4 - BIDDING AND BID DEPOSITORY Flashcards

1
Q

Implementing the chosen procurement route through to the selection of the contractor / supplier and the establishment of basis for contract

A

BIDDING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Usually referred also as “Tendering”

A

BIDDING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

type of bidding where bids are usually based on complete design

A

Single Stage Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

type of bidding where bids based on partially developed consultant design

A

Two Stage Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

type of bidding where contractors assists with final development of design and tender documents

A

Two Stage Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

type of bidding where first stage bidder may bid / negotiate second construction stage

A

Two Stage Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

type of bidding where contractors invited to bid for a contract through advertisements

A

Open Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

type of bidding that can result to a large number of unsuitable firms bidding for the work

A

Open Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

type of bidding that can result in wasted time and effort in selection process

A

Open Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

type of bidding where best prices by firms wanting to establish themselves

A

Open Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

type of bidding where consultants / clients will normally have a list of contractors who undertake different types of contracts

A

SELECTIVE BIDDING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Most common arrangement because it allow price to be the deciding criterion

A

SELECTIVE BIDDING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

type of bidding where Contractors are invited to bid on their proven record in relation to the type and size of contract and their reliability

A

SELECTIVE BIDDING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

type of bidding where one contractor is approached

A

Negotiated Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

type of bidding that is used mainly for specialist work, such case there are limited number of contractors to do the work in the market

A

Negotiated Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

type of bidding that is based on one to one discussion with contractor

A

Negotiated Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

type of bidding where bids are invited from a selected list on the basis of a typical bill of quantities

A

Serial Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

type of bidding where the contractor chosen normally submits the lowest price who undertakes to enter into a series of contracts to carry out the work using the rates in the Bill of Quantities

A

Serial Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

type of bidding where method reduces the bid costs and normally results in contractors quoting low rates in order to obtain a guaranteed program of work

A

Serial Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

type of bidding that usually for repetitive minor works

A

Serial Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

type of bidding that can escalate to partnering agreement

A

Serial Bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

10 ELEMENTS OF A COMPLETE BIDDING SYSTEM

A
  • bid advertisement
  • invitation to bid
  • pre qualification
  • document distribution
  • addenda notification and distribution
  • creation of the bid form
  • submission of bid security
  • submission of the bid
  • bid tabulation
  • audit trail
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

If the project is not by invitation only it is important to be able to notify interested bidders that there is an opportunity to bid on. Public agencies are often mandated to advertise publicly.

A

Bid Advertisement

24
Q

For when there are bidders who are to be proactively advised of the opportunity. In addition to the ability to simply ‘send a message’ the system must help organize and manage the list of potential bidders.

A

Invitation to bid

25
For some projects the bidders must demonstrate their competence and ability to complete the work prior to being invited to submit a bid.
Prequalification
26
Distributing the drawings, specifications and any supplementary information is an essential element of the process. If properly integrated into the system there is no possibility of missing or incomplete information being used in the formulation of a bid submission.
Document Distribution
27
All bidders must be quickly notified of any new addenda and be provided quick and easy access to the information to avoid delays or errors in the submission of bids.
Addenda Notification and Distribution
28
including all the varied elements that make up a construction bid at a minimum including; base bid, separate prices, alternate prices, unit prices, cash allowances, stipulated sums, tax clauses, bond requirements, time to completion, labour units and other required schedules.
Creation of the Bid Form
29
an integral and essential element of a complete bid submission and must be able to be included as part of the bid package.
Submission of Bid Security
30
It must include the ability to; apply for and receive a bid bond, complete sections of the bid as the information is available and ready to enter, allow others in their company to work on the submission if required, withdraw the bid prior to closing time if required and of course enter all required elements of the bid call.
Submission of the Bid
31
Once the bid closing time had been reached the recipient must be able to easily compare and evaluate the information. A tabulated set of bid responses is the most efficient means to do so and is an essential element of the complete bidding process.
Bid Tabulation
32
A complete and accurate log of all the activities required to complete this process is essential to assist in avoiding and resolving issues of non-compliance or claims arising from missing or incomplete information. Knowing exactly who saw what and when it happened helps avoid many of the problems that arise following submission of the bids.
 An Audit Trail
33
Creation of Bid Documents content
``` Approved Budget for the Contract Instruction to Bidders Terms of Reference Eligibility Requirements Plans and Technical Specifications ```
34
The Invitation to Bid shall contain
A brief description of the subject of procurement A general statement on the criteria to be used Approved Budget for the Contract Source of funds Period and place of availability of Bidding Documents Contract duration Other necessary information deemed relevant Invitation for a pre-bid conference
35
At least one (1) pre-bid conference shall be conducted for each procurement.
RA 9184 | Section 22
36
What happens in a PRE-BID CONFERENCE?
Attended by Procuring Entity/Owner’s Representatives Project Manager to discuss the Project Brief Distribution of Bid Documents Site Visit and Inspection
37
All Bids shall be accompanied by a Bid security, which shall serve as a guarantee that, after receipt of the Notice of Award, the winning bidder shall enter into contract with the Procuring Entity within the stipulated time and furnish the required performance security.
RA 9184 | Section 27
38
The BAC shall determine the eligibility of prospective bidders based on the bidders’ compliance with the eligibility requirements
RA 9184 | Section 23
39
A bid shall have two components, the technical and financial components, which should be in separate sealed envelopes submitted simultaneously. Bids shall be received by the BAC on such date, time and place specified.
RA 9184 | Section 25.
40
A bidder may modify his bid, provided that this is done before the deadline for the receipt of bids
RA 9184 | Section 26
41
The BAC shall publicly open all bids at the time, date, and place specified in the bidding documents
RA 9184 | Section 29
42
The BAC shall publicly open all bids at the time, date, and place specified in the bidding documents.
RA 9184 | Section 29
43
Prior to Bid Evaluation, the BAC shall examine first the technical components of the bids using "pass/fail" criteria to determine whether it contains all bid requirements for the technical component.
RA 9184 | Section 30
44
The ABC shall be the ceiling or upper limit of bids. Bid prices exceeding this ceiling shall be outright disqualified from further evaluation. There shall be no lower limit.
Ceiling Price
45
Post-qualification is the stage where the bidder with the LCB or HRB undergoes verification and validation whether he passed all the requirements and conditions as specified in the Bidding Documents.
RA 9184 | Section 34
46
There shall be failure of bidding if: No bids are received No bid qualifies as the LCRB or HRRB When the bidder with the LCRB or HRRB refuses, without justifiable cause, to accept the award of contract.
RA 9184 | Section 35
47
to prevent questionable practice of bid peddling (shopping of subcontractors prices) by the main contractors
BID DEPOSITORY
48
Open bid process scenario
Stage 1: suppliers bid to subtrades Stage 2: subtrades bid to subcontractors Stage 3: subcontractors bid to main contractors
49
buy packages of specially printed envelopes (color-coded and in pairs) from the bid depository office (or BDO)
Subcontractor
50
addressed to main contractor whom he wishes his bid to go (separate envelopes for each main contractor, if necessary)
first envelope
51
addressed to the BDO
second envelope
52
submit sealed envelopes to the bid depository office (usually __ hours) before the closing of bid
48
53
time-stamps the receipt of the subcontractor envelopes
Bid depository office
54
forwards (to authority who called for the bids) list of names of subcontractors who properly deposited
Bid depository office
55
picks up their respective packages of envelopes (usually a day before closing of bid and after receipt of envelopes by BDO)
Main contractor
56
analyze subcontractor quotations received
Main contractor
57
select from among the subcontractor prices and use this for their bid
Main contractor