8- Methods of Inspection Flashcards

1
Q

Before entering or re-entering any tank, appropriate safety precautions are necessary. These precautions are discussed in detail in ,,,,,,,,

A

API 2015 and API 2016

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Prior to conducting internal or external inspection, the inspector should thoroughly review any available ,,,,,,

A

inspection records
previous problems and
recommendations noted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In preparation for inspection, it is important that all personnel working in the area and any who may enter the area be informed that ,,,,,,,,

A

personnel will be working in the tank

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Anchor bolt nuts should be checked for a …….

A

snug fit to the anchor chair top plate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

For ground connection, . The

total resistance from tank to earth should …….

A

not exceed approximately 25 ohms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Corrosion under insulation (CUI) is most aggressive in temperature ranges between ,,,,,,,,

A

120 °F (49 °C) and 200 °F (93 °C)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In obtaining shell thickness, special attention should

be given to the ,,,,,,,of uncoated shells of floating-roof tanks

A

upper 24 in. (61 cm)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Modern ultrasonic ,,,,,, when properly calibrated, allow direct metal thickness readings to be taken through thinfilm coatings.

A

multi-echo thickness scopes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If caustic or amine is stored in a tank, the tank should be checked for evidence of damage from caustic stress
corrosion cracking, sometimes referred to as ,,,,,,,,

A

caustic embrittlement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

On a fixed roof, planks long enough to span at least ,,,,,,,, should be laid and used as walkways

A

two roof rafters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Electrical shunts, if present, should be checked to ensure adequate contact between the ,,,,,,,

A

floating roof and the shell

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Drainage systems on floating roofs should be inspected frequently for ,,,,,,

A

leakage or blockage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

,,,,,,, measurement equipment, which can provide accurate thickness through thin-film coatings, should be used wherever possible

A

Multi-echo ultrasonic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When external piping inspection is specified, the soil around the pipe should be dug away for ,,,,,,,to allow for inspection, as soil corrosion may be especially severe at such points.

A

6 in. to 12 in. (150 mm to 300 mm)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Coupons approximately ,,,,,,, in size can also be removed from the roof to check for under-side corrosion and rafter condition

A

12 in. × 12 in. (300 mm × 300 mm)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

although the best way to find leaks in the roof is with the ,,,,,, test discussed later in this document.

A

low-pressure air

17
Q

The drain lines, including the joints, can also be tested for any leak. The first stage is a test at about ,,,,,,, gauge pressure for approximately,,,,,,, to detect any leaks in the pipe, hose, or rigid joints. The pressure is then reduced to approximately ,,,,,, gauge for another ,,,, hour to test the tightness of the swing joints

A

30 lbf/in.2 (207 kPa) for 1/2 hour

5 lbf/in.2 (34.5 kPa) for 1/2 hour

18
Q

For tank bottom inspection, A minimum ,,,,,,,, halogen light is usually adequate

A

100-watt

19
Q

For tank bottom inspection, ,,,,,, are the most common but hybrid MFL/Eddy Current, ,,,,,,,,and well as ultrasonic based may also be used

A

Magnetic Flux leakage (MFL) scanners

Saturate Low frequency Eddy Current *SLOFEC)

20
Q

For tank hydro/leak tes, approximately ,,,,,, hours may be required for leaks to become evident

A

24 hours

21
Q

If water is not available and if the roof of the tank is reasonably air tight or can be made so, a carefully controlled air test using air pressure ,,,,,,,of water pressure may be applied.

A

not exceeding 2 in. (0.50 kPa)