19 - Project Finance / Quantification and Costing (of Construction Works) / Design Economics and Cost Planning Flashcards
789 - What are the typical responsibilities of the cost manager on a construction project? (14)
Subject to the scope of service, typical responsibilities may include;
1) Manage risk allowance expenditure
2) Initiate action to avoid overspend
3) Prepare pricing documents for tendering
4) Evaluate and analyse tender bids
5) Prepare interim valuations
6) Value variations and compensation events
7) Assess the contractor’s financial claims
8) Negotiate and agree final accounts
9) Issue financial reports or statements
10) Provide initial cost advise on capital investment costs
11) Produce cost estimates and cost plans
12) Provide advice on whole life costs
13) Produce cost reports, estimates and forecasts
14) Prepare and maintain the cash flow forecast
790 - If you are producing estimates and cost plans, which measurement rules represent industry best practice for capital building and building maintenance works in the UK?
New Rules of Measurement (NRM)
791 - Can you name the 3 documents in the NRM suite? (3)
1) NRM 1 - Order of cost estimating and cost planning for capital building works
2) NRM 2 - Detailed measurement for building works
3) NRM 3 - Order of cost estimating and cost planning for building maintenance works
792 - Can you provide a brief overview of each of the NRM documents please? (3)
1) NRM 1 - Provides guidance on the quantification of building works for the purpose of preparing cost estimates and cost plans. It is the cornerstone of good cost management of construction projects. enabling more effective and accurate cost advice to be given to clients and other project team members, as well as facilitating better cost control.
2) NRM 2 - Is written mainly for the preparation of bills of quantities and quantified schedules of works, although the rules will be invaluable for designing and developing standard or bespoke schedules of rates.
3) NRM 3 - Gives guidance on the quantification and description of maintenance works for the purpose of preparing initial order of cost estimates. The rules also aid the procurement and cost control of maintenance works.
(See book for QR code links to documents)
793 - What is the structure of NRM 1? (5)
1) 1 - General introduction
2) 2 - Measurement rules for order of cost estimating
3) 3 - Measurement rules for cost planning
4) 4 - Tabulated rules of measurement for elemental cost planning
5) Appendices
794 - What is the structure of NRM 2? (4)
1) 1 - General introduction
2) 2 - Detailed measurement of building works
3) 3 - Rules of measurement for building works
4) Appendices
795 - What is the structure of NRM3? (7)
1) 1 - General introduction
2) 2 - Measurement rules for building maintenance works
3) 3 - Measurement rules for order of cost estimating
4) 4 - Cost planning of R and M works
5) 5 - Calculation of annualised costs for R and M works
6) 6 - Elemental cost planning
7) Appendices
796 - Why is it important to measure the works according to industry standards and best practice? (2)
1) To provide consistency and greater accuracy of pricing
2) To ensure that all parties price on the sae basis and therefore reduce the risk of disputes
797 - Is it mandatory for Chartered Surveyors to follow the procedures set out in NRM?
Following NRM is not a mandatory requirement. However, when an allegation of professional negligence is made against a surveyor, the adjudicator or court is likely to take account of the contents of any relevant guidance notes published by RICS in deciding whether the surveyor had acted with reasonable competence.
798 - What are the key headings for contractor preliminaries identified in NRM2? (19)
1) 1 - PRELIMINARIES
2) 1.1 - Employers requirements
3) 1.1.1 - Site accommodation
4) 1.1.2 - Site records
5) 1.1.3 - Completion and post completion requirements
6) 1.2 - Main contractors cost items
7) 1.2.1 - Management and staff
8) 1.2.2 - Site establishment
9) 1.2.3 - Temporary services
10) 1.2.5 - Safety and environmental protection
11) 1.2.6 - Control and protection
12) 1.2.7 - Mechanical plant
13) 1.2.8 - Temporary works
14) 1.2.9 - Site records
15) 1.2.10 - Completion and post completion requirements
16) 1.2.11 - Cleaning
17) 1.2.12 - Fees and charges
18) 1.2.13 - Site services
19) 1.2.14 - Insurance, bonds, guarantees and warranties
799 - How is risk dealt with under NRM?
NRM recommends that risk allowances are not a standard percentage, but a properly considered assessment of the risk, considering completeness of the design and other uncertainties such as the extent of site investigations undertaken.
800 - Can you tell me the 4 risk categories identified in NRM? (4)
1) Employer change risk
2) Employer other risk
3) Design development risk
4) Construction risk
801 - How does NRM define the ‘cost limit’ for the project?
NRM 1 definition - The maximum expenditure the client is prepared to make in relation to the completed building. Includes construction costs, the cost of professional services, certain other project costs, items required post completion and during its operation, and risk allowances
802 - How does NRM define the ‘base cost estimate’ for the project?
NRM 1 definition - An evolving estimate of known factors without any allowances for risk and uncertainty, or elements of inflation. The base cost estimate is the sum of the works cost estimate, the project and design team fees estimate, and the other development and project costs estimate
803 - What is an order of cost estimate?
NRM 1 definition - An estimate based on benchmark data for a similar type of project based on the clients strategic definition or initial brief. It’s purpose is to establish affordability of a proposed development for a client. It takes place prior to the preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process. Order of cost estimates are a method of cost prediction.
804 - Which RIBA stage is the order of cost estimate typically produced?
RIBA stage 1 - Preparation and Briefing
805 - What are the RIBA Stage of Work? (8)
1) Stage 0 - Strategic definition
2) Stage 1 - Preparation and briefing
3) Stage 2 - Concept design
4) Stage 3 - Spatial coordination
5) Stage 4 - Technical design
6) Stage 5 - Manufacturing and construction
7) Stage 6 - Handover
8) Stage 7 - Use
806 - What is the difference between an order of cost estimate and cost plan? (2)
1) An estimate provides a possible cost based on the employers requirements and is the initial phase of the cost planning process. The estimate is usually completed using m2 areas or functional units.
2) A cost plan is a more detailed elemental breakdown and shows how the costs are distributed across the project. A cost plan is an estimate based on a specific design.
807 - Can you explain the term ‘cost per functional unit’?
NRM 1 definition - The unit rate that, when multiplied by the number of functional units, gives the total building works estimate (i.e. works cost estimate minus main contractors preliminaries and main contractors overheads and profit). The total recommended cost limit (i.e. the cost limit, including inflation) can also be expressed as a cost per functional unit when reporting costs.
808 - What typical information should accompany an order of cost estimate? (10)
1) Covering letter
2) Executive summary
3) Cost limit
4) Specification notes
5) Assumptions
6) Exclusions
7) Drawings and other information upon which the estimate is based
8) A schedule of value enhancing options
9) Risk register
10) Cash flow information
809 - What is a cost plan?
NRM 1 definition - In the context of cost prediction, RICS professional statement, a cost plan is ‘an estimate based on a specific design.’ A statement showing an apportionment of an estimate of or an agreed budget between cost headings. This would not necessarily be in elemental form. Cost planning is a method of cost prediction.
810 - Other than predicting the final project cost, what other benefits does the cost plan provide to the project and project team? (2)
1) Designers are aware of the cost implications of their proposals which enables them to arrive at practical and balanced designs.
2) Provides information upon which the employer can make informed commercial decisions.
811 - Do you need a programme to complete the cost plan?
Preliminaries are typically presented as a weekly rate in developed cost plans, therefore, a programme or at least some high-level dates will be required.
The key information usually required is;
1) Design and tendering periods
2) Start on site date
3) Construction period
4) Completion date
812 - How do you structure an elemental cost plan?
NRM 1 recommends using the following structure;
(See book for diagram)