8 - Critical Path Analysis Flashcards

1
Q

Define dependency.

A

When an activity can’t proceed until another is completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define precedence/dependence table.

A

A table showing which activities must be completed before others are started.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type of activity network do you use?

A

Activity on arc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define events.

A

Completion of activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the arcs and nodes on this type of activity network?

A

Arcs - activities.
Nodes - events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does each arc have?

A

.Activity letter label.
.Beginning/end at ends of arc.
.Arrow - direction.
.Straight line conventionally.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you draw an activity network?

A

.First node, labelled 0 is the source node.
.Number each node added to the network.
.Last node is the sink node.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a dummy activity?

A

No time/cost and shows dependency - dotted lines.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the two reasons to use a dummy activity?

A

.Show dependencies.
.Uniquely represented in terms of its events - one between any two events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define duration.

A

Length of time an an activity takes to complete - add arc weights.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define EET.

A

Earliest time of arrival at an event in which all preceding activities are completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Define LET.

A

Latest time an event can be left without extending the time needed for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you calculate EET?

A

Start from 0 at source nose and complete a forward pass towards sink node - Largest sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you calculate LET?

A

Start at sink node and complete a backward pass towards the source nose - smallest sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly