Access and Rights L1 (Powers of NR/Utility companies) Flashcards
Describe difficulties of obtaining rights on third party land (negs with landowner)
- Unpredictable, can be very slow
- Often protracted.
- Sometimes refuse to engage or cannot find landowner
Disadvantages of using CPO as a utility company
- Utility companies can bring about a CPO under enabling statue
- Long process and costly
- No guarantee the CPO will be confirmed
- Via Acquisition of Land Act 1981
Name the statutory powers of water companies
Water Industry Act 1991
Describe powers of Water Industry Act 1991
Powers to lay water main or sewer in private land
Carry out future works of inspections, / maintenance / right of entry for surveys
Acquire land interests and rights via acquisition of Land Act 1981
Describe powers under the Water Industry Act 1991
s155 of 1991 Act allows water companies to undertake compulsory acquisition of land for the purpose of carrying out functions – authorise the acquisition of interests in and rights over land
s159 of 1991 Act gives notice of intention to carry out works (laying of pipes) and conveys statutory easement to protect works post construction. Laying of Pipes - usually on Notice of Entry served under s159 on owner and occupier – three months for new works, 42 days for repair on existing infrastructure
Entry for works purposes - s168 - Undertaker can enter any premises for the purposes of carrying out surveys or tests fir the purpose of determining whether it is appropriate and practicable for the undertaker to exercise relevant works power.
S168 sets out conditions when serving notice of entry relating to survey works or installing/monitoring of equipment. 7 days or 24hrs if public health at risk/emergency. Prefer to approach landowners for consent prior to issuing notices.
Describe Compensation of rights acquired under The Water Industry Act 1991 to landowners
- As per compensation code / section 5 of LCA 1961
- If not freehold, basis is the depreciation of the value of the land – recognition payment
- Paid to landowner, not occupier as assumes VP
- Payments sometimes made per structure e.g. per manhole
- Agricultural Land, St Johns College Oxford v Thames Water 1990 - 50% value of the area of the statutory wayleave
Head of Claim for water companies
- Disturbance – crop losses, physical damage, reinstatement costs
- Surveyors fees
- Interest payable from date of entry
Name law relating to statutory powers for gas companies
Gas Act 1986 (1995)
Describe main powers under Gas Act 1986
Schedule 3 – acquisition of land and rights over land for laying of gas pipes and land for pressure reducing stations / gas pumping stations
Enter into Deed of Agreement for rights required – letter of undertaking informs landowner of project and asks for consent to enter into deed of Grant. Consent payment made
Procedure for authorisation outlined in Paragraph 1, Schedule 3 of Gas Act 1986 and Acquisition of Land Act 1981 and CPA 1965.
Gas supplier can serve a 14 day notice to treat to enter for purpose of surveying or doing work – paragraph 10 of Schedule 3
Heads of claim for gas companies
payment for rights, crop loss and severence
Name powers for entry used by railway companies (Network Rail)
British Rail Act 1981 s71
Railway Regulation Act 1982, s14
Transport and Works Act 1992, s53
Describe powers under British Railway Act 1981
British Railway Act 1981, s71
- Powers to carry out surveys, soil tests on land and leaving / removing of apparatus, without having to obtain consent from landowner (prior to using powers, NR would try to negotiate via license)
- For the purpose of determining its suitability for the construction works
- 28 days notice
- Compensation – loss or damages only
- Right for landowner to appeal through court
Describe powers under Railway Regulation Act 1842
Railway Regulation Act 1842, s14
- Powers to enter land adjacent to railway for repairs / slips to ensure public safety. Enabling access and to work upon and for temporary acquisition of private land adjoining railway that is required to undertake the works to safeguard the railway
- SoS consent required via DfT
- 48 hrs notice in emergency cases, 28 days days minimum otherwise. Reactive or Proactive Entry
- Compensation – damages
Describe powers under Transport and Works Act 1992, s53
Transport and Works Act Orders (Under Transport and Works Act 1992)
- made under TWA 1992 providing NR statutory powers to carry out works which are defined in the Order.
- NR does not have general powers to acquire third party land if new powers to construct railway works are required. TWAO can include compulsory purchase of land
TWAO provides (scope for developments is wide – station carparks / new bridges)
- powers to construct and operate railways
- compulsory acquisition rights or land for works and compulsory acquisition of land required temporarily or permanently (environmental mitigation / worksites) – public must benefit from proposals and outweigh the interference with private rights
- deemed planning permission for authorising works
- closures of roads / diversions
Name act that helps electricity companies gain third party access
Electricity Act 1989 -
Right to enter land to replace, repair or alter lines or plant.
Right to compulsorily purchase land.
Right to obtain a necessary wayleave.