2nd Chapter Flashcards
Capital for the required manufacturing and plant facilities
fixed capital investment
Capital required for the operation of the plant
working capital
Sum of the fixed-capital investment and the working capital
labeled as total capital investment
Capital required for the installed process equipment (e.g. vessels, reactors, columns, heat exchangers,
pumps, motors, fans, filters, etc.) with all auxiliaries needed.
Direct field costs (manufacturing fixed capital)
Capital required for construction overhead and for plant components which are not directly related to
the process operation.
Indirect field costs (nonmanufacturing fixed capital)
Cost indexes
Indexes can be applied to get a general cost estimate
Cost indexes are often used to extrapolate costs into the future and work fairly accurate if the
period considered is less than 10 years
Average installation cost of equipment
30%-70%
Piping costs
80 % of purchased-equipment
cost or 17 % of the fixed capital investment (FCI).
(Methods for the estimation of capital investment) Method A
Detailed-item estimate
Determination of each item of the fixed capital investment
Achieved accuracy: ± 5 %
(Methods for the estimation of capital investment)
Method B
Unit cost estimate
Based on detailed estimation of purchased equipment costs obtained from quotations or indexcorrected cost records and published information.
An accuracy of ± 10 - 20 % is achieved
(Methods for the estimation of capital investment)
Method C
Percentage of delivered-equipment cost
Based on the determination of the delivered equipment costs.
Usage of average percentage values → should be determined in accordance to the type of plant,
complexity, materials of construction, location etc.
expected accuracy of ± 20 - 30 %
(Methods for the estimation of capital investment)
Method D
Lang factors for approximation of capital investment
Method presented by H.J. Lang was based on a study of fourteen plant estimates of various sizes
and types, ranging from $100 000 to $15 000 000
Commonly used to obtain order of-magnitude cost estimates with
± 50 % .
(Methods for the estimation of capital investment)
Method E
Power factor estimate
Power factor x applied to plant capacity ratio.
C_new = C_ex * f_e * R^x
cost index = fe
R → capacity of the new plant divided by the capacity of existing plant
average power factor x has been obtained in the range of 0.6 to 0.7
(Methods for the estimation of capital investment)
Method F
Investment cost per unit of capacity
Method based on: Determination of the unit investment costs (for average conditions).
Division of costs by capacity → Fixed-capital investment per unit of annual production capacity
(Types of capital cost estimates) Class 1
Detailed estimates (± 5 %)