3. Life as a PM: Planning and managing Flashcards

1
Q

Competencies for boundaryless careers?

A

Knowing What, Why, Where, Whom, When, How

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Characteristics of successful project managers

A
Skills 
•	analytical 
•	technical 
•	leadership and delegation 
•	time management 
•	problem-solving 
Attitudes
•	customer and goal focused 
•	accepts challenges and responsibility 
•	challenges waste 
•	integrity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

“The Eight Lookings”

A
  • forward/backward
  • internally/externally
  • inward/downward
  • outwards/upwards
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Ten principles focused on planning, managing and leading projects:
(Randolf and Posner, 1988)

A

Planning

  1. Set a clear project goal
  2. Determine the project objectives
  3. Establish checkpoints, activities, relationships and time estimates
  4. Draw a picture of the project schedule

Managing Projects

  1. Direct people individually and as a project team
  2. Reinforce commitment and excitement of the project team
  3. Keep everyone connected with the project informed
  4. Build agreements that vitalise team members
  5. Empower yourself and others on a project
  6. Encourage risk taking and creativity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What were the key reasons for the cost escalation of the Scottish Parliament?

A
  • The approved design was more complex than envisaged at the feasibility stage
  • Increase in construction cost estimates, almost half of which is attributable to a 47% increase in the total area of the building
  • “Whenever there was a conflict between quality and cost, quality was preferred”
  • Additional costs for landscaping and road re-alignment work
  • Shortfalls in procurement strategy
  • Inadequate risk allowance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Work Breakdown Structure (WBS)

A

Deconstruction of large projects into manageable chunks

overall project –> deliverables –> sub-deliverables –> work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Ground up and Top down costing?

A

Top down - costs fixed externally to project and pms allocated budgets to sub-projects.

Ground up - costs set by the project, pm collates estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Common mistakes in negotiations

A
  1. Neglecting the other sides problems
  2. Price over other elements
  3. Searching too hard for common ground
  4. Neglecting BATNAs
  5. Failing to correct for skewed vision/wrong assumptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Risk appetite

A

Amount of risk that an organisation is willing to take on in pursuit of value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Changing beliefs of project nature?

Crawford and Pollack, 2007

A
  • standardised to unique
    e. g. Projects are also differentiated as being either hard or soft. McElroy (1996) classified projects as either hard or soft based on the tangibility of proj- ect outputs, ease of estimation, and ambiguity of logical relationships.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly