Q
What is network analysis ?
A
Management technique to aid decision making
2
Q
What is network analysis also known as ?
A
Critical path analysis
3
Q
What does a critical path always start and end with ?
A
A node
4
Q
What does EST stand for?
A
Earliest Start Time
5
Q
What does LFT stand for?
A
Latest Finish Time
6
Q
What is the critical path?
A
The activities which carry no float time
i.e the activities which must be completed on time otherwise they will delay the whole project