AGILE PROCESS, PROJECT, & PROGRAM CONTROL Flashcards
1
Q
What are the 3 constraints in each project? and what are the 2 names for it?
A
The 3 inseparable constraints for each project are:
+ Scope
+ Schedule
+ Budget
These 3 constraints are called “Triple Cost Constraints”; or “ Iron Triangle”
2
Q
What does Agile PM adjust in the Triple Cost Constraints?
How does Agile PM pick the providers (sourcing)?
What does Agile PM value (Goals)?
A
- Agile will adjust SCOPE in the Triple Cost Constraints
- Agile pick the providers by TRUST
- Agile’s Goal is SPEED
3
Q
What does Lean PM adjust in the Triple Cost Constraints?
How does Lean PM pick the providers (sourcing)?
What does Lean PM value (Goals)?
A
- Lean PM will adjust SCHEDULE in the Triple Cost Constraints
- Lean PM w