4. Integration management Flashcards

0
Q

What is the initiating process?

A

Develop project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

How many processes are in integration management?

A

6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the planning process?

A

Develop project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the executing process?

A

Direct and manage project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the first monitoring and controlling process?

A

Monitor and control project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the second monitoring and controlling process?

A

Perform integrated change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the closing process?

A

Close project or phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the three types of meetings?

A

Information exchange.
Brainstorming.
Decision making.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which is the only process to output work performance reports?

A

4.4 monitor and control project work