4. Total Development Costs Flashcards

1
Q

What are the different forms of development costs?

A

Site preparation
Planning costs
Building costs
Professional fees
Contingency
Marketing costs & fees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe some site preparation costs

A

Demolition, site clearance, levelling.

Obtain a contract’s cost plan for these works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Describe some planning costs

A

TCPA (Section 106 payments) - Affordable housing (set out in local planning policy)
Section 278 payments for highway works
CIL - Charge by most LPAs (see planning notes)
Planning application fees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Describe some sources of building costs

A

Estimate of total building costs from:

Client information (for a development appraisal)
Quantity surveyor estimate
BCIS (usually based on GIA) - obtains updated from QS/BS sources and recent contract prices/tenders agreed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Describe some professional fee costs

A

10% - 15% plus VAT of construction costs:

Architects (Usually the largest proportion of total fees)
Project managers
CDM Principal Designer costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Describe contingency

A

5% - 10% of construction costs depending on level of risk and likely movement in building costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe some marketing & fees

A

Sale fee: around 1% - 2% GDV
Letting fee: around 10% of annual rent

Other fees include cost of EPC