2.1.2 Cost Estimate Classifications Flashcards
1
primary parameter for the classification of estimates
1
maturity level of project definition upon which the estimate is based
purpose of the estimate
methodology used in development of the estimate
acuracy of the estimate
relative effort required to produce the estimate
1
ACCURACY RANGE
1
An expression of an estimate’s predicted closeness to final actual costs or time. Typicallyexpressed as high/low percentages by which actual results will be over and under the estimate along with the confidence interval these percentages represent
1
Allowance
1
For estimating, resources included in estimates to cover the cost of known but undefined requirements for an individual activity, work item, account or sub-account.
1
Contingency
1
An amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, or effect is uncertain and that experience shows will likely result, in aggregate, in additional costs
1
KNOWN-UNKNOWN
1
An identifiable quantity or value having variability or an identifiable condition lacking certainty
1
UNKNOWN-UNKNOWN
1
A quantity, value or condition that cannot be identified or foreseen, otherwise referred to as unknowable
1
The term “unit hours” refers to
1
Work hours per unit of production.
1
LEARNING CURVE
1
A graphic representation of the progress in production effectiveness as time passes
1
PROFITABILITY
1
A measure of the excess income over expenditure during a given period of time
1
PROFITABILITY ANALYSIS
1
The evaluation of the economics of a project, manufactured product, or service within a specific time frame.
1
VARIANCE
1
The difference between what was originally expected and what actually happened
1
The key areas are to be practice by the Cost Estimator
1
The key areas are: Ethics; Leadership; Information Management; Quality Management; Value Management; Health and Safety. If all of these are practiced by the Cost Estimator, there will be continuous improvement in the estimating process and the final project or process that is being produced.
1
What allows an ethical behavior, well develop database
1
Ethical behavior leads to a more harmonious society.
A well‐developed database leads to a quality estimate.
The input of cost estimating is important to value engineering to provide a more effective project.
The continuous use of the Deming Cycle (Plan‐Do‐Check‐Act) leads to better estimates.
1
CONCEPT PHASE
1
First phase of a project in which need is examined, alternatives are assessed, the goals and objectives of the project are established and a sponsor is identified
1
PARAMETRIC ESTIMATE
1
In estimating practice, describes estimating algorithms or cost estimating relationships that are highly probabilistic in nature