CIRT
Confirmed issue resolution tracker
FWT
Factory Witness Test
IST
Integrated Systems Test
DSI
Design Systems Integrator
CSI
Construction Systems Integrator
EPMS
Electrical Power Management System - (form of SCADA) Telecom, power utilities, water, waste control, energy, oil, gas refining
ETL
Equipment Tracking Log
FACNet
Facility Network
EOR
Engineer of Record
SCADA
Supervisory Control and Data Acquisition - Used for monitoring and controlling equipment w/ critical and time sensitive equipment (using PLCs). Used for data acquisition, network data comm., data presentation, control
DCIM
Data Center Infrastructure Management - Manage monitor, measure, control data center utilization and energy consumption of IT related equipment (storage, network switch, servers), PDUs (power distribution units)
CPMS
Critical Power monitoring System - Manage critical power generation and distribution - gen-sets, circuit breakers, transfer switches, bus bars, parallel control switch gears, UPS’, etc
CMOP
Contractor Method of Procedure - submitted via E-Builder
L1 - L5
Phases of Facebook Data Center to turnover a space
L1
FWT and bench tests
i. ATS - PTP, Alarm, trend, SOO, graphic checklist depending on system
ii. Done on all 1st of kind code and graphics - identify issues early on
iii. (2) Weeks - 1st led by CSI, 2nd - led by CxA