1409: PPBE Process Flashcards
What is the DODs resource management system?
The planning, programming, budgeting and execution (PPBE) process
What is the means of providing budget authority for program funding?
An appropriation
What are the five major appropriation categories of funds Congress provides DoD with ?
Research, Development, Test, and Evaluation (RDT&E) Procurement Operation and Maintenance (O&M) Military Personnel (MILPERS) Military Construction (MILCON)
Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Research Developement Test & Evaluation(RDT&E)?
2 years
Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Procurement?
What about for ship building and conversion, Navy (SCN)
3 years
5years
Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Operations and Maintenance?
1 Year
Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Military Personnel (MILPERS)?
1 year
Each appropriation has a legal time limit, or obligation period, within which funds can be obligated (i.e., put on contract).
What is the obligation period for Military Construction (MILCON)?
5 years
What are the three key concepts of the Full funding policy?
Usable End Items
12-Month Delivery Period
Budget for Fiscal Year of Contract Award
What does CAPE stand for?
Cost Analysis and Program Evaluation (CAPE)
What are the four reasons programs lose funding?
Scarcity of financial resources
Questionable need for the program
Excessive risk
Budget review issues