1409: PPBE Process Flashcards

1
Q

What is the DODs resource management system?

A

The planning, programming, budgeting and execution (PPBE) process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the means of providing budget authority for program funding?

A

An appropriation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the five major appropriation categories of funds Congress provides DoD with ?

A
Research, Development, Test, and Evaluation (RDT&E) 
Procurement 
Operation and Maintenance (O&M) 
Military Personnel (MILPERS) 
Military Construction (MILCON)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Research Developement Test & Evaluation(RDT&E)?

A

2 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Procurement?
What about for ship building and conversion, Navy (SCN)

A

3 years

5years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Operations and Maintenance?

A

1 Year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Military Personnel (MILPERS)?

A

1 year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Military Construction (MILCON)?

A

5 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the three key concepts of the Full funding policy?

A

Usable End Items
12-Month Delivery Period
Budget for Fiscal Year of Contract Award

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does CAPE stand for?

A

Cost Analysis and Program Evaluation (CAPE)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the four reasons programs lose funding?

A

Scarcity of financial resources
Questionable need for the program
Excessive risk
Budget review issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly