47+ Work Processes Flashcards

1
Q

Which Group Does ‘Selecting Project Manager’ Belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which Process Group Does ‘Determining Company Culture and Existing Systems’ Belong To?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which Process Group Does ‘Collect Process, Procedures and Historical Information’ belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which Process Group Does ‘Divide Large Projects into Phases’ belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which Process Group Does ‘Understand the Business Case’ Belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which Process Group Does ‘Uncover Initial Requirements, Assumptions, Risk, Constraints and Existing Agreements’ Belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which Process Group Does ‘Assess Project and Product Feasibility Within Given Constraints’ Belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which Process Group Does ‘Create Measurable Objectives’ Belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which Process Group Does ‘Develop Project Charter’ Belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which Process Group Does ‘Identify Stakeholders and Determine their Expectations, Influence and Impact’ Belong to?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which Process Group Does ‘Plan How You Will Plan for Each Knowledge Area’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which Process Group Does ‘Determine Detailed Requirements’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which Process Group Does ‘Create Project Scope Statement’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which Process Group Does ‘Assess What to Purchase and Create Procurement Documents’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which Process Group Does ‘Determine Planning Team’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which Process Group Does ‘Create WBS and WBS Dictionary’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which Process Group Does ‘Create Activity List’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Which Process Group Does ‘Create Network Diagram’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Which Process Group Does ‘Estimate Resource Requirements’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Which Process Group Does ‘Estimate Time and Cost’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Which Process Group Does ‘Determine Critical Path’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Which Process Group Does ‘Develop Schedule’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Which Process Group Does ‘Develop Budget’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Which Process Group Does ‘Develop Quality Standards, Processes and Metrics’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Which Process Group Does ‘Create Process Improvement Plan’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Which Process Group Does ‘Determine all Roles and Responsibilities’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Which Process Group Does ‘Plan Communication and Stakeholder Engagement’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Which Process Group Does ‘Perform Risk Identification, qualitative and quantitative risk analysis and Risk response planning’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Which Process Group Does Go back, iterations’’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Which Process Group Does ‘Finalize Procurement Documents’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Which Process Group Does ‘Create Change Management Plan’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Which Process Group Does ‘Finalize the How to Execute and Control Parts of Mgmt Plans’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Which Process Group Does ‘Develop Realistic and Final PM Plan and Performance Measurement Baseline’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Which Process Group Does ‘Gain Formal Approval of Plan’ Belong To?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Which Process Group Does ‘Hold Kickoff Meeting’ Belong To?

A

Planning

36
Q

Which Process Group Does ‘Executing the Plan According to the PM Plan’ Belong To?

A

Executing

37
Q

Which Process Group Does ‘Produce Product Deliverables(Product Scope)’ Belong To?

A

Executing

38
Q

Which Process Group Does ‘Gather Work Performance Data’ Belong To?

A

Executing

39
Q

Which Process Group Does ‘Request Changes’ Belong To?

A

Executing

40
Q

Which Process Group Does ‘Implement Only Approved Changes’ Belong To?

A

Executing

41
Q

Which Process Group Does ‘Continuously Improve’ Belong To?

A

Executing

42
Q

Which Process Group Does ‘Follow Processes’ Belong To?

A

Executing

43
Q

Which Process Group Does ‘Determine Whether Processes are Correct and Effective (Quality Assurance)’ Belong To?

A

Executing

44
Q

Which Process Group Does ‘Perform Quality Audits’ Belong To?

A

Executing

45
Q

Which Process Group Does ‘Acquire Final Team’ Belong To?

A

Executing

46
Q

Which Process Group Does ‘Manage People’ Belong To?

A

Executing

47
Q

Which Process Group Does ‘Evaluate Team and Individual Performance’ Belong To?

A

Executing

48
Q

Which Process Group Does ‘Hold Team Building Activities’ Belong To?

A

Executing

49
Q

Which Process Group Does ‘Give Recognition Awards’ Belong To?

A

Executing

50
Q

Which Process Group Does ‘Use Issue Logs’ Belong To?

A

Executing

51
Q

Which Process Group Does ‘Facilitate Conflict Resolution’ Belong To?

A

Executing

52
Q

Which Process Group Does ‘Release Resources as Work is Completed’ Belong To?

A

Executing

53
Q

Which Process Group Does ‘Send and Receive Information and Solicit Feedback’ Belong To?

A

Executing

54
Q

Which Process Group Does ‘Report on Project Performance’ Belong To?

A

Executing

55
Q

Which Process Group Does ‘Manage Stakeholder Engagements and Expectations’ Belong To?

A

Executing

56
Q

Which Process Group Does ‘Hold Meetings’ Belong To?

A

Executing

57
Q

Which Process Group Does ‘Select Sellers’ Belong To?

A

Executing

58
Q

Which Process Group Does ‘Take Action to Control the Project’ Belong To?

A

Monitor and Control

59
Q

Which Process Group Does ‘Measure Performance Against the Performance Measurement Baseline’ Belong To?

A

Monitor and Control

60
Q

Which Process Group Does ‘Measure Performance Against other Metrics in the PM plan’ Belong To?

A

Monitor and Control

61
Q

Which Process Group Does ‘Analyze and Evaluate Performance’ Belong To?

A

Monitor and Control

62
Q

Which Process Group Does ‘Determine if Variances Warrant a Corrective Action or Other Change Request’ Belong To?

A

Monitor and Control

63
Q

Which Process Group Does ‘Influence the Factors that Causes Changes’ Belong To?

A

Monitor and Control

64
Q

Which Process Group Does ‘Request Changes’ Belong To?

A

Monitor and Control

65
Q

Which Process Group Does ‘Perform Integrated Change Control’ Belong To?

A

Monitor and Control

66
Q

Which Process Group Does ‘Approve or Reject Changes’ Belong To?

A

Monitor and Control

67
Q

Which Process Group Does ‘Update PM Plan and Project Documents’ Belong To?

A

Monitor and Control

68
Q

Which Process Group Does ‘Inform Stakeholders of the Results of Change Requests’ Belong To?

A

Monitor and Control

69
Q

Which Process Group Does ‘Monitor Stakeholder Engagement’ Belong To?

A

Monitor and Control

70
Q

Which Process Group Does ‘Manage Configuration’ Belong To?

A

Monitor and Control

71
Q

Which Process Group Does ‘Create Forecasts’ Belong To?

A

Monitor and Control

72
Q

Which Process Group Does ‘Gain Acceptance of Interim Deliverables from Customer’ Belong To?

A

Monitor and Control

73
Q

Which Process Group Does ‘Perform Quality Control’ Belong To?

A

Monitor and Control

74
Q

Which Process Group Does ‘Perform Risk Reassessments and Audits’ Belong To?

A

Monitor and Control

75
Q

Which Process Group Does ‘Manage Reserves’ Belong To?

A

Monitor and Control

76
Q

Which Process Group Does ‘Control Procurements’ Belong To?

A

Monitor and Control

77
Q

Which Process Group Does ‘Confirm Work is Done to Requirements’ Belong To?

A

Closing

78
Q

Which Process Group Does ‘Complete Procurement Closure’ Belong To?

A

Closing

79
Q

Which Process Group Does ‘Gain Final Acceptance of Product’ Belong To?

A

Closing

80
Q

Which Process Group Does ‘Complete Financial Closure’ Belong To?

A

Closing

81
Q

Which Process Group Does ‘Complete Financial Closure’ Belong To?

A

Closing

82
Q

Which Process Group Does ‘Hand Off Completed Product’ Belong To?

A

Closing

83
Q

Which Process Group Does ‘Solicit Feedback from the Customer About the Project’ Belong To?

A

Closing

84
Q

Which Process Group Does ‘Complete Final Performance Reporting’ Belong To?

A

Closing

85
Q

Which Process Group Does ‘Index and Archive Records’ Belong To?

A

Closing

86
Q

Which Process Group Does ‘Gather Final Lessons Learned and Update Knowledge Base’ Belong To?

A

Closing