All Flashcards
Three essential drivers that must be achieved to generate positive characteristics in project teams
Cohesiveness, Trust, Motivation
The five stages Dr. Bruce Tuckman (1965) introduced of group development
Forming, Storming, Norming, Performing, Adjorning
Forming
In this stage, team members may be meeting for the first time. Often, no one really knows much about anyone else on the team. It may be premature to refer to this group of individuals as a team. It is a time of introduction and forming relationships and understanding from exchange of information.
Storming
Team members are beginning to know about each other, but they do not yet understand how to work together. Members may “jockey for position” within the team. The dynamics of working together beyond any written statement of “roles and responsibilities” are being established. Personalities surface, showing the strengths, weaknesses, and personal needs of each individual on the team. Integration into a team may come with some struggle and conflict.
Norming
Team members have “figured out” how they will interact with each other. Working relationships are beginning to form. Trust and understanding is beginning to form between team members. They are beginning to feel comfortable working together and openly and willingly sharing information.
Performing
Team members are fully comfortable working together. Trust has been developed. Working relationships have jelled. Work is being conducted and project progress is occurring.
Adjourning
This only occurs when all the team’s work has been completed and the team is no longer required. This may occur at any time in the project life cycle.
Co-located Teams
involves team members physically working at the same location or holding project meetings together in a common setup.
Virtual Teams
are teams whose members interact primarily through electronic communications. Members of a virtual team may be within the same building or across continents.
Two common situations occur that may prompt a change to the baseline scope
The scope may be expanded to include additional functionality or the scope may be diminished due to changes in the project environment such as reduced funding or requirements or changing time/due date.
Scope creep
occurs when the project team integrates enhancements to the scope without proper evaluation and approval.
work performance data
will identify the work activities that are completed, partially completed, or not started.
risk register
is a list of potential risks, how the risks will be monitored, and what action will be taken should the risk event occur.
corrective action
is a document issued to identify quality failures and how they will be corrected. The deliverable itself may need to be reworked and the project plan may need to be revised to ensure that future deliverables do not include the same error.
The Four Categories of Change
Contingency plans, improvement changes, external events, scope change
The change management system
is in place to formally identify, evaluate, decide, and communicate project changes.
Recording
is the process of documenting and archiving project-related information.
Reporting
is a key nonverbal communications methodology used to inform and to document project information.
Weekly status reports that are often working documents for the team to communicate:
Accomplishments, Issues, Schedules, Resource utilization
Monthly status reports for senior stakeholders that would include:
Project overview bragging about progress, Issues including red light (critical) problems needing immediate resolution, yellow light items that are warning flags, and resolved issues, Current accomplishments, Future plans for the next month, Resource utilization and plans
Monthly Financial Report
showing progress against the budget quantifying monies spent and planned to be spent and identifying issues with recommendations for resolution
Change management reporting
showing changes identified, requiring approval, and resolution.
Project controls
are the data gathering, management, and analytical processes used to predict, understand, and constructively influence the time and cost outcomes of a project or program.
Three Aspects of Project Quality
quality management, quality assurance, and quality control.
Quality management
is the process of identifying the customer’s requirements and how they will be measured.
Quality assurance
is the process of validating that the requirements and measurements are appropriate for the project environment.
Quality control
is the process of monitoring and changing project execution to ensure that activities are being executed as planned and will result in meeting the customer requirements. It is the monitoring and controlling process that occurs during project execution.
Standards
are requirements that are generally accepted by a group of firms that produce similar products or services.
Requirements
are what the customer needs to achieve from the completed project.
Quality audits
are rigorous reviews of the project performance. These reviews are often completed by groups of experts outside of the project team such as a company’s quality assurance (QA) department or an outside consultant.
positive outcomes of the audit
Identifying issues before we go into production
Identifying best practices that can be adopted by future project teams
Identifying lessons learned that can improve performance on other projects
Identifying problems that can be corrected before additional costs are incurred
Checklists
are one way of monitoring that activities/tasks have been addressed and one method of assuring that all needed documents are written.
Project charters
contain enough information to understand who the project sponsor and project manager are, the purpose the project, a general idea of the scope, budget, and schedule.
Statement of Work (SOW)
defines the project’s outcomes in terms of objectives, specific deliverables, acceptance criteria, technical requirements, milestones, constraints, and assumptions.
Work Breakdown Structure (WBS)
is a methodical deconstruction of deliverables into activities and then tasks to be performed. It details each activity that must be completed.
living documents
are all planning documents
project scope
describes how the project outcomes will be created. Documents the customer’s expectations with regard to when the project will be completed (the time/schedule constraint) and how much the completed project will cost (the budget or cost constraint).
Evolution of the Scope Statement
Initial Scope (defining phase), Approved Scope Statement (planning phase), scope management (executing phase), scope verification (closing phase)
product scope
is used to describe the portion of the scope statement that defines the features and functions of the project outcome or deliverables.
project scope statement
represents a mutual understanding between the customer and the project team.
project requirement
is a characteristic, function, or capability that must be present in the project final outcome.
Project deliverables
are the features and functions of the project outcome that form the product scope.
Resource Responsibility Matrix
the resources needed are identified and the roles and responsibilities are detailed
histogram
is a graph of a frequency distribution in which rectangles with bases on the horizontal axis are given widths equal to the class intervals and heights equal to the corresponding frequencies.
Knowledge, Skills, and Abilities (KSAs)
skills required by the project team
resource leveling
The act of leveling the amount of resources needed to be constant over a period of time
deliverable
is a specific product or functionality that the project will provide.
Activities are connected to two types of deliverables:
Project management - communications, planning, execution, etc.
Project specific to the desired end result of this project
8/80 rule
do not assign anything that takes less than eight hours so we allow resources sufficient work to occupy them and we don’t micromanage
Project management deliverables
the concrete items we need to manage this project. They are usually generic to a business or methodology adopted by a PM for use to manage the team and create sound communications.
Project specific deliverables
project specific deliverables are required tasks
Risk Appetite
is the degree of uncertainty an entity is willing to take on in anticipation of a reward.
Risk Tolerance
is the degree, amount, or volume of risk that an organization or individual will withstand.
Risk Threshold
refers to measurements along the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Below that risk threshold, the organization will accept the risk. Above that risk threshold, the organization will not tolerate the risk (PMBOK, 2015).
Risk Planning
is the process of reviewing every aspect of the project to identify what risks may occur.
Risk Breakdown Structure (RBS)
which follows the WBS and insures that each activity and task in the WBS is reviewed for risk and opportunity and documented as identified.
Risk Management Options
Avoid, mitigate, transfer and accept.
Risk Avoidance
During our planning, the team identifies the risk and sets a path to avoid the risk.
Transfer of the risk
transfer risk to someone else
Mitigation
is when the team acts in some fashion to reduce the impact or likelihood of the risk occurring.
Accepting
the risk is a response strategy where we recognize the risk and say that it is a part of the project, normal business practice and the team will plan to accept it accordingly.
Opportunity Management
Acceptance, Enhancing the opportunity and Sharing the opportunity
risk register
lists all risks (external, technical, or organizational) and assigns scores for probability and severity.
Probability Severity (P*S) score
helps us prioritize the risks appropriately.
top-down estimation methods
These estimates are often provided by someone at the organization who has knowledge or experience from prior projects similar to the project being considered
Bottom-up estimation methods
require that estimates be made at the detailed work activity level of the WBS.
parametric estimating
top-down methods are based on the relationship between the current project and historical data
ratio method
uses experience from prior projects to estimate the overall cost of the current project.
apportion method
is based on the ratio method but takes into consideration specific functionality or types of work that will be required.
Cost management
is the process of measuring how close actual costs are to the budget and then making changes in project execution as needed.
baseline budget
is the approved budget and will be used as the standard for comparison of actual costs throughout the life of the project and identifying variances.
Direct costs
are costs that are directly attributable to completing the project work.
Direct overhead costs
are costs from the project that are shared across the work activities.
General and administrative costs (G&A)
are overhead costs from the project organization.
padding
people tend to add in extra time or money “just in case.”
Contingency reserves
are costs included in the budget to cover situations that may occur. If the project requires the use of lumber, and lumber prices are known to fluctuate, then some portion of the lumber costs may be included in a contingency reserve. In a restaurant, food costs are very volatile and so the project must budget for those variances that can occur
management reserve
is an amount added to the overall project budget to cover unknown risks.
Realistic
Accurately reflects the way the organization does business.
Appropriate for the level of resources, capabilities, and external environment of the organization.
Capable
Uses factors that are relevant to the organization.
We would not expect one model to cover all dimensions of a project, we would want to use models that cover their dimension comprehensively.
Flexible
The model should provide accurate measures across a reasonable range of conditions.
Easy to use
Provide results in a reasonable amount of time.
Results should be easily understood by the decision makers.
Low cost
The costs of gathering data and running the model should be low relative to the scale of the project.
Comparable
The model should be usable across a range of projects such that the outcomes of the model can be used to compare projects.
Non-numeric project selection models
focus on selection criteria that are not limited to traditional numeric performance measures (return on Investment [ROI], profit, revenue, etc.).
competitive necessity model
require a project proposal, which includes justification, cost, and time estimates, as well as documented outcomes.
Operating necessity
evaluates a project based on whether it will ensure ongoing operations with the understanding that not executing the project will result in operations being interrupted.
Sacred cow projects
are suggested by senior leadership or a powerful constituent of the company.
Numeric project selection models
use financial and other quantitative measures to drive decision making. Types are: internal rate of return, net present value, payback period.
time value of money
suggests that money is worth more to an organization now than in the future.
payback period
calculates the amount of time required to earn back the cost of doing the project.
payback period formula
(months) =Estimated Project Cost / Monthly Return
(annual) =Cost / Savings
internal rate of return (IRR)
evaluates potential projects as if they were financial investments. It calculates the rate of return for a project.
Net present value (NPV)
is a financial measure of the total future benefits of a project minus the costs of the project.
future net cash flows
need to know the costs (cash outflows) and benefits (cash inflows) for the entire working life of the project outcome.
Checklist project selection model
use a series of questions to evaluate each potential project and then the answers to the questions would be compared to determine whether a project is accepted or rejected.
Profit/profitability-based
measure the financial returns of the project and include: payback period, net present value, and internal rate of return as possible measure.
Scoring project selection model
extends the benefits to the checklist approach and uses quantitative or qualitative criteria that are using a scale.
Weighted factor scoring model
senior management assigns a level of importance of each criterion which then assigns a value based on that level when calculating the total project score.
operations
are the ongoing, daily activities of an organization that produces revenue and expense.
project
is an activity or group of activities to generate a new, unique product, service, or results to support that program. However, it is possible that not all projects will be part of a larger program. There could, for example, be a project to develop a new battery that is more adaptable to more extreme temperature conditions. The product of this project could be applicable to all existing automobiles and not strictly a single program.
portfolio
is a group of related programs that support a long-term company goal or objective. The projects in a portfolio may individually address separate initiatives within the organization but collectively move the organization toward meeting a long-term goal or objective.
business strategy
consists of the activities, methods, tactics, etc. that will be employed to meet the business’s goals.
program
is a group of related projects.
project management
the application of knowledge, skills, tools and techniques to project activities.
Phases of the Project Life Cycle
Defining (intializing), Planning, executing and closing
Defining
Defining (intializing), Planning, executing and closing
Planning
Technology Business process Staffing Training Testing Communications Budget constraints Integration of the project with operations and other projects
Executing
Unexpected changes that may present themselves in the competitive environment
New organizational priorities
Loss of key project resources
Previously unidentified risks surfacing that puts the project plans in jeopardy
Closing
The closing phase of the project occurs when the project is completed to the customers’ satisfaction.
triple constraint
cost (budget), schedule (time), and scope (deliverables).
Project Manager (PM)
is responsible and accountable for managing the project to maximize its success