4: Earned Value Analysis Flashcards
What does EVA use to measure project performance?
Planned cost
Actual cost
Earned value
What is planned cost sometimes referred to as?
Budgeted cost of work scheduled (BCWS)
What is actual cost sometimes referred to as?
Actual cost of work performed (ACWP)
What is earned value sometimes referred to as?
Budgeted cost of work performed (BCWP)
What is the formula for cost variance?
Earned Value (EV) - Actual Cost (AC)
What is the formula for schedule variance?
Earned Value (EV) - Planned Cost (PC)
What is the formula for Cost Performance Index (CPI)
CPI = Earned Value / Actual Cost
What is the formula for Schedule Performance Index (SPI)
SPI = Earned Value / Planned Cost
How do you interpret CPI & SPI?
If the index values are less than 1.0, then the project is lagging behind, if the values are greater than 1.0, then the project is outperforming the plan.
What is the formula for forecasting the final cost?
Final Cost = Budgeted Cost / CPI
What is the formula for forecasting the final duration?
Final Duration = Original Duration / SPI
What are the limitations to EVA? (3)
- Assumes money is spent linearly and prorated based on time (not the case).
- Costs in terms of money spent is accurate, however, judgement of task or project progress are subjective and therefore so are costs associated with the schedule.
- Predictions for the future are based on extrapolations of what has occurred so far. Often what has happened does not represent accurately what will happen in the future.
What should you comment on when asked to give your views on the health of a project at a certain point? (5)
- Stage of the project
- Whether delay is critical or not
- Whether under/over cost or time is insurmountable or not
- Any CE’s or loss in profit due to over spend/time
- If more data should be captured at this stage
Describe in greater detail what should be considered when talking about the health of a project if the project is at an early stage.
At an early stage any overspend or overrun may be due to weather or unexpected conditions. The existing trend may not be representative of the future trend.
Describe in greater detail what should be considered when talking about the health of a project if the project is delayed.
Whether delay is to critical tasks or not. The SPI being negative does not necessarily mean the total project duration will be extended, as non-critical tasks may be delayed.
This is a weakness of SPI tracking.