ACC CORB Questions Flashcards

1
Q

Why is inspection and acceptance important to the Government? FAR 8.406-2 https://www.acquisition.gov/far/part-8#FAR_8_406_2__d481e10

A

At base, the government’s ability to inspect allows it to identify nonconformities in goods or services and demand correct- time action to bring those goods or services up to the level specified by the government.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain the difference between an offeror’s experience and an offeror’s past performance.

A

Should indicate that experience reflects WHAT an offeror has done (similar to a resume) and past performance reflects HOW WELL the offeror performed the work (similar to a performance appraisal).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A legally binding contract must contain what elements?

A

Must involve two or more parties that have the capacity to contract.
Must show agreement, including offer, acceptance, and mutual assent.
Must show something of value changing hands between the parties to a contract, or other inducement that leads a person to make a promise.
Must be for a legal purpose.
Must be in the correct form.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain the “Bona Fide Needs” rule. https://www.law.cornell.edu/uscode/text/31/1502

A

The bona fide needs rule is a rule of appropriations law. It mandates that a fiscal year’s appropriations only be obligated to meet a legitimate—or bona fide—need arising in (or sometimes before) the fiscal year for which the appropriation was made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the order of precedence for a solicitation or contract in accordance with FAR 52.215-8? For example, the specifications require a different item than is stated in the Schedule (Section B). What does the contractor use?

A

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order: FAR 15.204

  (a) The Schedule (excluding the specifications).

  (b) Representations and other instructions.

  (c) Contract clauses.

  (d) Other documents, exhibits, and attachments.

  (e) The specifications.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Once all receivables have been delivered/completed and verified by the customer/COR, the ACO or KO reviews the contract files for remaining closeout actions. Why is contract closeout so important? What actions need to be taken in closeout? https://www.acquisition.gov/far/part-4#FAR_4_804

A

Extremely important because excess funds may need to be de-obligated; in addition, many types of contracts require the withholding of final payments, which can amount to large sums of money for the Contractor (cash flow issue).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

On a full and open competitive negotiated acquisition, you have received five proposals and determined that discussions are needed, what is the process of determining which offerors are in the competitive range for these discussions?

A

If the Contracting Officer decides that an offeror’ proposal should no longer be included in the competitive range, the proposal will be eliminated from further consideration for award. The Contracting Officer must provide written notice of this decision to unsuccessful offerors in accordance with FAR Part 15.503(a). The notice to each offeror must state (1) the basis for excluding/eliminating it offer, (2) the basis for the determination, and (3) that a revision of its proposal will not be considered.
The Contracting Officer must prepare a written competitive range determination based on all evaluation factors, including a complete rationale for decisions to include or exclude specific proposals from the competitive range. This document is the Competitive Range Determination memorandum.
Did the solicitation state the government could reserve the discussions?
KO should hold discussions for action over 100 million.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If you have a competitive requirement, how will you determine the Best Value Approach to use in regard to choosing LPTA or Tradeoff? Also, give at least one example when each is appropriate.

A

LPTA would be used for simpler supply buys, where price is the most important factor. Lowes price, no tradeoff. Tradeoff would usually be used in more complicated requirements when other factors outweigh cost. Certain qualities are more important to the customer than others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you mentor a new Contract Specialist (recent intern graduate) that has been assigned to your team? What tools would you provide to your specialist in accomplishing their duties? What tools do you use in accomplishing your duties?

A

Conduct an initial counseling that covers duties and expectations. Set goals and priorities. Review and approve their individual Development Plan (IDP), Assign a coach and mentor. I would mentor a new CS assigned to my team by helping them through a common SAT perchase, explaining the steps and procedures involved. I would show them local SOP, Policy Letters, PCF, SAM, FAR site, and WAWF.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is an unauthorized commitment? What steps do you take in evaluating, processing and approving and unauthorized commitment?

A

An unauthorized commitment is means an agreement that is not binding solely because and Government representative who made it lacked the authority to enter into that agreement on behalf of the Government. The act of approving an unauthorized commitment is called a ratification. Unauthorized commitments may be ratified only when the conditions of FAR 1.602-3(c) are met. a) Use of appropriated funds, b) Provided to or accepted by the Government - received a benefit, c) Ratification official has the authority to ratify, d) Resulting contract must otherwise be proper, e) Price must be fair & reasonable, f) Funds are available and were available at the time the action occurred, g) The CO recommends payments, h) It is IAW other requirements and limitations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you envision is the role of your CORs? When are you required to appoint one? What authorities are you allowed to delegate to your COR? What authorities are not delegable to the COR?

A

The KO usually delegates surveillance and status reporting under FAR PART 42. The COR is the eyes and ears of the Contracting Officer. Shall decertified and maintain certification. CORs are not authorized to make commitments. CORs must be a government employees. CORs duties are to promptly inspect services, ID if they meet or do not meet AQL, SAT or UNSAT completion, and complete performance evaluation. The COR accepts and inspects goods and services. At the DoD level, the guidance for when a COR is required to be designated is not tied to a dollar threshold. It requires a more subjective analysis surrounding the risk of contract performance and oversight the government wishes to have. That said, there is guidance for use in making this decision. Unless you have local or agency level policy we are unaware of, the guidance you need can be found at DFARS PGI 201.602-2(iv)(A), which states:
“Contracting officers shall designate a COR for all service contracts, including both firm fixed price and other than firm fixed price contracts, awarded by a DoD component or by any other Federal agency on behalf of DoD. The surveillance activities performed by CORs should be tailored to the dollar value/complexity of the specific contract for which they are designated. Contracting officers may exempt service contracts from this requirement when (each of) the following three conditions are met:
(1) The contract will be awarded using simplified acquisition procedures;
(2) The requirement is not complex; and
(3) The contracting officer documents the file, in writing, why the appointment of a COR is unnecessary.
For cost reimbursement contracts that are not service contracts, contracting officers shall either retain or delegate surveillance activities to a COR or DCMA.”
If there is no COR assigned; then ultimately the contracting officer is responsible for monitoring contractor performance. This makes sense considering that when a COR is appointed it is some of the contracting officer’s authority/responsibility they are being delegated.
What is

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Your contractor presents you with a request for equitable adjustment (claim). Describe your process/steps that you will take in evaluating, processing and approving a claim?

A

First you should notify your attorney that you have received an Request for Equitable Adjustment (REA). Then, you will need to determine whether the contractor’s request has any merit. If you determine that the request has merit, you may attempt to negotiate a settlement with the contractor, involving your attorney as you deem necessary. If negotiating with the contractor is difficult, and the involvement of your program counsel has not helped, you may refer the case to legal for formal Alternative Dispute Resolution (ADR). Formal ADR can be accomplished either before or after the issuance of a final decision. If you determine that the REA is without merit, you may still attempt to discuss the issues with the contractor prior to issuing the PCO’s final decision. Once a stalemate has occurred and the claim can’t be resolved at the PCO level, a final decision is issued, and an appeal is processed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Your customer has submitted a requirement and states that only one source can meet their requirements. Describe your process/steps that you will take in evaluating, processing and approving or rejecting a sole source acquisition? Discuss any differences in the process based on different threshold levels.

A

Market research to confirm market conditions. Document it with a J&A with facts that support sole source. $650 or less KO, $650-12.5MIL competition advocate, 12.5 MIL - $85MIL is the PARC. 6.303-1 –Requirements.
(a) A contracting officer shall not commence negotiations for a sole source contract, commence negotiations for a contract resulting from an unsolicited proposal, or award any other contract without providing for full and open competition unless the contracting officer –and approved on a class basis, the contracting officer must ensure that each contract action taken pursuant to the authority of the class justification and approval is within the scope of the class justification and approval and shall document the contract file for each contract action accordingly.
(e) The justifications for contracts awarded under the authority cited in 6.302-2 may be prepared and approved within a reasonable time after contract award when preparation and approval prior toward would unreasonably delay the acquisitions.
(1) Justifies, if required in 6.302, the use of such actions in writing;
(2) Certifies the accuracy and completeness of the justification; and
(3) Obtains the approval required by 6.304.
(b) The contracting officer shall not award a sole-source contract under the 8(a) authority (15 U.S.C.637(a)) for an amount exceeding $22 million unless–
(1) The contracting officer justifies the use of a sole-source contract in writing in accordance with 6.303-2;
(2) The justification is approved by the appropriate official designated at 6.304; and(3) The justification and related information are made public afterward in accordance with 6.305.
(c) Technical and requirements personnel are responsible for providing and certifying as accurate and complete necessary data to support their recommendation for other than full and open competition.
(d) Justifications required by paragraph (a) above may be made on an individual or class basis. Any justification for contracts awarded under the authority of 6.302-7 shall only be made on an individual basis. Whenever a justification is made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you determine the most appropriate contract type? Give examples of when you would use the different types.

A

A wide selection of contract types is available to the Government and contractors to provide needed flexibility in acquiring the large variety and volume of supplies and services required by agencies. Contract types vary according to: (1) The degree and timing of the responsibility assumed by the contractor for the costs of performance, and (2) The amount and nature of the profit incentive offered to the contractor for achieving or exceeding specified standards or goals. (b) The contract types are grouped into two broad categories, fixed-price contracts, cost-reimbursement contracts. The specific contract types range from firm-fixed-price, in which the contractor has full responsibility for the performance costs and resulting profit (or loss), to cost-plus-fixed-fee, in which the contractor has minimal responsibility for the performance costs and the negotiated fee (profit) is fixed. In between are the various incentive contracts in which the contractor’s responsibility for the performance costs and the profit or fee incentives offered are tailored to the uncertainties involved in contract performance. There are many factors that the contracting officer should consider in selecting and negotiating the contract type. They include the following: (a) Price competition. Normally, effective price competition results in realistic pricing, and fixed-price contract is ordinarily in the Government’s interest. (b) Price analysis. Price analysis, with or without competition, may provide a basis for selecting the contract type. The degrees to which price analysis can provide a realistic pricing standard should be carefully considered. See FAR 15.404-1(b) (c) Cost analysis. In the absence of effective price competition and if price analysis is not sufficient, the cost estimates of the offeror and the Government provide the basis for negotiating contract pricing arrangements. It is essential that the uncertainties involved in performance and their possible impact upon costs be identified and evaluated, so that a contract type that places a reasonable degree of cost responsibility upon the contractor can be negotiated. (d) type and complexity of the requirement. Complex requirements, particularly those unique to the Government, usually result in greater risk assumption by the Government. This is especially true for complex research and development contracts, when performance uncertainties or the likelihood of changes makes it difficult to estimate performance costs in advance. As a requirement recurs or as quantity production begins, the cost risk should shift to the contractor, and a fixed-price contract should be considered. (e) Combining contract types. If the entire contract cannot be firm-fixed-price, the contracting officer shall consider whether or not a portion of the contract can be established on a firm-fixed-price basis. (f) Urgency of the requirement. If urgency is a primary factor, the Government may choose to assume a greater proportion of risk or it may offer incentives tailored to performance outcomes to ensure timely contract performance. (g) Period of performance or length of production risk in times of economic uncertainty, contracts extending over a relatively long period may require economic price adjustment or price redetermination clauses (h) Contractor’s technical capability and financial responsibility (I) Adequacy of the contractor’s accounting system. Before agreeing on a contract type other than firm-fixed-price, the contracting officer shall ensure that the contractor’s accounting system will permit timely development of all necessary cost data in the form required by the proposed contract type.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you determine a prospective contractor to be responsible? Are there any differences in that process for contracts under the SAT versus contracts exceeding the SAT? If so, what are they?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Your contract requires a modification. Address the different types of modifications that could be executed. Describe the steps you would take in executing the modification and include in your discussion the different modification authorities and what documentation would be necessary to support the modification action.

A

A D&F is a prerequisite for modification, extension, and ratification.
Change Order: Any written change in the terms and scope of the contract. These changes can be in the specifications, drawings, designs, method of packaging or shipment, time or place of delivery, and quantity or type government provided material. Unilateral order signed by the KO (Based on the changes Clauses) Quantities may not be unilaterally adjusted by the changes clause. Commercial contras cannot be changed unilaterally. Changes cannot exceed limitation of costs and funds and must be within the scope of the contract.
Three things needed to execute an option: 1. Need2. Funds available 3. Option is advantageous to the GOV
Administrative Change: Unilateral changes not affecting substantive rights of the parties. These changes to paying office, name of KO, contracting office. Etc.
Constructive Change: occurs when the contract work is actually changed but the procedures of the change clause have not been followed. Same effects a formal change order. An increased burden of the contractor is compensable. Example, contractor fails to complete project with in the specified date and time, and the government allows work to continue without approval. Bilateral changes a retreated as a sole source and require a J&A
How do you determine whether or not a change is within scope?
The FAR itself does not provide a definition of “scope.” Instead each determination is made on a case-by-case basis. Over the years the GAO and the federal courts have articulated a number of factors that can guide the Contracting Officer’s scope determination. The primary consideration whether a potential offeror (in the original procurement) would have reasonably anticipated that this type of change would occur. To quote the U.S. Court of Appeals for the Federal Circuit (in AT&T Communications, Inc. v. Wiltel, Inc., 1 F.3d 1201 (Fed. Cir. 1993)) the question is “whether the solicitation for the original contract adequately advised offerors of the potential for the type of changes during the course of the contract that in fact occurred, or whether the modification is of a nature which potential offerors would reasonably have anticipated.”
In 2012 the Court of Federal Claims (in American Apparel, Inc., v. U.S., No. 12-293 C) reviewed the facts in a number of cases and summarized some questions that the Contracting Officer should consider in making the determination of whether potential offerors could reasonably have anticipated the change:
· Does the modification substantially change the type of work, performance period and costs as between the original contract and the modified contract?
· Is it essentially the same performance or not?
· Is there a lack of resemblance to the original procurement?
· Is there a significant addition or subtraction of the quantity of work?
· Is there additional time spent on performance of the contract when such time is extended in order to add significantly more quantity or new requirements to the contract?
These examples are not all-inclusive, so we encourage you to consult with your legal counsel on your specific situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describe the different types of terminations available. Address both non commercial (FAR Part 49) and commercial (FAR PART 12) terminations. Discuss the termination procedures and remedies (if any) of each type of termination.

A

There are three types of terminations.
1. Termination for default (T4D). Two types. 1. Any default (actual breach) 2. Anticipatory breach
2. Termination for Cause (T4Cause) A T4Cause andT4C are for commercial contracts.
3. Termination for Convenience settlement agreement, no dispute.
Reasons to terminate for convenience: Lack of funds, in the best interest of the Government, change in situation or technology.
A small business termination must be reported to the SBA.
T4C Best interest no breach.
All payments stop at termination.
An improper T4D is settled as if it was aT4Convenience.
No cure notice needed past delivery date.
Show cause sent after due date, may be used but not required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Discuss your understanding of SAM (System for Award Management Exclusions) and how / when it is to be utilized.

A

SAM is an official website of the U.S. government. SAM consolidated the capabilities of CCR/FedReg, ORCA, and EPLS. SAM is always utilized to validate the contractors Certs and Reps. Contractors must be registered in SAM to contract with the Federal government.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

You have received a sole source proposal. How would you determine the price to be fair and reasonable. Address any differences when dealing with different dollar thresholds, contract type, etc. (i.e., cost analysis and/or price analysis).

A

It depends on the threshold and if it is a commercial buy and if there is sufficient competition. We always do a price analysis but not a cost analysis unless it is non-commercial and or above the TINA threshold of$750K. I would use the IGCE, conduct MR, look at previous similar efforts and draw on my experience. The complexity, contract value and type of the effort would determine how much effort I would put forth. Cost Analysis would be for a cost type contract and price analysis would be for FFP. The FAR provides guidance for the requirements information included in the J&A. Pursuant to FAR6.302 there are limited circumstances that allow for contracting using other than full and open competition. These are:
1. 6.302-1– Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements.
2. 6.302-2– Unusual and Compelling Urgency.
3. 6.302-3– Industrial Mobilization; Engineering, Developmental, or Research Capability; or Expert Services.
4. 6.302-4– International Agreement.
5. 6.302-5– Authorized or Required by Statute.
6. 6.302-6– National Security.6.302-7– Public Interest.
There are three types of competition: 1. Full and Open 2. Full and Open after exclusion of sources 3.Other than full and open sources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

You have received competitive proposals in an LPTA situation. How would you determine the prices to be fair and reasonable.

A

Through the competition of the technically acceptable proposals. 1) Make a determination if lowest offeror offer is technically acceptable -move to award or 2) if the lowest price is not technically acceptable then move on to the next lowest offeror…The prudent Contracting Officer must be able to support the determination of fair and reasonable in a manner to which they are willing to put their signature. There is a large degree of discretion for the Contracting Officer in this area, so what in their judgment meets the standard?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

You have received competitive proposals in a trade-off situation. You are required to evaluate realism as well as the reasonableness of the cost/price. How would you evaluate each of these.

A

Realism analysis under the FAR is used to determine “whether your low price reflects a lack of understanding of contract requirements or risk inherent in your technical approach. “Reasonableness analysis during source selection evaluations is typically conducted to determine whether your price is too high. Cost realism analysis Shall be performed on Cost-reimbursement contracts. May be used in competitive fixed price incentive contracts. Must be the probable cost of contract performance developed in cost realismanalys is to determine best value. May also use cost realism as a factor in evaluating offers understanding of contract technical requirement and risk.

21
Q

When are you required to synopsize contract actions? Discuss both the solicitation as well as contract award. Address the differences (if any) between synopsis and posting a solicitation. Also, address some of the exceptions to synopsis.

A

​Synopsis req’d if > $25K.
Synopsis is posted 15 days before the Solicitation is posted.
FAR 5.202 has exceptions including, but not limited to, Unusual and Compelling Urgency, if the Synopsis posting would compromise national security, for utility services.
For commercial items, you may use a combined synopsis and solicitation procedure (see 12.603).

22
Q

Address the importance of acquisition planning. What are some things that you, as a KO, can do to assist the customer in acquisition planning? Additionally, discuss when formal acquisition planning is required.

A

To ensure that the Government meets its needs in the most effective, economical, and timely manner. An acquisition plan is required at the following thresholds: $50M or more for production or services for all years, or $25M or more for any fiscal year; $10M or more for development. FAR part 7. Start working as soon as a need is identified. it is a team effort, but it is created by the RA. Are we going to create a well-defined requirement.

23
Q

When do you perform market research, why is it necessary, and how is it documented? Describe some of the market research techniques.

A

​To check for SB, mandatory list, priority provider, we have a template provided for market research. Techniques include:
1. Contacting knowledgeable individuals in Government and industry regarding market capabilities to meet requirements.
2. Reviewing the results of recent market research undertaken to meet similar or identical requirements.
3. Publishing formal requests for information in appropriate technical or scientific journals or business publications.
4. Querying the Government-wide database of contracts and other procurement instruments intended for use by multiple agencies and other Government and commercial databases that provide information relevant to agency acquisitions.
5. Participating in interactive, on-line communication among industry, acquisition personnel, and customers.
6. Obtaining source lists of similar items from other contracting activities or agencies, trade associations or other sources.
7. Reviewing catalogs and other generally available product literature published by manufacturers, distributors, and dealers or available on-line.
8. Conducting interchange meetings or holding pre-solicitation conferences to involve potential offerors early in the acquisition process.

24
Q

When is certified cost and pricing data required? What are the exceptions to certified cost and pricing data?

A

The threshold for obtaining certified cost or pricing data is $750,000. Unless an exception applies, certified cost or pricing data are required before accomplishing the award of any negotiated contract, The award of a subcontract at any tier, if the contractor and each higher-tier subcontractor were required to furnish cost or pricing data, or the modification of any sealed bid or negotiated contract expected to exceed the current threshold or, in the case of existing contracts, the threshold specified in the contract. Exceptions to certified cost or pricing data include: adequate price competition, prices are set by law or regulation, when acquiring a commercial item, a waiver has been granted, or when modifying a contract or subcontract for commercial items.

25
Q

How do you determine if a small business category is applicable to your procurement? What documentation is needed to support this determination? What are different categories in the small business program?

A

Refer to FAR Part 19. To determine the correct Subcategory, I would talk to my SB POC and get an approved DD 2579. The FED GOV’s policy is to maximize practicable opportunity in its acquisitions to small businesses. The goal is to award 23% of contracts to small businesses. Small businesses must be registered as such with the SBA. The categories of small businesses are 8(a) Small Disadvantaged Business (members of a disadvantaged group: African American, Hispanic, Asian, Native American, woman, or veteran owned). Small Business Programs, only applies to contracts in the Unites States or its outlying areas? See FAR 19.000(b).However, FAR 19.6, Certificates of Competency and Determinations of Responsibility apply to contracts worldwide when dealing with U.S. small business concerns.

26
Q

One of your specialists is new to contracting policies and procedures and asks you to explain a “D&F”. How would you describe a D&F?

A

1.704Content. Each D&Fshallset forth enough facts and circumstances to clearly and convincingly justify the specific determination made. As a minimum, each D&Fshallinclude, in the prescribed agency format, the following information:(a)Identification of the agency and of thecontracting activityand specific identification of the document as a “Determination and Findings.”(b)Nature and/or description of the action being approved.(c)Citation of the appropriate statute and/or regulation upon which the D&F is based.(d)Findings that detail the particular circumstances, facts, or reasoning essential to support the determination. Necessary supporting documentationshallbe obtained from appropriate requirements and technical personnel.(e)A determination, based on the findings, that the proposed action is justified under the applicable statute or regulation.(f)Expiration date of the D&F, if required (see1.706).(g)Thesignatureof the official authorized to sign the D&F (see1.707) and the date signed. A prerequisite to taking certain contracting actions. The “determination” is a conclusion or decision supported by the “findings”. Determination and Findings” means a special form of written approval by an authorized official that is required by statute or regulation as a prerequisite to taking certain contract actions. The “determination” is a conclusion or decision supported by the “findings.’’ The findings are statements of fact or rationale essential to support the determination and must cover each requirement of the statute or regulation.

27
Q

If a contractor is included on the List of Parties Excluded from Federal Procurement and No procurement Programs, what are the rules on continuation of current contracts with the contractor?

A

Authority: FAR 9.405 – 1. Agencies may continue contracts or subcontracts in existence at the time the contractor was debarred, suspended, or proposed for debarment unless the agency head or a designee directs otherwise. 2. Ordering activities may continue to place orders against existing contracts, including indefinite delivery contracts, in the absence of a termination. 3. Agencies shall not renew or otherwise extend the duration of current contracts (i.e. exercise options), or consent to subcontracts, unless the agency head or a designee authorized representative states, in writing, the compelling reasons for renewal or extension.

28
Q

What is the difference between price and cost analysis?

A

Price analysis - involves overall evaluation of total price without evaluating its separate cost elements or profit and is required for all acquisitions. Based essentially on data that is obtained from sources other than the prospective KTR. Cost Analysis - involves review and evaluation of each separatecost element to include profit/fee.

29
Q

Describe the Anti-deficiency Act (ADA) and list some actions that would constitute a violation of it. What are the potential penalties for a violation of the ADA?

A

The Anti-deficiency Act means that Government officials have no authority to obligate or spend funds unless the funding is available prior to the obligation occurring. Some of the violations of the ADA include: a. Obligation in excess of available funds. b. Expenditure in excess of available funds. c. Involving the Government in a contract or obligation in advance of appropriations. d. Improper augmentation of appropriations e. Accepting most voluntary services. Administrative discipline including suspension without pay and removal from job, criminal prosecution (if knowing and willful violation) - up to two years imprisonment and $5,000 fine, and the contract may be declared null and void, although the contractor may still be owed compensation.

30
Q

You are a PCO and a new trainee comes to you seeking advice. The trainee states that he/she just had a conversation with the resource manager who referred to funds categorized by status as either active, expired, or cancelled. The trainee doesn’t understand the differences. Can you explain the differences between the 3 status categories?

A
  1. Active - appropriation is available for obligation & disbursement. 2. Expired - Appropriations expire for new obligations at the end of the period for which they were appropriated, but are available to adjust and liquidate previous obligations for a 5 year period (available for disbursement, not new obligations). 3. Cancelled - no longer available for any purpose. Expired appropriations are cancelled at the end of the 5th full fiscal year following expiration.
31
Q

What are some of the benefits of competition? What are some barriers to competition?

A

Benefits of competition: 1) drives cost savings, 2) improves quality of product/service, 3) enhances solutions and the industrial base, 4) promotes fairness and openness leading to public trust, 5) prevents waste, fraud, and abuse, because KTR’s know they must perform at a high level or else be replaced, 6) increases likelihood of efficiencies and innovations Keys to Effective Competition: 1) gather information from relevant sources in and outside the organization to support : a) commercial product/service that meet minimum requirement and mission needs: b) expand insight into commercial marketplace, 2) Use results to determine if: a) if capable sources exists, b) availability of commercial and/or non-developmental items

32
Q

The COR has reported to you that the contractor has failed to deliver a service per the contract requirements. What actions should you take as the Contracting Officer in this instance?

A

​Contact the customer/COR first to confirm that the services were not performed. Would reach out to the contractor to understand why the services weren’t performed, i.e.: Fact finding. The goal is to ensure that no one on the Government side provided direction that they did not have the authority to direct the contractor and to get the contractor’s story. From there, we have a couple of options, assuming no Gov’t direction was provided. 1. Could issue a cure notice, which gives the contractor 10 days to cure the failure, if they do not, I could terminate for default. That is pretty aggressive, especially if we still need the services because getting another contractor in would obviously result in a break of service. The second approach would be to send a PCO letter and ask them for consideration for an extension in order to complete the performance. The consideration is usually monetary, but other possibilities could be discussed. For either scenario, legal would also have to be involved.

33
Q

As Contracting Officer, you have a unique role when it comes to representing the United States of America. Please take a minute or two to describe this unique role, paying particular attention to your allegiance to the US Government versus the contractor in decisions regarding tax-payer dollars.

A

The candidate should discuss in general terms the role and responsibility of a Contracting Officer (e.g., 1) The only person who can bind the US Government; 2) Must be fair and impartial, (etc., etc.). I think it important that the candidate also touch on the fact that they are to look at and consider both sides of every situation (US Government and industry) and make decisions on a fair, ethical, and impartial basis, not siding on the side of the US Government (customer) simply because they are employed by same.

34
Q

As Contracting Officer, how do you view guidance versus policies versus regulations versus laws or statutes?

A

The candidate should clearly articulate their position to uphold laws and statutes at any cost. The candidate’s answer regarding the differences between the remaining items should help the Board determine the knowledge, experience, maturity, risk-taking level, and acceptability of the candidate with respect to using these resources in making decisions.

35
Q

What part of the FAR covers “Cost Accounting Standards (CAS)”, what are they, and when do they apply?

A

FAR Part 31 and Appendix 1 cover CAS. CAS represents a consistent way to handle costs in accordance with Public Las 100-679. CAS applies to larger negotiated contracts awarded to large businesses. [FAR AP-1, 9901.306, Standards Applicability: Cost Accounting Standards promulgated by the Board shall be mandatory for use by all executive agencies and by contractors and subcontractors in estimating, accumulating, and reporting costs in connection with pricing and administration of, and settlement of disputes concerning, all negotiated prime contract and subcontract procurements with the United States Government in excess of the Truth in Negotiations Act (TINA) threshold, as adjusted for inflation (41 U.S.C. 1908 and 41 U.S.C. 1502(b)(1)(B)), other than contracts or subcontracts that have been exempted by the Board’s regulations.]., CAS applies to larger negotiated acquisitions awarded to large businesses.]

36
Q

Please describe what is meant by an “Unsolicited Proposal” according to FAR 15.6, and explain in basic terms the relationship between full and open competition and the acceptance of an unsolicited proposal.

A

An Unsolicited Proposal (UP) is a essentially a proposal submitted by industry that is not in response to a US Government request. UPs allow unique and innovative ideas or approaches that have been developed outside the Government to be made available to Government agencies for use in accomplishment of their missions. Unsolicited proposals are offered with the intent that the Government will enter into a contract with the offeror for research and development or other efforts supporting the Government mission, and often represent a substantial investment of time and effort by the offeror. There are many discriminators used in validating a UP. If in the end the UP has received a favorable comprehensive evaluation, providing for full and open competition is still required unless a justification and approval has been obtained under Subpart 6.3 [see FAR 15.607]

37
Q

What is VCE PCF and why is it important? As a contracting officer, what steps will you take to personally ensure data being reported is accurate?

A

It is the repository for the contract file. It hold all the documents that for that actions. The KO verifies that supports the actions. RPA holds accountability.

38
Q

What would be some of the reasons where the Contracting Officer would need to provide written consent before a prime contractor is allowed to enter into a subcontract?

A

If the contract exceeds 150K and a subcontracting opportunity exists. In addition, a MOD or new working excess of $150K. Not required for personal service contracts, small business, or OCONUS.
44.201-1 -Consent requirements.
(a) If the contractor has an approved purchasing system, consent is required for subcontracts specifically identified by the contracting officer in the subcontracts clause of the contract. The contracting officer may require consent to subcontract if the contracting officer has determined that an individual consent action is required to protect the Government adequately because of the subcontract type, complexity, or value, or because the subcontract needs special surveillance. These can be subcontracts for critical systems, subsystems, components, or services. Subcontracts may be identified by subcontract number or by class of items (e.g., subcontracts for engines on a prime contract for airframes).

39
Q

What is a Quality Assurance Surveillance Plan (QASP) and when is it required?

A

The Quality Assurance Surveillance Plan (QASP) is Used in Performance Based Service Contracts to assess contractor performance. Required for contracts in excess of $2,500 IAW the Service Contract Act. The Performance Work Statement (PWS) is the heart of a service acquisition. It describes the requirement in terms of measurable outcomes. Acceptable Quality Level (AQL) is what the contractor needs to accomplish to get paid.
When a COR is appointed for contracts, a surveillance plan (QASP) shall be prepared, unless specifically exempted in writing by the contracting officer? See page 2 of DASA(P) Memo dated Oct 212010 titled “Post Award Oversight and Surveillance of Contracts”.
Quality assurance surveillance plans (QASPs) should describe how the COR will monitor the contractor’s performance regarding trafficking in persons such that non-compliance with FAR Clause 52.222-50,Combating Trafficking in Persons, is brought to the immediate attention of the KO? See DFARS 222.1703and PGI 222.1703.
DFARS 246.401 provides, in part, “for contracts for services, the contracting officer should prepare equality assurance surveillance plan to facilitate assessment of contractor performance.”
DFARS 237.172, in turn, directs that “these plans should be tailored to address the performance risks inherent in the specific contract type and the work effort addressed by the contract.”

40
Q

How do you determine what clauses to include in a solicitation / contract?

A

By using the Clause Matrix in FAR 52.3 Provisions and clauses Matrix and incorporating clauses as directly by local policies. It depends on the contract type (Commercial vs. noncommercial), If the contract has option years, Inclusion of GFP, OCONUS Contracts. FAR Clause 52.222-50,”Combating Trafficking in Persons” is required in all solicitations and contracts? See FAR 22.1705(a). The KO shall insert FAR Clause 52.237-2, Protection of Government Buildings, Equipment, and Vegetation, in solicitations and contracts for services to be performed on Government installations? Prescription

41
Q

What is unbalanced pricing, and how should you address it?

A
42
Q

Explain the difference between suspension and debarment FAR 9.404.

A

Suspension is temper cannot exceed 12 months during legal action look up / Debarment is permeant. Excludes them for all actions for up to three years. Cause or reason. Excludes from contracts or subcontract.

43
Q

What is an organizational conflict of interest as it relates to contractor (or provider) access to acquisition information? Give an example.

A

FAR 9.5

44
Q

What is the difference between and Agency Protest and a GAO protest?

A

Agency is local and they are not the discovery documents (35 day). GAO is Higher and they have 110 day, or 65 for an expedited. GAO will give them discovery documents. Within 10 day after award or the reason for the protest is known. After a debrief it is 5 days

45
Q

What is the difference between and Agency Protest and a GAO protest?

A

Agency is local and they are not the discovery documents (35 day). GAO is Higher and they have 110 day, or 65 for an expedited. GAO will give them discovery documents. Within 10 day after award or the reason for the protest is known. After a debrief it is 5 days

46
Q

Describe a Cure Notice and when you would use one as a KO. FAR 49.607 Delinquency Notice. 12.403(c)

A

​If a contract is to be terminated for default before delivery date, a “cure notice” is required by the Default clause. Before using this notice, it must be ascertained that the amount of time equal to or greater than the period of “cure” remains in the contract delivery schedule or any extension to it. If the amount of time remaining in the contract delivery schedule is not sufficient to permit a “cure” period of 10 days or more, the Cure
Notice should NOT be issued, instead a “Show Cause Notice” may be issued.

47
Q

Explain the difference between severable and non-severable services

A

A severable service is a service that can be separated into components that independently meet a separate need of the government. As a general rule, severable services are the bona fide needs of the fiscal year in which performed, however, DoD agencies may award severable services contracts that cross fiscal years, provided they do not exceed one year in duration. A non-severable service is a service that produces a single or unified outcome, product, or report that cannot be subdivided for separate performance in different fiscal years. Thus, the government must fund the entire effort with dollars available for obligation at the time the contract is executed, and the contract performance may cross fiscal years.

48
Q

When would you use a bilateral modification versus an unilateral modification?

A

Bilateral modifications are negotiated changes such as delivery schedule change, funding change, significant change to the SOW, etc. A unilateral modification can be issued for administrative changes, change orders within the general scope of the contract, termination notices, etc. If the contract has an option (to extend the contract, to purchase additional supplies or services, etc.) the contract should have an option clause in it and then the option can be exercised unilaterally. Numerous modification authorities (and associated clauses) exist for modifications such as Engineering changes, changes to usage of government property, funding changes, etc. The Changes Clauses (52.243-X) allow for unilateral modifications.

49
Q

How do you determine whether or not a change is within the scope of the contract?

A

In general, a modification is considered to be outside the scope of an existing contract when there is a “material difference” between the contract as modified and the contract as it existed before the modification. The rule is to examine any changes in the type of work, performance period and costs between the contract as awarded and as modified. The PCO must look at the Acquisition Plan, the Scope of Work (SOW), the Pricing Negotiation Memorandum (PNM), Justification & Approval (J&A), to determine if the change was contemplated by the parties at the time of contract award. Neither dollar amount nor quantity of changes is sole determinations deciding whether a change is in or out of scope. The proposed change must also be evaluated with the consideration as to whether it would have significantly affected the original competition (more or different offerors, different technical approaches in the proposals, use of commercial items, etc.). the KO needs to determine if the offerors could have reasonably anticipated the requested change if the the change would have significantly impacted the competition and if it would be a CICA violation.