.52 Karl Flashcards
What order defines required coordination with ATC and specifies standard flight check terminology?
The 8240.41.
What phraseology should be used with ATC to describe the ILS-1, 2, and 3 maneuvers respectively?
“Flight Inspection Arc,” “Flight Inspection Holding Pattern,” “Flight Inspection Low Approach”
In the .52, altitudes referenced are true unless specified otherwise. When flight inspecting an instrument flight procedure, the aircraft is considered “on altitude” if it is within 100 feet of the planned true altitude. On non-precision final approaches, when would we have to correct altitudes to true?
When the temperature deviation exceeds ISA +/- 15 or the altimeter setting source is beyond 15NM.
Should we attempt to restrict or remove from service when an OT condition is found?
Restrict.
If a NOTAM is issued, how long does the PIC have to verify issuance?
24 hours.
What appendix describes the procedures for FIDEX?
14
When a commissioning inspection is performed prior to the completion of runway construction activities, what should be done by the flight inspector?
A special inspection should be performed after completion of the runway work, before the facility is placed into service. The inspector should request the special inspection unless in the flight inspector’s judgement, the remaining work is negligible and no special is required. Document all conditions in the DFL.
What should be done when equipment is replaced with the same type and configuration as the former and located on the same physical site, including antenna location?
A special check is required, applicable items for antenna change in the relevant chapter must be accomplished as a minimum. Additional requirements will be jointly determined by the flight inspector and facilities maintenance.
What priority is after accident?
1A
What is a reconfiguration?
A special inspection when modifications or relocation affect the radiation pattern of the facility.
Is an antenna type change a reconfiguration?
Yes, antenna changes to a different type must be classified as reconfiguration. All commissioning checks should be performed following a reconfiguration, except those that are not required as determined jointly by flight inspection and mx personnel. Commissioning tolerances must be applied.
In general, what type of reporting is required on surveillance inspections?
OT or unsat findings. Discrepancies require DFL, report, and, if necessary, notam action. See Appendix 12 for surveillance on VGSI (they’re probably supposed to be documented with a V for surveillance).
What priority does a system become when it has exceeded the end of the due date window?
1a
What happens if you cannot complete all SIAPs during a periodic inspection?
The periodic inspection will be considered complete. Specials must be established to ensure the remaining SIAPs are completed. In the event SIAPs are not checked by the end of the window/extension, FICO must initiate a NOTAM to remove the procedure from service and it will be restored by a special flight inspection.
How long may navaids and SIAPs be extended beyond their due dates respectively?
7 days, 30 days. They take on the same priority as an overdue Navaid or procedure.
On a periodic inspection, what if standby equipment or an associated navaid is not inspected due to out-of-service condition or if it’s removed from service to due an uncorrectable discrepancy?
The periodic inspection will be considered complete. The standby equipment or associated NAVAID must be restored to service by the successful completion of a flight inspection which satisfies all periodic requirements (including monitors, where applicable).
What happens if ground or airborne receiver checkpoints cannot be completed on a periodic or special Rho-Theta inspection.
The inspection must be considered complete. Enter in Remarks those checkpoints not checked. FICO will schedule a special to complete the checkpoints within the facility periodicity and will take appropriate NOTAM action if they are not inspected in that time.
Must monitors be inspected on every periodic for ILS with GS? Loc only?
Yes, every other periodic
What should be done if one unit of a dual equipped facility is found out-of-tolerance?
It must be identified and removed from service.
What must be done if standby power is installed after the commissioning flight inspection?
Standby power must be checked during the next regularly scheduled periodic inspection. Standby power checks are not required on facilities when the facility is powered by batteries that are constantly charged by another power source or to be rechecked when the standby power source is changed.
Can you remove published spectrum management restrictions based on flight inspection results?
No
If an inspection on a commissioned facility is halted in an abnormal condition due to aircraft malfunction, weather, etc. and maintenance handbooks allow adjustments of the facility parameter without flight check, can the equipment may be returned to service?
Yes, inspection is incomplete.
When a prescribed checklist item cannot be adjusted within tolerance, what must happen?
The inspection will be terminated, facility status changed to unusable, and the inspection classified as incomplete until the remainder of the checks are complete.
What is required if localizers or glideslopes are transmitting HMI?
The glideslope or localizer must be off. This does not apply to routeine monitor checks. These actions are backed up by NOTAM action that must be verified by someone other than the notam initiator.