Agile Flashcards
AGILE -
PREDICTIVE - PROCESS GROUPS
PREDICTIVE - PROCESS GROUPS
PLANNING:
Develop Project Mgmt Plan (I)
Plan Scope Mgmt (S)
Collect Requirements (S)
Define Scope (S)
Create WBS (S)
Plan Schedule Mgmt (Sc)
Define Activities (Sc)
Schedule Activities (Sc)
Estimate Activity Durations (Sc)
Develop Schedule (Sc)
Plan Cost Mgmt (C)
Estimate Costs (C)
Determine Budget (C)
Plan Quality Mgmt (Q)
Resource Mgmt (R)
Estimate Activity Resources (R)
Plan Communication Mgmt (Com)
Plan Risk Mgmt (R)
Identify Risk (R)
Perform Qualitative Risks Analysis (R)
Perform Quantitative Risks Analysis (R)
Plan Risk Responses (R)
Plan Procurement Mgmt (P)
Plan Stakeholder Engagement (SE)
PREDICTIVE - PROCESS GROUPS
EXECUTING:
Direct and Manage Project Work (I)
Manage Project Knowledge (I)
Manage Quality (Q)
Acquire Resources (R)
Develop Team (R)
Manage Team (R)
Manage Communications (Com)
Implement Risk Responses (RM)
Conduct Procurements (P)
Manage Stakeholder Engagement (SE)
PREDICTIVE - PROCESS GROUPS
MONITORING & CONTROLLING:
Monitor and Control Project Work (I)
Perform Integrated Change Control (I)
Validate Scope (S)
Control Scope (S)
Control Schedule (Sc)
Control Costs (C)
Control Quality (Q)
Control Resource (R)
Monitor Communications (Com)
Monitor Risks (R)
Control Procurements (P)
Monitor Stakeholder Engagement (SE)
PREDICTIVE - PROCESS GROUPS
CLOSING:
Close Project or Phase (I)
PREDICTIVE - KNOWLEDGE AREAS
PROJECT MGMT PLANS:
Scope
Resource
Quality
Stakeholder Engagement
Cost
Procurement
Risk
Integration
Communication
Schedule
PREDICTIVE - PROCESS GROUPS
INITIATION:
Develop Charter
Identify Stakeholders
PROJECT DOCUMENTS
Process: Manage Quality
Test and evaluation documents: Used to help evaluate the project deliverables when completed.
PROJECT DOCUMENTS
Process: Plan Resource Mgmt
Team Charter: Guidelines team should follow on a project, includes values, decision-making process, acceptable behavior, code of conduct, and etiquette
PROJECT DOCUMENTS
Process: Identify Stakeholders
Stakeholder Register: A list of all stakeholders, which can include categorization, impact, and communication requirements
PERFORMANCE -
PROJECT DOCUMENTS
Process: Control Schedule
Schedule Forecasts: A prediction of when the project may be completed based on the current progress of the work.
AGILE - VARIANCE & TREND ANALYSIS
VARIANCE: measure of how far apart planned vs actual varies.
TREND ANALYSIS: measure that provides insights into future issues/defects -
LAGGING METRICS: Info on past events
LEADING METRICS: Info on current or future events
AGILE - RISKS
How does risk negatively effect your project
Adjusting the backlog for risk -done after risk response (removing/reprioritizing features)
Expected Monetary Value(EMV) =
Impact ($) x Probability (%)
50 X 5 = 2500
Risk Severity
Risk Probability x Risk Impact
Uses a scale of numbers (i.e. 1-5)
AGILE - CONTROL LIMITS
Provides guidelines to operate within.
Looks at how many points are being used within an iteration.
Aides in analyzing issues before issues occurs.
When to take needed action, diagnose issues.
AGILE - DEFECTS
ESCAPED DEFECTS: DEFECTS THAT MAKES IT TO THE CUSTOMER.
PERFOMANCE - LEAD & CYCLE TIME
LEAD TIME: Time it takes to go through the entire process to delivery requirements.
CYCLE TIME: Subset of LEAD TIME - HOW LONG something takes to go through part of the process.
WIP, should be shorter time frame. (i.e. Design, gathering requirements, etc). Money invested w/o currently ROI)
Cycle Time = WIP/Throughput
Throughput = Amt of work that can be done in a time period
60 points total work /5 points per day = 12 days
120 miles/60miles per hour = 2 hours
PERFOMANCE - VELOCITY
Shows how the team has been performing.
PERFOMANCE - BURN UP CHART
Work that has been done
AGILE - RETROSPECTIVES
Set the stage:
1. Check-in
2. Get team focused
3. Encourage participation
4. Outline approach and topics for discussion
5. Focus on/Focus off
6. ESVP (Explorer, shopper, vacationer or prisoner)
AGILE - RETROSPECTIVES
Occurs after Sprint Review
Adds immediate value
Looks at continuous improvements
Inspect and improve methods and how team works
2 hr time limit.
Steps:
1. Set the stage
2. Gather data
3. Generate insights
4. Decide what to do
5. Close Retrospective
AGILE - PRE-MORTEMS
Team meeting that looks at things that can cause failures during a project before they take place
List possible failures
List causes or reasons that may cause failures
Review Project Plan to determine what can be done to reduce or remove the reasons for failure
VALUE STREAM MAP/MAPPING
Look at process
Allows optimization of process or flow of information or materials to complete a process
Reduce waste or unnecessary work
Steps:
Identify product or service
Create a “as is” value stream map of what it currently is
Review to find waste
Create a new map w/improvements (to be)
Develop a road map to implement the fixes
Plan to revisit and analyze for new improvements
AGILE - PROCESS ANALYSIS & TAILORING
First analyze
Review and diagnose issues
Look for tailoring possibilities to improve
Customize based on need and environment
AGILE - KAIZEN
Continuous Improvement
Focus on team to implement small incremental improvements
AGILE CYCLE: Plan - Develop - Evaluate - Learn (PDEL)
(PDCA) Cycle: Plan - Do - Check - Act
(Deaman Cycle)
AGILE - PROBLEM SOLVING
ALWAYS HAVE TEAM TO SOLVE PROBLEMS
GET CONSENSUS FROM TEAM WHO HAS BROAD KNOWLEDGE
APPROACH AS CONTINUOUS IMPROVING PROCESS
SOME PROBLEMS AREN’T WORTH SOLVING AND SOME DON’T HAVE A SOLUTION.
PERFOMANCE - BURN DOWN CHART
Work that remains to be done
Risk Burndown Chart: Chart showing severity of risk over time. (i.e. Fund and resource shortage.)
PROJECT DOCUMENTS
Process: Develop Schedule
Schedule Data: The information that is used to create the schedule such as who made it, assumptions, and constraints
PROJECT DOCUMENTS
Process: Identify Risks
Risk Report: A description of the overall project risks
PROJECT DOCUMENTS
Process: Identify Risks
Risk Register: A list of all positive and negative risks on project, along with responses
PROJECT DOCUMENTS
Process: Acquire Resources
Resource calendars: Show the availability of resources on the project both physical or HR.
PROJECT DOCUMENTS
Process: Estimate activity resources
Resource Breakdown Structure: Categorization and type of the project resources
PROJECT DOCUMENTS
Process: Collect Requirements
Requirements Traceability Matrix: A table that traces the origin of the requirement
PROJECT DOCUMENTS
Process: Collect Requirements
Requirements Documentation: Description of all requirements from project stakeholders
PROJECT DOCUMENTS
Process: Manage Quality
Quality Report: A report which generally includes information about quality issues on the project and recommendations on how to improve the processes on the project.