3.3.4 Critical path analysis Flashcards
1
Q
What is the critical path?
1
A
- Series of activities which take the longest to complete
2
Q
What is float time?
1
A
- Any slack time available attached to an activity
3
Q
How do you calculate float time?
1
A
- LFT (of activity) - duration (of activity) - EST (of activity)