Adjudication Flashcards

1
Q

What act compounds on the adjudication requirements?

A

Local Democracy, Economic Development and Construction Act 2009

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Under what act is Adjudication mandatory as a dispute resolution route

A

The Housing Grants Construction and Regeneration Act 1996

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Under JCT, where does it say about adjudication?

A

Articles of agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the timeline for adjudication?

A
  • Issue notice of adjudication
  • Within 7 days, appoint adjudicator and a referral notice
  • within 7 days, the other party issues their response
  • Within 28 days of the referral notice, the adjudicator makes a decision
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How long can the period for adjudicators decision be extended?

A
  • Can be extended by a further 14 days if the referring party decides
  • Can be extended by any time if both parties agree
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a referral notice?

A

provides information to the adjudicator about the dispute and the context around it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What info is included in a referral notice?

A
  • Copy of the contract
  • The background to the issue
  • Evidence and/or case law
  • The remedies being sought