions can be difficult.
Requests for assistance from other departments not easily prioritized.
It is inefficient for projects requiring collaboration/cooperation between departments.
Project customer is not the only focus.
Organization does not focus on solving project business issues.
Project does not have a single individual responsible for all aspects of the project.
Response to customer needs is slow and difficult.
Project issues are not all given the same level of attention.
Project is not managed holistically.

Advantages of Projectized
Clear lines of authority, the project manager has full authority.
Once SMEs are assigned, there is less need to negotiate availability of resources.
Project is managed holistically.
Response to customer and stakeholder issues is faster and clearer.
Skilled project team can support several successive projects of the same type.
Timely decision making on project issues.
Organizational structure is simple, flexible, and easy to understand.

disadvantages of Projectized
PM must have enough work to keep SMEs busy full-time or risk loss to another project or functional area.
SME assigned may not have the most appropriate knowledge or expertise for the project.
Approach is expensive because of the duplication of personnel.
Equipment and personnel may be hoarded to ensure access to those resources.
Team members lose access to a repository of functional or technical expertise.
Policies and procedures may be applied inconsistently.
Team members may be anxious about post-project work.

278
Q

Advantages of Matrix

A

Central focus is the project.
Project managers have access to a large reservoir of technically skilled people. Potentially more access to SMEs as needed. More chance to get the most appropriate SME.
Project team members have less anxiety about the future.
Customer issues are responded to quickly.
Administrative personnel are not duplicated in each project team.
Resource balancing between projects is simpler and more efficient.
Project team organization is more flexible.

279
Q

Disadvantages of Matrix

A

Requires cooperation and coordination between and among functional departments and project managers.
SMEs not in daily contact with other SMEs for sharing of technical knowledge.
Person with decision-making power is not always clearly identified.
Resource balancing between projects can lead to friction.
Project closeout tasks are often difficult in strong matrix organizations.
Division of authority and responsibility is complex.