Q

What is network analysis ?

A

Management technique to aid decision making

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is network analysis also known as ?

A

Critical path analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does a critical path always start and end with ?

A

A node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does EST stand for?

A

Earliest Start Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does LFT stand for?

A

Latest Finish Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the critical path?

A

The activities which carry no float time

i.e the activities which must be completed on time otherwise they will delay the whole project