5.3 Test Monitoring, Test Control, and Test Completion Flashcards
Which tool can be used by an agile team to show the amount of work that has been completed and
the amount of total work remaining for a given iteration? (5.3.3 / K2)
a) Acceptance criteria
b) Defect report
c) Test completion report
d) Burndown chart
Select ONE option.
d) Burndown chart
Which of the following pieces of information contained in a test progress report is the LEAST useful
for business representatives? (5.3.2 / K2)
a) Impediments to testing
b) Branch coverage achieved
c) Test progress
d) New risks within the test cycle
Select ONE option.
b) Branch coverage achieved
Which TWO of the following options are common metrics used for reporting on the quality level of
the test object? (5.3.1 / K1)
a) Number of defects found during system testing
b) Total effort on test design divided by the number of designed test cases
c) Number of executed test procedures
d) Number of defects found divided by the size of a work product
e) Time needed to repair a defect
Select TWO options.
a) Number of defects found during system testing
d) Number of defects found divided by the size of a work product
FL-5.3.1 / K1 (Recall metrics used for testing)
C
FL-5.3.2 / K2 (Summarize the purposes, content, and audiences for test reports)
C
FL-5.3.3 / K2 (Exemplify how to communicate the status of testing)
A