Adjudication Flashcards
1
Q
Pre-Statutory Adjudication & Policy Background
A
- Before statutory adjudication, other dispute resolution forms were available, such as contractual adjudication (NEC/ECC contracts, DOM sub-contracts) and mediation.
- Adoption of new procedures was slow, leading to arbitration and court dominating construction disputes.
- The 1994 “Constructing the Team” report by Sir Michael Latham recommended adjudication for speedier, cheaper dispute resolution and cash-flow remedy during contracts.
- The legislation uniquely imposed a dispute resolution form on the construction industry due to concerns about its inability to resolve disputes quickly and cheaply affecting overall performance.
2
Q
Key Legislation, Features & Dates in Construction Adjudication
A
- Key legislation includes the 1996 Act, the 2009 Act, and the Schemes for Construction Contracts.
- Legislation introduced mandatory requirements for “construction contracts”, payment provisions, and the right to adjudicate.
- The right to adjudicate, imposed upon parties’ contracts, was a revolutionary innovation.
- The 1996 Act applies to contracts made on or after 1 May 1998, and 2009 Act amendments apply to contracts after 1 October 2011 (England & Wales) or 1 November 2011 (Scotland).
3
Q
Contracts in Writing (S.107)
A
- The 1996 Act required construction contracts to be in writing or evidenced in writing for adjudication.
- Oral contracts were not subject to adjudication under the Act.
- Section 107 provided a complex definition of “agreement in writing” and included various scenarios.
- Determining compliance with the “in writing” requirement caused difficulties and led to numerous enforcement actions
4
Q
Satisfying Section 107 & Adjudication Jurisdiction
A
- RJT Consulting Engineers v DM Engineering settled the debate on what’s needed to satisfy Section 107, requiring the whole agreement to be evidenced in writing.
- Glendalough Associated v Harris Calnan Construction clarified that a minimum agreement must include parties, scope of work, price, and time.
- Numerous cases explored the effect of oral terms, oral amendments, and variations on adjudication jurisdiction under the Act.
- Challenges related to Section 107 and adjudication jurisdiction remain a significant area of debate and legal development.
5
Q
Contracts in Writing and Confusion in Case Law
A
- T & T Fabrications v Hubbard: Decision not enforced due to certain terms not being in writing, causing a dispute about whether the terms were agreed upon.
- Allen Wilson Joinery v Privetgrange: Implied terms and budget prices don’t prevent a contract from being in writing.
- Rok Building v Bestwood Carpentry: A construction contract in writing with no agreed price can still be a written contract, using implied terms for price determination.
- All Metal Roofing v Kamm Properties: A flexible approach, considering exchanges of correspondence and purchase orders as evidence of a contract in writing.
6
Q
Legislation - Contracts in Writing (s.107)
A
- Section 107 removed by the 2009 Act; ‘in writing’ requirement no longer applies to construction contracts entered after the effective dates.
- Old contracts still need to be ‘in writing’ for the 1996 Act to apply; relevant cases still apply to these contracts.
- 2009 Act requires all provisions on adjudication procedures to be in writing.
- Change introduced to reduce barriers in referring disputes to adjudication and to support smaller companies.
- Practical implications: establishing whether the Act applies, right to adjudicate, and adjudicator jurisdiction; potential challenges in determining contract existence and provisions.
7
Q
Legislation - Construction Contract (s.104)
A
- Construction contract defined in Section 104 of the 1996 Act.
- Includes carrying out construction operations, arranging subcontract work, providing labor, architectural/design/surveying work, and advice on building-related matters.
- Collateral warranties can be considered construction contracts depending on wording and ongoing future performance (Abbey Healthcare case).
- Warranties that provide simple fixed promises or guarantees for past state of affairs may not be construction contracts.
- Warranty’s execution date or work completion doesn’t affect its classification as a construction contract; key is the promise to both past and future work and the standard of that work.
8
Q
Legislation - Construction Operations (s.105) and Exclusions/Exemptions
A
- Construction operations broadly include building, civil engineering, mechanical/electrical works, cleaning during construction, preparatory work, and painting/decorating.
- 1996 Act exclusions: oil/gas drilling, mineral extraction, specific industrial plant/machinery works, and manufacturing/delivery of components (unless installation included).
- Exclusion Orders: PFI contracts, finance contracts, development agreements with land transfer, and specific statutory agreements.
- PFI arrangements generally subject to the 1996 Act, but top-tier PFI contracts excluded.
- LDEDC Act 2009 extends power to exclude certain construction contracts.
- Residential occupiers and primary activity on site important for determining if operations are construction operations (Engie Fabricom case).
9
Q
s.108 of 1996 Act - Construction Contracts Adjudication
A
- Applies to construction contracts as defined in Section 104.
- Parties have a right to refer disputes for adjudication.
- “Dispute” includes any difference.
- No restrictions on type, timing, value, or issues of disputes.
- Covers time, money, quality, and workmanship issues.
- “Under the contract” - no statutory right for misrepresentation claims.
- AMEC v. Secretary of State: 7 propositions to define a dispute.
10
Q
s.108(2) - Procedure Complying with Adjudication
A
- Applies to construction contracts with disputes.
- Mandatory requirements in the Act can’t be contracted out.
- Non-compliant contracts default to Scheme for Construction Contracts.
- Procedure must:
a. Allow dispute referral notice anytime.
b. Secure adjudicator appointment within 7 days.
c. Adjudicator to decide within 28 days (or longer if agreed).
d. Adjudicator can extend 28 days by up to 14 days with consent.
e. Adjudicator must act impartially (not necessarily independent).
f. Adjudicator can take initiative in ascertaining facts and law.
11
Q
s.108(3) - Other Key Provisions
A
- Adjudicator’s decision binding in the interim.
- Adjudicator can correct clerical/typographical errors (slip rule).
- Pre-2009 Act: slip rule governed by case law (e.g., Bloor, YCMS, Rok).
- Post-2009 Act: slip rule in Scheme for Construction Contracts.
- Adjudicator may correct slips within 5 days of decision delivery.
- Unclear scope of typographical/clerical errors.
- Caution: Invoking slip rule may abandon right to challenge enforcement (Dawnus case).
12
Q
s.108(4) & s.108(5) - Adjudicator Immunity and Schemes
A
- Adjudicator immune from suit, except in bad faith (s.108(4)).
- Non-compliant contracts default to Schemes for Construction Contracts (s.108(5)).
- Schemes: default rules for England/Wales, Scotland, Northern Ireland.
- Adjudication has become more formal, with detailed submissions.
- Common adjudication issues: payment, EOT, scope, defective/incomplete works.
- Disputes typically adjudicated during contract works, not at the end.
13
Q
Risks of Adjudication
A
- Ambush: unexpected detailed claims/defenses.
- Quality of adjudicator: competence varies, may lead to poor decisions.
- Poor/bad decision: parties stuck with it, recourse to arbitration/litigation.
- Complex disputes: might be better suited for litigation or arbitration.
- Parties often adjudicate during contract, rather than waiting for the end.
14
Q
Adjudication Process
A
- Notice of Adjudication: states dispute, parties, redress sought.
- Appointment of Adjudicator: within 7 days of Notice, agreed or by ANB.
- Referral Notice: detailed case, served within 7 days of Notice of Adjudication.
- Responding Party’s Response: defense to claims, usually within 7-14 days.
- Further Submissions: Reply, Rejoinder, etc., if needed.
- Decision: reached within 28 days, extendable with consent.
15
Q
Adjudicator’s Fees and Parties’ Costs
A
- Losing party generally pays adjudicator’s fees; may be apportioned for mixed results.
- Adjudicator can determine reasonable fees, disputed amounts can be taken to court.
- Parties jointly and severally liable for adjudicator’s fees.
- Each party usually bears its own costs in adjudication.
- “Tolent Clauses” invalidated by 2009 Act; adjudicator can allocate fees and expenses with specific provisions.
- Late Payment of Commercial Debts Act claims for adjudication costs largely disallowed.