411 Flashcards
AUTHORITY
Authority at a hazmat incident is derived from
Interagency hazardous materials response
-Which defines the general responsibilities of respondent agency
The Jacksonville fire and rescue department has the authority with a few exceptions to assume command of any hazardous material incident: Exceptions are: 3
Marine incident under jurisdiction of the US Coast Guard
Incident on military bases
Nuclear incident such as plane crashes involving nuclear weapons
The first arriving agency will take command until
A more appropriate Coordinator/incident commander arrive
When a call is received indicating a possible hazmat incident if FRCC will attempt to obtain information regarding incident is involved including: 6
- Name
- Amount
- Type
- Size container
- Type of problem
- Property Of the reporting material
Once confirmation of a hazmat incident has been established the IC Will advise if FRCC
Make required notifications as needed
EMRD, STATE WARNING POINT, COAST GUARD, DOT
COMMAND
-Establishing into the command is required by federal law is not an option
Person in charge of the first arriving unit will- established command,And they will advise are responding units with the staging if possible a safer route to the incident location
Safety officer must be designated to monitor operations. This is required by federal law is not an option
SIZE UP
The critical aspect of the response to A hazmat incident is the
Initial size up of the situation
Upon arrival of the first unit, there are certain factors/conditions that must be taken into account before any commitment of Jeopardy personnel. These are: 4
-Wind conditions and direction
Topography the incident location
-Area of involvement(open or confined space)
-Type of materials involved (solid, liquid, or vapor)
-Hazards of the materials involved
The objective of size up is to the following reasons:3
- Identify product involved
- Assess the nature and severity of the problem
- Gathered sufficient information to formulate a valid incident action plan
HAZARD IDENTIFICATION:
A primary consideration in the size of any hazmat incident is the…..
This is a prime responsibility of the……
Identification of materials involved in hazards present
First arriving you
To help identify the hazard personnel so check for the following: (6)
- Labels
- placards
- Shipping papers
- Material safety data sheets(MSDS)
- Find and talk to the driver possible
SCENE ASSESSMENT:
Follows size up and consideration of the first arriving company officer should be:
- The need for the hazardous Materials team
- Scene management
INCIDENT ACTION PLAN:
-Incident action plan begins with a thorough on scene analysis by the first arriving company officer.
-Formulated the incident action plan utilizing the following priorities:
4
- Safety for jfrd personnel
- Unless rescue is required that IC should not commit personnel to the hot zone until decontamination capabilities are available
- Work in pairs - Safety of civilians
- Begin evacuation/rescue of civilians that are downwind of fumes, vapors, and/or runoff
- Secure Hazard area with barriers
- Provide medical assistance As needed
- Patients May need to be decontaminated for transport - Conservation of property
- Minimize the amount of property damage
- Dike for ventilate materials away from persons and property - Control/stabilization of incident
- Primary effort should Be made to minimize the escape of hazardous materials
- Direct and run off to a safehold area
- Dissipating Vapors
Defensive
- Diluting materials
- Neutralizing substance
- Plugging for shutting off leak
Offensive
ZONING
Immediately after identifying the hazard, ___ shall be Established
Control zones
Zoning will be divided into three distinct areas determined by
Hazmat team