1.5 Basic contractual mechanisms and procedures at various stages of the contra Flashcards
Client / Contractor Protection
1.5
Give a list of mechanisms to protect the main contractor from the client.
1.5
Give a list of mechanisms which protect the client from the main contractor?
1.5
How would a dispute be dealt with in the contract?
1.5
What is meant by adjudication?
1.5
Which party under the contract has a right to adjudicate?
1.5
What is meant by arbitration?
1.5
Explain how provisions relating to Testing and opening up might benefit the client under a construction contract.
1.5
How do you deal with defective work?
1.5
What is meant by fluctuation provisions?
1.5
Can you explain what is meant by contribution levy and tax fluctuations
1.5
Can you explain what is meant by labour and materials cost and tax fluctuations
1.5
How are fluctuations rates worked out?
1.5
What is an advance payment? Why might the client wish to use one?
1.5
What is an advance payment bond?
1.5
Can you tell me the advantages and disadvantages of using an advanced payment compared to an advanced payment bond?
1.5
Explain what is meant by retention
1.5
Why is it beneficial to the client to use retention?
1.5
At what RIBA stage will retention firstly need to be considered?
1.5
Explain the significance of retention at tender stage and how it may be incorporated into particular tender documents.
1.5
What is a typical rate of retention?
1.5
Explain the process of releasing half then full retention.
1.5
What is an alternative to retention?
1.5
What is a retention bond? Why might this be used?
1.5
What might be a typical rate of retention?
1.5
What is the rectification (or defects) period?
1.5
What is a typical timescale for a rectification period?
1.5
Why is it beneficial to the client to include a rectification period under the contract?
1.5
Under a construction contract what contractual provisions may be in place to deal with materials off site?
1.5
Explain what a Performance Bond is.
1.5
At what RIBA stage will a Performance Bond firstly need to be considered?
1.5
How does the use of a Performance Bond affect certain processes at tender stage?
1.5
What is a typical value of a Performance Bond?
1.5
How will the client go about claiming a Performance Bond?
1.5
Explain what a Parent Company Guarantee is.
1.5
What are the benefits to the client of using a Parent Company Guarantee?
1.5
At what RIBA stage do we firstly need to consider Parent Company Guarantees?
1.5
How is a Parent Company Guarantee triggered? What are step-in rights?
1.5
Can you tell me the advantages and disadvantages of using a performance bond compared to a parent company guarantee?
1.5
What do you understand about the Third Parties Rights Act?
1.5
What are the disadvantages of using the Third Parties Rights Act?
1.5
How might a construction contract be suspended?
1.5
What is force majeure?
1.5
How can a construction contract be terminated by the contractor?
1.5
How can a construction contract be terminated by the employer?
1.5
What are LADs? How are they calculated?
1.5
What is the process for deducting Liquidated Damages?
1.5
Can Liquidated Damages be challenged by the contractor?
1.5
What provisions are within the JCT SBC to protect the client financially should the contractor become insolvent?
1.5
Can you tell me some of the reasons why an employer may determine the contract? What are the procedures in relation to this?
1.5
What is acceleration?
1.5
What is the process of acceleration?
1.5
What do we mean by a claim for Loss & Expense?
1.5
Why is it beneficial to the contractor to be able to claim for Loss & Expense?
1.5
What are the general heads of claims for loss & expense?
1.5
Give an example of the procedures and timescales which may govern a claim for loss & expense under a given construction contract.
1.5
What is an Extension of Time?
1.5
For what reasons may a contractor claim for an Extension of Time?
1.5
Why is it beneficial to the contractor to be able to claim for an Extension of Time?
1.5
Give an example of the procedures and timescales which may govern an Extension of Time claim under a given construction contract.
1.5
Can you explain what a Collateral Warranty is?
1.5
Why is it beneficial to the client to use a Collateral Warranty?
1.5
At what RIBA stage do we firstly need to consider a collateral warranty?
1.5
How is a Collateral Warranty triggered?
1.5
Timescales
1.5
Give an example of mechanisms which place timescales on parties named under a construction contract
1.5
Commencement & Completion
1.5
What do you understand by sectional completion?
1.5
What contractual considerations are required if the works are divided into sections?
1.5
What do you understand by partial possession?
1.5
What things do you have to consider if the client takes partial possession of a site?
1.5
How does partial possession effect LADs and insurances as set out in the contract?
1.5
What are the advantages and disadvantages of Partial Possession?
1.5
What is the difference between sectional completion and partial possession?
1.5
What is meant by deferment of possession? How long might deferment of possession typically be?
1.5
What is an Extension of Time? How is it granted?
1.5
What is meant by a relevant event? Give some examples.
1.5
Sub-contractors
1.5
What are the different types of sub-contractors which may be named under a construction contract?
1.5
What are the contractual implications of using domestic sub-contractors?
1.5
What are the contractual implications of using a named sub-contractor?
1.5
Variations / CEs
1.5
What constitutes a variation under a JCT contract?
1.5
What are the rules for valuing variations under JCT?
1.5
If you are using JCT in relation to a variation how can you make it so that time and cost for implications are agreed upfront?
1.5
What is a Schedule 2 variation quotation? Why might this be beneficial to the client?
1.5
What constitutes a Compensation Event under a NEC contract?
1.5
What are the rules for valuing Compensation Events under NEC?
1.5
What is the difference between valuing variations under a JCT compared to an NEC contract?
1.5
Explain what a verbal instruction is.
1.5
Is a verbal instruction applicable to both JCT and NEC?
1.5
Payment
1.5
What are the different types of payment mechanisms used under various construction contracts?
1.5
Explain the procedures and timescales which govern interim valuations under a JCT SBC.
1.5
How would the roles in the interim valuation process (in relation to the certifier and the valuer) differ under a JCT SBC and a JCT D&B Contract?
1.5
What do we mean by stage payments?
1.5
What do we mean by milestone payments?
1.5
What do we mean by payment against an activity schedule?
1.5
What do we mean by Valuation of works done to date on site (third-party certification)?
1.5
What is your understanding of a pay less notice? When might the client issue one?
1.5
Which timescales are governed by statute in relation to interim valuations?
1.5
If the contract did not state any rules for interim valuations and stage payments how would you know which rules to follow?
1.5
Insurances
1.5
What insurances are likely to be included under a construction contract?
1.5
Can you explain what Employers Liability insurance is?
1.5
Can you explain what Public Liability insurance is?
1.5
Can you explain what insurance of the works and existing structures is? How is this dealt with under a JCT contract?
1.5
What other optional insurances might be used under a construction contract?
1.5
Can you tell me about Professional Indemnity Insurance?
1.5
Other
1.5
What are the implications if an Employer is deemed to be a residential occupier within the meaning of section 106 of the Housing Grants Construction and Regeneration Act 1996?
1.5
What is an information release schedule and why might the client choose to provide one?
1.5
What are the implications if an Employer is considered a ‘contractor’ for the purposes of the Construction Industry (CIS) scheme?
1.5
What is the significance of inserting a Base Date into a construction contract?
1.5
Under a construction contract what is meant by listed items? How are these significant?
1.5
Why might you have a bond for a listed item?
1.5
Under a construction contract what is meant by ‘assignment of rights’?
1.5
What is the difference between executing a contract underhand or as a deed?
1.5
For NEC contracts what is the mechanism for amending the terms?
1.5
What is your understanding of Practical Completion? What needs to be in place to grant Practical Completion?
1.5
What obligations do the Contractor commit to after Practical Completion?
1.5
Explain the process and timescales in relation to interim valuations under JCT and NEC
1.5
Explain the process of Early Warning Notices through to instructing a Compensation Even under an NEC contract
1.5
What is the Joint Fire Code and when does it apply to a contract? What effect does it have?
1.5