304 Flashcards
What is meant by initial verification and why is it carried out?
The first time that inspection, testing and certification of new work is carried out. This is to verify that all requirements of the design specification and regulations have been met.
During which 2 stages of an installation is inspection carried out?
During erection and on completion
What is the purpose of the inspection?
To verify that the correct equipment has been selected and erected and that it is not damaged or defective so as to impair safety
List 5 supply characteristics which must be recorded on the Electrical Installation Certificate
Any 5 from: Earthing arrangement, number of live conductors, type of live conductors, nominal voltage, nominal frequency, Ze, Ipf, Supply Protective Device and rating.
State the correct names of the 2 documents which must accompany an Electrical Installation Certificate.
Schedule of Circuit Details, and Schedule of Test Results
What do the letters IP stand for?
International Protection
State the 2 alternative IP codes for enclosures generally
IPXXB or IP2X
State the 2 alternative IP codes for horizontal top surfaces of enclosures
IPXXD or IP4X
In the code IP4X, what is the relevance of the X?
This means no protection specified.
What would an enclosure rated as IP56 be protected against?
Ingress of dust and jets of water
A new conduit system is to be inspected prior to the cables being installed. The conduit extends over some 30m of wall and supplies a number of socket-outlets.
Complete the table below, stating 5 items that should be checked before the cables are installed, what is being checked for and the human sense to be used in each case.
Item number -> What item is being checked -> What is the item being checked to confirm? -> Human sense used
1 -> Saddles -> Sufficient mechanical support and saddles appropriately spaced -> Sight
2 -> Saddle fixings -> Security of fixing -> Touch
3 -> Inspection bends/boxes -> Sufficient number of inspection boxes to allow ease of drawing in cables -> Sight
4 -> Correct size of conduit -> Sufficient capacity for number of conductors -> Sight
5 -> Joints -> Joints securely made -> Touch
Appropriate type of conduit to comply with specs and environment, no screw threads showing, galvanising spray used, deburring -if for steel conduit. and for either metal or plastic conduit checking that no damage was visible. See GN3 for a comprehensive list of other possibilities.
State the instrument used to carry out the following tests:
i) A continuity test on a main protective bonding conductor
ii) An earth electrode resistance test for a generator on a construction site
iii) An earth electrode resistance test on a TT installation protected by an RCD
i) Low resistance ohmeter
ii) Earth electrode resistance tester
iii) Earth fault loop impedance tester
An insulation resistance test is to be carried out on a low voltage lighting circuit
i) State the test voltage and minimum acceptable result, including the units
ii) What action should be taken with lamps and switches prior to test?
i) 500 VDC and 1 M Ohm
ii) Lamps out, switches on -operate 2-way switching if present.
Briefly describe the 3 steps of the ring final circuit test, with the reason for each step
1) End to end, confirm a ring exist in all 3 conductors
2) X-connect L-N and measure at each socket, verify that each point is connected to the ring and identify any spurs
3) As for 2 but with L and CPC, record highest measured value as (R1+R2)
The value of r1 in a ring final circuit wired in 2.5/1.5 mmˆ2 T&E cables is .45 ohms
i) What value would you expect for r2? -show your full working.
ii) For sockets on the ring, what would be the expected value of (R1+R2)
i) Multiplier = 2.5/1.5 = 1.67 so r2 = 1.67(r1) = 1.67(.45) = .75 ohms
ii) (R1+R2) = (r1 + r2) / 4 = (.45 + .75) / 4 = .3 ohms