60 Compensation Events Flashcards
60.1 (1)
The Project Manager gives an instruction changing the Works Information: except
- a change made in order to accept a Defect or
- a change to the Works Information provided by the Contractor for his design which is made either at his request or to comply with other Works Information provided by the Employer.
60.1 (2)
The Contractor does not allow access to and use of a part of the site by the later of its subcontract access date and the date shown on the accepted programme.
60.1 (3)
The Contractor does not provide something which he is to provide by the date for providing it shown on the accepted programme.
60.1 (4)
The Contractor gives an instruction to stop or not to start any work or to change a key date.
60.1 (5)
The Employer, the Contractor, or Others:
- do not work within the times shown on the accepted programme,
- do not work within the conditions stated in the subcontract works information, or
- carry out work on site that is not stated in the subcontract works information.
60.1 (6)
The Contractor does not reply to a communication from the subcontractor within the period required by this subcontract.
60.1 (7)
The Contractor gives an instruction for dealing with an object of value or of historical importance or other interest found within the site.
60.1 (8)
The Contractor changes a decision which he has previously communicated to the subcontractor.
60.1 (9)
The Contractor withholds an acceptance(other than acceptance of a quotation for acceleration or for not correcting a defect) for a reason not stated in this subcontract.
60.1 (10)
The Contractor instructs the Subcontractor to search for a defect and no defect is found unless the search is needed only because the subcontractor gave insufficient notice of doing work obstructing a required test or inspection.
60.1 (11)
A test or inspection done by the Contractor or the Supervisor causes unnecessary delay.
60.1 (12)
The Subcontractor encounters physical conditions which
- are within the Site
- are not weather conditions and
- an experienced subcontractor would have judged at the Subcontract Date to have such a small chance of occurring that it would have been unreasonable for him to have allowed for them.
60.1 (13)
A weather measurement is recorded:
- within a calendar month,
- before the Completion Date for the whole of the works and
- at the place stated in the Contract Data
the value of which, by comparison with the weather data, is shown to occur on average less frequently than once in ten years.
Only the difference between the weather measurement and the weather which the weather data show to occur on average less frequently than once in ten years is taken into account in assessing a compensation event.
60.1 (14)
An event which is an Employer’s or a Contractor’s risk stated in this subcontract.
60.1 (15)
The Contractor certifies take over of a part of the subcontract works before the Completion and the Subcontract Completion Date.
60.1 (16)
The Contractor or the Employer does not provide materials, facilities and samples for tests and inspections as stated in the Subcontract Works Information.
60.1 (17)
The Contractor notifies a correction to an assumption which he has stated about a compensation event.
60.1 (18)
A reach of subcontract by the Contractor which is not one of the other compensation events in this subcontract.
60.1 (19)
An event which:
- stops the Subcontractor completing the subcontract works or
-stops the Subcontractor completing the subcontract works by the date shown on the Accepted Programme,
and which
- neither Party could prevent,
- an experienced subcontractor would have judged at the Subcontract Date to have such a small chance of occurring that it would have been unreasonable for him to have allowed for it and
- is not one of the other compensation events stated in this subcontract.