4.1 Develop Project Charter

A
  1. Project Charter

2. Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

4.2 Develop Project Management Plan

A
  1. Project management plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

4.3 Direct & Manage Project Work

A
  1. Deliverables
  2. Work Performance Data
  3. Issue Log
  4. Change requests
  5. Project Management Plan updates
  6. Project documents updates
  7. OPA updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4.4 Manage Project Knowledge

A
  1. Lessons Learned register
  2. Project Management Plan updates
  3. OPA updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

4.5 Monitor & Control Work

A
  1. Work performance reports
  2. Change requests
  3. Project Management Plan updates
  4. Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

4.6 Perform Integrated Change Control

A
  1. Approved change requests
  2. Project Management Plan updates
  3. Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

4.7 Close Project or Phase

A
  1. Project documents update
  2. Final product, service, or result transition
  3. Final report
  4. OPA updates