5. Construction Drawings & Specifications Flashcards

1
Q

For construction drawings, what is the most effective way to communicate large amounts of complex information in a small space?

A. schedules
B. power plan
C. key plan
D.CMP Chart

A

A. schedules

Explanation: Schedules are a very efficient way to communicate a large amount of complex information in a relatively smalls space.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You are specifying for a health care system who will be using a solution-dyed antimicrobial carpet in a custom pattern and colors for use in some of the corridors.
What type of specification should you use?

A.reference
B. descriptive
C. Masterspec
D. proprietary

A

B. Descriptive

Explanation: In this scenario, the specification must meet both performance and design criteria, without mentioning trade or brand names (proprietary). The best type of specification is a descriptive spec.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type of specification would be the best to include in the bid documents to ensure your client’s concerns are addressed?

A. proprietary specification
B. descriptive specification
C. base - bid specification
D. performance specification

A

C. base - bid specification

Explanation: Because a base-bid spec is a type of prescriptive spec and basically an expanded proprietary spec, it ensures the designer truly understands the difference as well as the concerns of the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the phrase “or approved equal” mean in a specification?

A. the interior designer and client can permit the substitution of an alternate product if they feel it is better than the one specified.
B. the contractor may propose a substitution, but it must be approved by the interior designer
C. the client must agree to the use of a product selected by the contractor
D. an alternative product may be bid on by the contractor if he or she is sure it provides the same quality as the product

A

B. the contractor may propose a substitution, but it must be approved by the interior designer

Explanation: Both the interior designer and client must agree to the use of a contractor-selected product. The alternative product must be reviewed and approved by the interior designer, not just the contractor. The intent of the “or approved equal” language is to permit equal products, although sometimes the alternative does turn out to be better than the one specified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Your client has indicated that they would like to incorporate a sustainable rooftop garden and water collection system in the redesign of their office building.
What drawing would you need to begin work on this feature?

A. as built plan
B. site plan
C. exterior elevation
D. reflected ceiling plan

A

B. site plan

Explanation: A site plan is a view of a building as seen from directly above, showing the roof of the building, as well as the surrounding yards, walks, driveways, and other features

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does a section detail show in addition to the cut plane?

A

This type of detail drawing also shows a partial elevation in that it indicates what is beyond the main view plane.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an open dimension and why it is used?

A

This is an undimensioned distance in a string dimension on a floor plan. It is used to accommodate any slight variation caused by the distance being established by other dimensions or existing construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the four most common schedule types for interior design projects?

A

The most common are for finishes, doors, kitchen equipment and millwork.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a match line?

A

This term is used to describe where two portions of a large floor plan drawn on two sheets would be joined if combined on one large sheet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How can the interior designer verify that an outlet is a dedicated outlet?

A

The interior designer can look at the electrical engineer’s power plan to determine if this type of outlet is on a separate circuit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does a reflected ceiling plan show?

A

This drawing type shows all items that are part of the ceiling, elements that touch the ceiling, and elements that penetrate the ceiling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In regard to construction drawings, what does an elevations show?

A

This type of drawing shows vertical dimensions and the configurations and finishes of wall surfaces.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a title block?

A

This is the area of a drawing sheet that contains identifying information about the project as well as information specific to that particular sheet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

For a large commercial remodeling project, where is a demolition plan typically placed in the drawing set?

A

This plan is placed before the construction plan for large commercial remodeling projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are two ways to show partition types on a construction floor plan?

A

Flag notes and patterns can be used to show these on a construction floor plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why are enlarged floor plans used?

A

These are used to show construction elements, dimensions, and other annotations that could not be shown on a small-scale plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is shown on the reflected ceiling plan that is also shown on the fire protection plan?

A

Sprinklers are shown on this plan as well as on the fire protection plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What does a typical floor plan show?

A

This type of drawing shows the overall configuration of a building (or portion of an interior under contract). It includes all partitions, doors, and other fixed elements and gives dimensions, notes, and references to elevations and details drawn elsewhere.

19
Q

What are construction drawings?

A

These are detailed drawings the contractor uses to construct a project and describe the extent of the work and the locations, dimensions and relationships of the various construction elements.

20
Q

What type of gypsum wallboard must be used for fire rated partitions?

A

Type X gypsum wallboard

21
Q

What is a schedule?

A

This is a presentation of information in tabular format with rows and columns of data.

22
Q

What is the purpose of an approved equal type of specification?

A

This is used to state a desired product in a specification section but allow for possible alternates submitted by the contractor.

23
Q

What surfaces are typically shown on a finish schedule?

A

Floor, base, wall, and ceiling materials

24
Q

How is a finish plan different from a finish schedule?

A

Finish plan consists of a separate floor plan with notations indicating wall, base and floor finishes. Finish schedule consists of a tabular listing of finishes using room numbers to identify the rows of the schedule.

25
Q

What system was created to standardize the organization and writing of specifications, and what group developed it?

A

The Master Format system was developed by the Construction Specifications Canada to accomplish this.

26
Q

Individual specification sections of the CSI MasterFormat system are divided into three parts. What broad subjects do these three parts cover?

A

Part 1, General
Part 2, Products
Part 3, Execution

27
Q

In regard to electrical drawings, what is a home run?

A

This is a graphic element on an electrical drawing that uses arrowheads to indicate that the line joining lights or power outlets is connected to a particular circuit breaker in a particular electrical panel box.

28
Q

What is a project manual?

A

This is a bound book that contains:

  • technical construction specifications
  • contract forms
  • general and supplementary conditions of the contract
  • bidding requirements
  • supplemental bid forms
29
Q

What is detailing in interior design?

A

This is the process of determining a design’s technical requirements - that is, how the individual components will fit together and exactly how they will look.

30
Q

What is used to fit a cabinet tightly to an irregular wall?

A

A scribe piece is used for this.

31
Q

How would the interior designer determine what circuit a particular outlet is connected to?

A

The interior designer would look at the home run designations on the electrical engineer’s power plan to determine this.

32
Q

Why is the term “reflected” used for a reflected ceiling plan?

A

This term is used to indicate that this plan has the same orientation as the construction plan.

33
Q

In addition to location, a typical construction floor plan shows what two pieces of information for partitions?

A

The thickness and type of partition are shown on this drawing.

34
Q

How is the MasterFormat system organized?

A

This system for standardizing specifications is organized into major subgroups and individual divisions within each subgroup.

35
Q

What distinguishes reveal overlay cabinetry from other types of cabinetry?

A

With this type of cabinet construction, the edges of adjacent drawer and door fronts are separated (rather than being very close together) to distinctly show the face frame behind.

36
Q

What should be included on the furniture plan to refer to detailed furniture information?

A

Code numbers that refer to a furniture schedule or furniture specifications can be included on this plan.

37
Q

What is sometimes shown on a furniture plan in addition to furniture and furniture key notes?

A

Electrical and telephone outlets are sometimes shown on this interior designer’s drawing.

38
Q

Under what circumstances would the electrical engineer develop a telephone/ communication plan separate from a power plan?

A

When a project has a large number of electrical outlets, computer outlets, telephone jacks, and other communication outlets the electrical engineer would provide these two separate plans.

39
Q

Who is responsible for coordinating the reflected ceiling plan with the electrical engineer’s lighting plan?

A

The interior designer is responsible.

40
Q

When producing construction drawings for a house remodeling, what type of plan would probably not be necessary?

A

Demolition Plan

41
Q

In regards to construction drawings, what is layering?

A

This is the method of placing different information on separate levels in a CAD system when creating a construction drawing.

42
Q

What should be included on the reflected ceiling plan to refer to more detailed luminaire information?

A

Code numbers that refer to a luminaire schedule should be included on this plan.

43
Q

At what scale should the reflected ceiling plan be drawn?

A

This plan should be drawn at the same scale at the construction floor plan.