1.5 Basic contractual mechanisms and procedures at various stages of the contra Flashcards

1
Q

Client / Contractor Protection

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Give a list of mechanisms to protect the main contractor from the client.

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Give a list of mechanisms which protect the client from the main contractor?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How would a dispute be dealt with in the contract?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is meant by adjudication?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which party under the contract has a right to adjudicate?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is meant by arbitration?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Explain how provisions relating to Testing and opening up might benefit the client under a construction contract.

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you deal with defective work?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is meant by fluctuation provisions?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can you explain what is meant by contribution levy and tax fluctuations

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you explain what is meant by labour and materials cost and tax fluctuations

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How are fluctuations rates worked out?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is an advance payment? Why might the client wish to use one?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is an advance payment bond?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Can you tell me the advantages and disadvantages of using an advanced payment compared to an advanced payment bond?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Explain what is meant by retention

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Why is it beneficial to the client to use retention?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

At what RIBA stage will retention firstly need to be considered?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Explain the significance of retention at tender stage and how it may be incorporated into particular tender documents.

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a typical rate of retention?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Explain the process of releasing half then full retention.

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is an alternative to retention?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is a retention bond? Why might this be used?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What might be a typical rate of retention?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is the rectification (or defects) period?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is a typical timescale for a rectification period?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Why is it beneficial to the client to include a rectification period under the contract?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Under a construction contract what contractual provisions may be in place to deal with materials off site?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Explain what a Performance Bond is.

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

At what RIBA stage will a Performance Bond firstly need to be considered?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

How does the use of a Performance Bond affect certain processes at tender stage?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is a typical value of a Performance Bond?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

How will the client go about claiming a Performance Bond?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Explain what a Parent Company Guarantee is.

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What are the benefits to the client of using a Parent Company Guarantee?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

At what RIBA stage do we firstly need to consider Parent Company Guarantees?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

How is a Parent Company Guarantee triggered? What are step-in rights?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Can you tell me the advantages and disadvantages of using a performance bond compared to a parent company guarantee?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

What do you understand about the Third Parties Rights Act?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What are the disadvantages of using the Third Parties Rights Act?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

How might a construction contract be suspended?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What is force majeure?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

How can a construction contract be terminated by the contractor?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

How can a construction contract be terminated by the employer?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

What are LADs? How are they calculated?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

What is the process for deducting Liquidated Damages?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Can Liquidated Damages be challenged by the contractor?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

What provisions are within the JCT SBC to protect the client financially should the contractor become insolvent?

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Can you tell me some of the reasons why an employer may determine the contract? What are the procedures in relation to this?

A

1.5

51
Q

What is acceleration?

A

1.5

52
Q

What is the process of acceleration?

A

1.5

53
Q

What do we mean by a claim for Loss & Expense?

A

1.5

54
Q

Why is it beneficial to the contractor to be able to claim for Loss & Expense?

A

1.5

55
Q

What are the general heads of claims for loss & expense?

A

1.5

56
Q

Give an example of the procedures and timescales which may govern a claim for loss & expense under a given construction contract.

A

1.5

57
Q

What is an Extension of Time?

A

1.5

58
Q

For what reasons may a contractor claim for an Extension of Time?

A

1.5

59
Q

Why is it beneficial to the contractor to be able to claim for an Extension of Time?

A

1.5

60
Q

Give an example of the procedures and timescales which may govern an Extension of Time claim under a given construction contract.

A

1.5

61
Q

Can you explain what a Collateral Warranty is?

A

1.5

62
Q

Why is it beneficial to the client to use a Collateral Warranty?

A

1.5

63
Q

At what RIBA stage do we firstly need to consider a collateral warranty?

A

1.5

64
Q

How is a Collateral Warranty triggered?

A

1.5

65
Q

Timescales

A

1.5

66
Q

Give an example of mechanisms which place timescales on parties named under a construction contract

A

1.5

67
Q

Commencement & Completion

A

1.5

68
Q

What do you understand by sectional completion?

A

1.5

69
Q

What contractual considerations are required if the works are divided into sections?

A

1.5

70
Q

What do you understand by partial possession?

A

1.5

71
Q

What things do you have to consider if the client takes partial possession of a site?

A

1.5

72
Q

How does partial possession effect LADs and insurances as set out in the contract?

A

1.5

73
Q

What are the advantages and disadvantages of Partial Possession?

A

1.5

74
Q

What is the difference between sectional completion and partial possession?

A

1.5

75
Q

What is meant by deferment of possession? How long might deferment of possession typically be?

A

1.5

76
Q

What is an Extension of Time? How is it granted?

A

1.5

77
Q

What is meant by a relevant event? Give some examples.

A

1.5

78
Q

Sub-contractors

A

1.5

79
Q

What are the different types of sub-contractors which may be named under a construction contract?

A

1.5

80
Q

What are the contractual implications of using domestic sub-contractors?

A

1.5

81
Q

What are the contractual implications of using a named sub-contractor?

A

1.5

82
Q

Variations / CEs

A

1.5

83
Q

What constitutes a variation under a JCT contract?

A

1.5

84
Q

What are the rules for valuing variations under JCT?

A

1.5

85
Q

If you are using JCT in relation to a variation how can you make it so that time and cost for implications are agreed upfront?

A

1.5

86
Q

What is a Schedule 2 variation quotation? Why might this be beneficial to the client?

A

1.5

87
Q

What constitutes a Compensation Event under a NEC contract?

A

1.5

88
Q

What are the rules for valuing Compensation Events under NEC?

A

1.5

89
Q

What is the difference between valuing variations under a JCT compared to an NEC contract?

A

1.5

90
Q

Explain what a verbal instruction is.

A

1.5

91
Q

Is a verbal instruction applicable to both JCT and NEC?

A

1.5

92
Q

Payment

A

1.5

93
Q

What are the different types of payment mechanisms used under various construction contracts?

A

1.5

94
Q

Explain the procedures and timescales which govern interim valuations under a JCT SBC.

A

1.5

95
Q

How would the roles in the interim valuation process (in relation to the certifier and the valuer) differ under a JCT SBC and a JCT D&B Contract?

A

1.5

96
Q

What do we mean by stage payments?

A

1.5

97
Q

What do we mean by milestone payments?

A

1.5

98
Q

What do we mean by payment against an activity schedule?

A

1.5

99
Q

What do we mean by Valuation of works done to date on site (third-party certification)?

A

1.5

100
Q

What is your understanding of a pay less notice? When might the client issue one?

A

1.5

101
Q

Which timescales are governed by statute in relation to interim valuations?

A

1.5

102
Q

If the contract did not state any rules for interim valuations and stage payments how would you know which rules to follow?

A

1.5

103
Q

Insurances

A

1.5

104
Q

What insurances are likely to be included under a construction contract?

A

1.5

105
Q

Can you explain what Employers Liability insurance is?

A

1.5

106
Q

Can you explain what Public Liability insurance is?

A

1.5

107
Q

Can you explain what insurance of the works and existing structures is? How is this dealt with under a JCT contract?

A

1.5

108
Q

What other optional insurances might be used under a construction contract?

A

1.5

109
Q

Can you tell me about Professional Indemnity Insurance?

A

1.5

110
Q

Other

A

1.5

111
Q

What are the implications if an Employer is deemed to be a residential occupier within the meaning of section 106 of the Housing Grants Construction and Regeneration Act 1996?

A

1.5

112
Q

What is an information release schedule and why might the client choose to provide one?

A

1.5

113
Q

What are the implications if an Employer is considered a ‘contractor’ for the purposes of the Construction Industry (CIS) scheme?

A

1.5

114
Q

What is the significance of inserting a Base Date into a construction contract?

A

1.5

115
Q

Under a construction contract what is meant by listed items? How are these significant?

A

1.5

116
Q

Why might you have a bond for a listed item?

A

1.5

117
Q

Under a construction contract what is meant by ‘assignment of rights’?

A

1.5

118
Q

What is the difference between executing a contract underhand or as a deed?

A

1.5

119
Q

For NEC contracts what is the mechanism for amending the terms?

A

1.5

120
Q

What is your understanding of Practical Completion? What needs to be in place to grant Practical Completion?

A

1.5

121
Q

What obligations do the Contractor commit to after Practical Completion?

A

1.5

122
Q

Explain the process and timescales in relation to interim valuations under JCT and NEC

A

1.5

123
Q

Explain the process of Early Warning Notices through to instructing a Compensation Even under an NEC contract

A

1.5

124
Q

What is the Joint Fire Code and when does it apply to a contract? What effect does it have?

A

1.5